TxDOT contract A00216492 bid tabulation
METAL BEAM GUARD FENCE REPAIR, US0096 (VARIOUS LOCATIONS WITHIN THE SHELBY to SHELBY COUNTY MAINTENANCE SECTION). Let by Texas DOT on July 30, 2025, Shelby, Lufkin District. 4 bids received; low bid $138,118 by Austin Barricade Company, L.L.C., -15% against the engineer's estimate of $161,949.
- Owner
- Texas DOT
- Letting
- 30 JUL 2025
- Pay items
- 45
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Austin Barricade Company, L.L.C. | $138,118 | Low | -15% |
| 2 | Above All Contracting LLC | $156,341 | +13% | -3.0% |
| 3 | Ace Contractors, Inc. | $168,485 | +22% | +4.0% |
| 4 | Rhino Equity, LLC | $169,552 | +23% | +5.0% |
Engineer's estimate: $161,949.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Austin Barricade Company, L.L.C. | 2. Above All Contracting LLC | 3. Ace Contractors, Inc. | 4. Rhino Equity, LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (curb) (104-7016) | LF | 5 | $1,850.00 | $10.00 | $50.00 | $5.00 | $1.00 |
| 2 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 5 | $50.00 | $50.00 | $50.00 | $1.00 | $50.00 |
| 3 | Concrete structure repair (standard) (429-7009) | SF | 5 | $100.00 | $50.00 | $50.00 | $50.00 | $50.00 |
| 4 | Rail (type T631) (450-7020) | LF | 25 | $50.00 | $50.00 | $75.00 | $80.00 | $40.00 |
| 5 | Rail (type T631LS) (450-7021) | LF | 10 | $10.00 | $50.00 | $75.00 | $1.00 | $50.00 |
| 6 | Mobilization (callout) (500-7002) | EACH | 20 | $750.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 7 | TMA (stationary) (505-7001) | DAY | 20 | $150.00 | $3,000.00 | $1,500.00 | $1,600.00 | $3,500.00 |
| 8 | Metal W-beam guard fence (timber post) (540-7001) | LF | 300 | $20.00 | $15.00 | $35.00 | $20.00 | $20.00 |
| 9 | Metal beam guard fence trans (thrie-beam) (540-7005) | EACH | 2 | $1,250.00 | $900.00 | $1,500.00 | $1,500.00 | $500.00 |
| 10 | Metal beam guard fence trans (T101) (540-7007) | EACH | 2 | $500.00 | $250.00 | $100.00 | $25.00 | $300.00 |
| 11 | Short radius (28") (540-7013) | LF | 15 | $1.00 | $55.00 | $50.00 | $1.00 | $40.00 |
| 12 | Driveway terminal anchor section (540-7014) | EACH | 2 | $50.00 | $100.00 | $1.00 | $1.00 | $50.00 |
| 13 | Downstream anchor terminal section (540-7015) | EACH | 1 | $500.00 | $1,350.00 | $1,500.00 | $25.00 | $500.00 |
| 14 | Metal W - beam guard fence (low fill culvert) (540-7018) | LF | 15 | $1.00 | $55.00 | $1.00 | $30.00 | $100.00 |
| 15 | Metal beam guard fence (long span system) (540-7027) | EACH | 15 | $25.00 | $50.00 | $200.00 | $30.00 | $350.00 |
| 16 | Terminal anchor section (540-7041) | EACH | 1 | $10.00 | $100.00 | $500.00 | $1.00 | $200.00 |
| 17 | Remove metal beam guard fence (542-7001) | LF | 800 | $3.00 | $0.10 | $3.00 | $0.50 | $3.00 |
| 18 | Remove terminal anchor section (542-7002) | EACH | 2 | $50.00 | $100.00 | $1.00 | $0.50 | $1.00 |
| 19 | Remove downstream anchor terminal (542-7003) | EACH | 5 | $100.00 | $100.00 | $1.00 | $1.00 | $25.00 |
| 20 | RM metal beam guard fence trans (thrie-beam) (542-7004) | EACH | 2 | $10.00 | $1.00 | $1.00 | $1.00 | $25.00 |
| 21 | Guardrail end treatment (install) (544-7001) | EACH | 5 | $500.00 | $1,000.00 | $500.00 | $250.00 | $2,900.00 |
| 22 | Guardrail end treatment (move & reset) (544-7002) | EACH | 2 | $1.00 | $100.00 | $100.00 | $100.00 | $250.00 |
| 23 | Crash cushion attenuator (remove) (545-7004) | EACH | 1 | $1,000.00 | $550.00 | $1,000.00 | $500.00 | $750.00 |
| 24 | Install delineator assembly (D-SW)SZ 1(BRF)GF1 (BI) (658-7016) | EACH | 5 | $10.00 | $50.00 | $30.00 | $20.00 | $50.00 |
| 25 | Install object marker assembly (OM-1)(WFLX)GND (658-7054) | EACH | 1 | $40.00 | $50.00 | $30.00 | $45.00 | $50.00 |
| 26 | Replace rail element (W-beam) (770-7001) | LF | 800 | $40.00 | $22.00 | $40.00 | $45.00 | $20.00 |
| 27 | Repl rail elmnt(thrie-BM trans to W-BM) (770-7003) | EACH | 5 | $50.00 | $100.00 | $1.00 | $50.00 | $200.00 |
| 28 | Replace timber post W/O concrete FND (770-7006) | EACH | 15 | $75.00 | $100.00 | $60.00 | $100.00 | $200.00 |
| 29 | Replace steel post W/O concrete FND (770-7007) | EACH | 15 | $60.00 | $1.00 | $75.00 | $1.00 | $50.00 |
| 30 | Replace timber post W/ concrete FND (770-7008) | EACH | 15 | $75.00 | $100.00 | $60.00 | $100.00 | $40.00 |
| 31 | Realign posts (770-7010) | EACH | 50 | $45.00 | $1.00 | $30.00 | $40.00 | $5.00 |
| 32 | Repair of terminal anchors posts (770-7011) | EACH | 5 | $2.00 | $1.00 | $1.00 | $1.00 | $15.00 |
| 33 | Replace terminal anchor posts (770-7012) | EACH | 5 | $5.00 | $1.00 | $1.00 | $1.00 | $100.00 |
| 34 | Rem obsolete get & repl W/ SGT (770-7013) | EACH | 10 | $6,000.00 | $3,000.00 | $4,500.00 | $6,000.00 | $2,900.00 |
| 35 | Repl single gdrail terminal impact head (770-7015) | EACH | 2 | $750.00 | $850.00 | $750.00 | $1,000.00 | $500.00 |
| 36 | Replace single gdrail terminal post (770-7017) | EACH | 5 | $150.00 | $200.00 | $100.00 | $200.00 | $600.00 |
| 37 | Replace blockout (770-7018) | EACH | 20 | $50.00 | $1.00 | $100.00 | $25.00 | $200.00 |
| 38 | Repair steel post with base plate (770-7019) | EACH | 2 | $40.00 | $100.00 | $200.00 | $200.00 | $50.00 |
| 39 | Reset SGT impact head (770-7020) | EACH | 10 | $200.00 | $1.00 | $100.00 | $200.00 | $50.00 |
| 40 | Replace SGT object marker (770-7021) | EACH | 5 | $35.00 | $1.00 | $50.00 | $20.00 | $25.00 |
| 41 | Replace SGT cable anchor (770-7022) | EACH | 2 | $1.00 | $1.00 | $100.00 | $1.00 | $75.00 |
| 42 | Replace SGT cable assembly (770-7023) | EACH | 2 | $50.00 | $1.00 | $100.00 | $100.00 | $75.00 |
| 43 | Replace SGT strut (770-7024) | EACH | 2 | $40.00 | $1.00 | $100.00 | $1.00 | $75.00 |
| 44 | Repair (wide quad) (774-7032) | LF | 5 | $2,000.00 | $500.00 | $1,000.00 | $2,000.00 | $200.00 |
| 45 | Repair (T101RC) (776-7008) | LF | 60 | $35.00 | $25.00 | $75.00 | $70.00 | $30.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of July 30, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.