TxDOT contract A00218069 bid tabulation
Install Traffic Signal, FM 550 (at Rabbit Ridge to in Rockwall). Let by Texas DOT on April 7, 2026, Rockwall, Dallas District. 8 bids received; low bid $2,341,217 by O. Trevino Construction, LLC, +7.9% against the engineer's estimate of $2,169,620.
- Owner
- Texas DOT
- Letting
- 07 APR 2026
- Pay items
- 100
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | O. Trevino Construction, LLC | $2,341,217 | Low | +8.0% |
| 2 | Ed Bell Construction Company | $2,619,501 | +12% | +21% |
| 3 | Durable Specialties, Inc. | $2,759,205 | +18% | +27% |
| 4 | Yunex LLC | $2,824,756 | +21% | +30% |
| 5 | Jagoe-Public Company | $2,920,901 | +25% | +35% |
| 6 | Select Maintenance, L.L.C. | $2,996,825 | +28% | +38% |
| 7 | Elecnor Belco Electric, Inc. | $3,002,028 | +28% | +38% |
| 8 | Highway Intelligent Traffic Solutions, Inc. | $3,364,410 | +44% | +55% |
Engineer's estimate: $2,169,620.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. O. Trevino Construction, LLC | 2. Ed Bell Construction Company | 3. Durable Specialties, Inc. | 4. Yunex LLC | 5. Jagoe-Public Company | 6. Select Maintenance, L.L.C. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 17.93 | $750.00 | $7,435.00 | $9,450.00 | $2,500.00 | $2,953.34 | $1,000.00 | $9,000.00 |
| 2 | Removing concrete (driveways) (104-7011) | SY | 496 | $20.00 | $50.00 | $26.25 | $65.00 | $53.34 | $70.00 | $40.00 |
| 3 | Remove (0"-6") TRT/untrt base & asphalt pavement (105-7046) | SY | 463 | $14.00 | $35.00 | $15.75 | $10.00 | $10.00 | $55.00 | $16.00 |
| 4 | Removing stab base and asphalt pavement(0"-16") (105-7129) | SY | 327 | $15.00 | $75.00 | $26.25 | $18.00 | $14.45 | $40.00 | $16.00 |
| 5 | Excavation (roadway) (110-7001) | CY | 4 | $20.00 | $225.00 | $210.00 | $280.00 | $222.23 | $600.00 | $500.00 |
| 6 | Subgr widen (OC) (112-7001) | STA | 17.93 | $300.00 | $2,400.00 | $1,050.00 | $5,000.00 | $4,083.34 | $1,600.00 | $900.00 |
| 7 | Embankment (final)(OC)(type C) (132-7005) | CY | 286 | $21.00 | $100.00 | $105.00 | $90.00 | $72.23 | $100.00 | $90.00 |
| 8 | Backfill (type A or B) (134-7004) | STA | 17.93 | $200.00 | $400.00 | $420.00 | $120.00 | $308.22 | $850.00 | $900.00 |
| 9 | Road grader work (ord comp) (152-7001) | STA | 17.93 | $75.00 | $150.00 | $420.00 | $150.00 | $122.23 | $60.00 | $900.00 |
| 10 | Block sodding (162-7002) | SY | 8,937 | $10.00 | $4.85 | $4.86 | $9.00 | $5.00 | $5.00 | $6.75 |
| 11 | Drill seed (temporary_warm_cool) (164-7015) | SY | 2,980 | $1.00 | $0.28 | $0.22 | $1.50 | $0.39 | $0.40 | $0.35 |
| 12 | Vegetative watering (168-7001) | TGL | 1,775 | $2.50 | $17.25 | $2.10 | $60.00 | $28.57 | $1.00 | $15.00 |
| 13 | FL BS (compacted in place)(type D GR 1-2) (12") (247-7125) | SY | 2,271 | $29.00 | $42.00 | $40.00 | $88.00 | $70.28 | $55.00 | $45.00 |
| 14 | Prime coat(MC-30 or AE-P) (310-7013) | GAL | 684 | $4.75 | $7.80 | $8.60 | $7.00 | $22.23 | $5.50 | $9.00 |
| 15 | SP mixes SP-B PG64-22 (344-7001) | TON | 502 | $120.00 | $172.00 | $183.93 | $115.00 | $211.39 | $150.00 | $175.00 |
| 16 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 972 | $130.00 | $150.00 | $161.47 | $195.00 | $185.84 | $150.00 | $185.00 |
| 17 | Tack coat (344-7077) | GAL | 883 | $4.00 | $8.00 | $8.60 | $3.00 | $1.67 | $4.00 | $5.00 |
| 18 | Flexible pavement structure repair(8") (351-7007) | SY | 558 | $98.00 | $140.00 | $148.57 | $90.00 | $122.23 | $120.00 | $125.00 |
| 19 | Plane & text asphalt concrete pavement(0" to 3") (354-7003) | SY | 6,085 | $3.00 | $4.00 | $4.25 | $18.00 | $22.23 | $5.00 | $4.00 |
| 20 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 42 | $245.00 | $268.18 | $685.00 | $416.57 | $310.00 | $350.00 | |
| 21 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 146 | $620.00 | $270.00 | $296.19 | $715.00 | $520.79 | $340.00 | $425.00 |
| 22 | Drilled shaft (traffic signal pole) (48 in) (416-7046) | LF | 44 | $850.00 | $500.00 | $544.27 | $890.00 | $857.32 | $615.00 | $525.00 |
| 23 | RC pipe (CL III)(18 in) (464-7003) | LF | 76 | $61.00 | $130.00 | $157.50 | $190.00 | $151.12 | $70.00 | $125.00 |
| 24 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 4 | $1,050.00 | $1,250.00 | $1,575.00 | $3,800.00 | $3,111.12 | $1,650.00 | $2,000.00 |
| 25 | Removing structure (set) (496-7004) | EACH | 4 | $200.00 | $300.00 | $315.00 | $400.00 | $333.34 | $200.00 | $650.00 |
| 26 | Removing structure (pipe) (496-7037) | EACH | 2 | $200.00 | $900.00 | $840.00 | $400.00 | $333.34 | $350.00 | $725.00 |
| 27 | Mobilization (500-7001) | LS | 1 | $200,000 | $231,350 | $247,000 | $115,000 | $228,489 | $324,000 | $300,000 |
| 28 | Barricades, signs and traffic handling (502-7001) | MO | 7 | $16,000 | $15,000 | $31,500 | $9,000.00 | $9,355.56 | $40,000 | $36,000 |
| 29 | Portable changeable message sign (503-7001) | DAY | 30 | $175.00 | $157.50 | $70.00 | $83.34 | $75.00 | $50.00 | |
| 30 | Portable changeable message sign (503-7002) | EACH | 17 | $2,000.00 | $1,000.00 | $1,050.00 | $70.00 | $18,678 | $10,000 | $500.00 |
| 31 | TMA (stationary) (505-7001) | DAY | 210 | $225.00 | $175.00 | $157.50 | $450.00 | $240.74 | $275.00 | $100.00 |
| 32 | TMA (mobile operation) (505-7003) | DAY | 10 | $275.00 | $695.00 | $1,050.00 | $800.00 | $400.00 | $275.00 | $500.00 |
| 33 | Temporary sediment control fence (install) (506-7039) | LF | 97 | $4.55 | $4.85 | $10.50 | $18.00 | $4.45 | $4.82 | $7.00 |
| 34 | Temporary sediment control fence (remove) (506-7041) | LF | 97 | $1.00 | $1.95 | $5.25 | $5.00 | $1.67 | $1.81 | $1.00 |
| 35 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 84 | $7.00 | $7.80 | $10.50 | $2.00 | $6.39 | $6.93 | $7.00 |
| 36 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 200 | $6.00 | $8.75 | $15.75 | $3.00 | $6.95 | $7.53 | $7.00 |
| 37 | Biodegradable erosion control logs (remove) (506-7046) | LF | 284 | $1.50 | $1.95 | $5.25 | $1.00 | $1.34 | $1.45 | $1.00 |
| 38 | Driveways (concrete) (hes) (530-7007) | SY | 500 | $125.00 | $135.00 | $157.50 | $185.00 | $150.00 | $135.00 | $160.00 |
| 39 | Driveways (ACP) (530-7010) | SY | 528 | $70.00 | $110.00 | $96.09 | $145.00 | $155.56 | $125.00 | $120.00 |
| 40 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 3,346 | $0.25 | $2.20 | $0.55 | $2.00 | $0.56 | $0.60 | $2.60 |
| 41 | Mailbox install-S (TWW-post) type 4 (560-7008) | EACH | 5 | $300.00 | $550.00 | $525.00 | $300.00 | $361.12 | $427.95 | $300.00 |
| 42 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 188 | $27.00 | $19.00 | $20.53 | $24.00 | $35.05 | $23.03 | $25.00 |
| 43 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 171 | $35.00 | $20.50 | $22.53 | $26.00 | $28.25 | $25.27 | $25.00 |
| 44 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 364 | $40.00 | $28.75 | $31.66 | $49.00 | $48.50 | $35.50 | $45.00 |
| 45 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 66 | $38.00 | $22.00 | $24.34 | $29.00 | $51.52 | $27.29 | $25.00 |
| 46 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 227 | $60.00 | $30.50 | $33.46 | $51.00 | $51.63 | $37.53 | $45.00 |
| 47 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 102 | $30.00 | $20.00 | $21.87 | $25.00 | $18.55 | $24.52 | $25.00 |
| 48 | Electrical conductor (no.12) insulated (620-7004) | LF | 640 | $2.50 | $2.25 | $2.48 | $1.00 | $2.05 | $2.78 | $1.50 |
| 49 | Electrical conductor (no.8) insulated (620-7008) | LF | 3,952 | $3.00 | $3.00 | $3.31 | $2.00 | $2.56 | $3.71 | $2.00 |
| 50 | Electrical conductor (no.6) bare (620-7009) | LF | 861 | $3.00 | $3.25 | $3.54 | $3.00 | $2.69 | $3.97 | $2.10 |
| 51 | Electrical conductor (no.6) insulated (620-7010) | LF | 500 | $3.50 | $3.75 | $4.19 | $3.00 | $3.07 | $4.70 | $2.40 |
| 52 | Electrical conductor (no.4) insulated (620-7012) | LF | 306 | $4.00 | $4.60 | $5.06 | $4.00 | $3.58 | $5.68 | $3.20 |
| 53 | Ground box type C (162911)W/apron (624-7006) | EACH | 7 | $2,000.00 | $1,650.00 | $1,782.24 | $2,300.00 | $2,994.45 | $1,998.60 | $2,500.00 |
| 54 | Ground box type D (162922)W/apron (624-7008) | EACH | 7 | $2,100.00 | $1,650.00 | $1,796.86 | $2,400.00 | $3,005.56 | $2,014.99 | $2,500.00 |
| 55 | Zinc-coat steel wire strand (3/16") (625-7001) | LF | 1,942 | $2.25 | $2.47 | $5.00 | $5.88 | $2.77 | $5.00 | |
| 56 | Zinc-coat steel wire strand (5/16") (625-7003) | LF | 2,780 | $2.75 | $2.96 | $5.00 | $6.46 | $3.32 | $5.25 | |
| 57 | Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190) | EACH | 4 | $11,500 | $11,500 | $15,000 | $9,500.00 | $6,413.34 | $18,000 | $34,500 |
| 58 | Aluminum signs (type A) (636-7001) | SF | 280 | $44.00 | $49.00 | $52.50 | $51.00 | $39.89 | $41.82 | $50.00 |
| 59 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 9 | $1,000.00 | $750.00 | $840.00 | $1,000.00 | $686.69 | $910.15 | $650.00 |
| 60 | Work zone pavement marking SHT terminal (tab)type W (662-7112) | EACH | 91 | $1.00 | $2.50 | $6.00 | $3.00 | $4.45 | $2.46 | $1.00 |
| 61 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 539 | $1.00 | $2.50 | $6.00 | $3.00 | $4.45 | $2.47 | $1.00 |
| 62 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 906 | $1.06 | $1.25 | $1.34 | $2.00 | $1.39 | $1.51 | $2.20 |
| 63 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 123 | $8.00 | $8.00 | $8.87 | $10.00 | $9.17 | $9.95 | $7.00 |
| 64 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 7 | $165.00 | $170.00 | $188.13 | $250.00 | $194.45 | $210.96 | $145.00 |
| 65 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 2 | $200.00 | $215.00 | $236.50 | $490.00 | $244.45 | $265.21 | $190.00 |
| 66 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 4 | $195.00 | $185.00 | $203.18 | $270.00 | $210.00 | $227.84 | $170.00 |
| 67 | Pavement sler 6" (666-7347) | LF | 352 | $0.75 | $1.00 | $1.08 | $0.20 | $1.12 | $1.21 | $2.50 |
| 68 | Pavement sler 8" (666-7348) | LF | 66 | $0.75 | $2.00 | $2.15 | $0.30 | $2.23 | $2.41 | $2.50 |
| 69 | Pavement sler 24" (666-7352) | LF | 269 | $1.00 | $3.00 | $3.23 | $3.00 | $3.34 | $3.62 | $5.00 |
| 70 | Pavement sler (arrow) (666-7353) | EACH | 3 | $1,653.00 | $55.00 | $59.13 | $14.00 | $61.12 | $66.30 | $100.00 |
| 71 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 3,777 | $0.55 | $1.50 | $1.61 | $2.00 | $1.67 | $1.81 | $2.00 |
| 72 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 5,379 | $0.55 | $1.50 | $1.61 | $2.00 | $1.67 | $1.81 | $2.00 |
| 73 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 229 | $15.00 | $16.66 | $23.00 | $17.23 | $18.69 | $15.00 | |
| 74 | Reflectorized pavement marker type I-C (672-7002) | EACH | 91 | $5.50 | $6.00 | $6.45 | $5.00 | $6.67 | $7.23 | $6.00 |
| 75 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 269 | $5.50 | $6.00 | $6.45 | $5.00 | $6.67 | $7.23 | $6.00 |
| 76 | Pavement surface preparation for marking (24") (678-7008) | LF | 229 | $1.00 | $1.08 | $1.00 | $1.12 | $1.21 | $5.00 | |
| 77 | Install highway traffic signal (isolated) (680-7002) | EACH | 4 | $50,000 | $43,000 | $60,000 | $54,000 | $39,050 | $55,000 | $75,000 |
| 78 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 32 | $420.00 | $425.00 | $468.96 | $650.00 | $300.00 | $525.89 | $325.00 |
| 79 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 12 | $420.00 | $432.00 | $476.27 | $650.00 | $300.00 | $534.09 | $325.00 |
| 80 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 32 | $420.00 | $425.00 | $468.96 | $650.00 | $300.00 | $525.89 | $325.00 |
| 81 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 16 | $420.00 | $432.00 | $476.27 | $650.00 | $300.00 | $534.08 | $325.00 |
| 82 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 32 | $420.00 | $425.00 | $468.96 | $650.00 | $300.00 | $525.89 | $325.00 |
| 83 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 12 | $420.00 | $432.00 | $476.27 | $650.00 | $300.00 | $534.09 | $325.00 |
| 84 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 26 | $250.00 | $215.00 | $237.61 | $280.00 | $222.23 | $266.45 | $160.00 |
| 85 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 6 | $350.00 | $290.00 | $319.46 | $290.00 | $333.34 | $358.24 | $220.00 |
| 86 | Backplate W/ref border(5 sec)(vent)aluminum (682-7044) | EACH | 6 | $400.00 | $296.00 | $326.77 | $300.00 | $455.56 | $366.44 | $220.00 |
| 87 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 564 | $4.00 | $3.00 | $3.27 | $3.00 | $2.88 | $3.66 | $3.20 |
| 88 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 2,359 | $4.50 | $3.75 | $4.15 | $3.00 | $3.39 | $4.65 | $3.50 |
| 89 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 406 | $7.00 | $7.76 | $6.00 | $5.24 | $8.70 | $5.50 | |
| 90 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 445 | $8.00 | $10.00 | $11.16 | $7.00 | $7.48 | $12.51 | $7.25 |
| 91 | Ins traffic signal PL AM (S)STR(type B)lum (686-7008) | EACH | 8 | $11,600 | $12,763 | $8,400.00 | $8,544.45 | $14,312 | $16,500 | |
| 92 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 3 | $12,500 | $13,624 | $13,000 | $12,121 | $15,278 | $19,500 | |
| 93 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 2 | $16,500 | $15,175 | $16,746 | $14,700 | $14,088 | $18,779 | $20,500 |
| 94 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 1 | $17,000 | $18,827 | $13,500 | $14,844 | $21,113 | $21,500 | |
| 95 | Ins traffic signal PL AM(S)1 arm(55')lum (686-7059) | EACH | 2 | $32,500 | $33,600 | $37,057 | $35,000 | $34,800 | $41,556 | $39,500 |
| 96 | Full - width mowing (730-7019) | CYC | 1 | $2,750.00 | $2,000.00 | $5,000.00 | $7,800.00 | $10,000 | $8,052.91 | $1,200.00 |
| 97 | Spot tree trimming / brush removal (752-7002) | LF | 25 | $40.00 | $262.50 | $85.00 | $279.00 | $70.41 | $300.00 | |
| 98 | Bbu system (external battery cabinet) (6007-7001) | EACH | 4 | $8,500.00 | $10,000 | $10,997 | $9,200.00 | $8,022.23 | $15,000 | $15,000 |
| 99 | RVDS (presence detection only) (6008-7001) | EACH | 12 | $12,000 | $10,500 | $11,497 | $14,250 | $10,021 | $14,000 | $12,000 |
| 100 | RVDS (advance detection only) (6008-7002) | EACH | 7 | $12,500 | $9,250.00 | $10,196 | $14,250 | $9,071.67 | $12,000 | $12,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of April 7, 2026. Compiled by Mirage Metrics.