TxDOT contract A00218072 bid tabulation
Install Traffic Signal, SH 78 (at CR 550 to in Farmersville). Let by Texas DOT on March 5, 2026, Collin, Dallas District. 8 bids received; low bid $1,754,724 by Elecnor Belco Electric, Inc., -15% against the engineer's estimate of $2,070,373.
- Owner
- Texas DOT
- Letting
- 05 MAR 2026
- Pay items
- 124
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Elecnor Belco Electric, Inc. | $1,754,724 | Low | -15% |
| 2 | Sice, Inc. | $1,991,344 | +13% | -4.0% |
| 3 | Yunex LLC | $2,075,799 | +18% | 0.0% |
| 4 | WG Engineering & Construction, LLC | $2,118,683 | +21% | +2.0% |
| 5 | Durable Specialties, Inc. | $2,268,374 | +29% | +10% |
| 6 | Florida Traffic Control Devices, Inc. | $2,334,334 | +33% | +13% |
| 7 | Highway Intelligent Traffic Solutions, Inc. | $2,365,026 | +35% | +14% |
| 8 | Select Maintenance, L.L.C. | $2,494,545 | +42% | +20% |
Engineer's estimate: $2,070,373.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Elecnor Belco Electric, Inc. | 2. Sice, Inc. | 3. Yunex LLC | 4. WG Engineering & Construction, LLC | 5. Durable Specialties, Inc. | 6. Florida Traffic Control Devices, Inc. |
|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Preparing row (100-7002) | STA | 14 | $5,095.00 | $1,802.24 | $4,572.18 | $2,100.00 | $1,100.00 | $6,020.00 | |
| 2 | Removing concrete (driveways) (104-7011) | SY | 509 | $44.00 | $47.58 | $38.81 | $68.00 | $60.00 | $51.10 | |
| 3 | Removing concrete (curb or curb & gutter) (104-7018) | LF | 30 | $59.00 | $64.63 | $52.71 | $78.00 | $75.00 | $69.40 | |
| 4 | Excavation (roadway) (110-7001) | CY | 180 | $61.00 | $67.07 | $54.69 | $84.00 | $90.00 | $72.00 | |
| 5 | Embankment (final)(DC)(type C) (132-7006) | CY | 650 | $55.00 | $60.22 | $49.11 | $84.00 | $90.00 | $64.70 | |
| 6 | Backfill (type A or B) (134-7004) | STA | 14 | $437.00 | $480.89 | $392.13 | $445.00 | $140.00 | $516.00 | |
| 7 | Blading (150-7001) | STA | 14 | $389.00 | $428.00 | $349.01 | $780.00 | $800.00 | $460.00 | |
| 8 | Drill seed (permanent_rural_clay) (164-7010) | SY | 8,581 | $0.70 | $0.45 | $0.37 | $1.00 | $1.00 | $0.50 | |
| 9 | Drill seed (temporary_warm_cool) (164-7015) | SY | 8,581 | $0.70 | $0.34 | $0.28 | $1.00 | $1.00 | $0.35 | |
| 10 | Vegetative watering (168-7001) | TGL | 2,553 | $15.00 | $18.94 | $11.28 | $12.00 | $8.00 | $17.80 | |
| 11 | SP mixes SP-B PG64-22 (344-7001) | TON | 799 | $202.00 | $221.80 | $178.76 | $181.00 | $230.00 | $235.00 | |
| 12 | SP mixes SP-C sac-B PG64-22 (344-7011) | TON | 335 | $264.00 | $290.14 | $280.76 | $330.00 | $300.00 | $370.00 | |
| 13 | Tack coat (344-7077) | GAL | 410 | $20.00 | $21.15 | $2.11 | $17.00 | $20.00 | $2.80 | |
| 14 | Plane & text asphalt concrete pavement(2") (354-7019) | SY | 1,246 | $21.00 | $22.70 | $16.30 | $20.00 | $22.00 | $27.00 | |
| 15 | Drilled shaft (traffic signal pole) (30 in) (416-7043) | LF | 132 | $354.00 | $229.82 | $480.57 | $480.00 | $630.00 | $645.00 | |
| 16 | Drilled shaft (traffic signal pole) (36 in) (416-7044) | LF | 92 | $620.00 | $401.00 | $471.91 | $527.28 | $620.00 | $710.00 | $670.00 |
| 17 | RC pipe (CL III)(18 in) (464-7003) | LF | 104 | $101.00 | $110.69 | $90.27 | $178.00 | $200.00 | $119.00 | |
| 18 | Set (type II) (18 in) (RCP) (6: 1) (P) (467-7308) | EACH | 2 | $762.00 | $837.81 | $683.18 | $3,250.00 | $3,500.00 | $900.00 | |
| 19 | Removing structure (set) (496-7004) | EACH | 2 | $192.00 | $210.69 | $171.81 | $720.00 | $550.00 | $225.00 | |
| 20 | Removing structure (pipe) (496-7007) | LF | 85 | $38.00 | $41.59 | $33.92 | $80.00 | $25.00 | $45.00 | |
| 21 | Mobilization (500-7001) | LS | 1 | $200,000 | $39,000 | $164,550 | $315,000 | $138,550 | $65,000 | $220,000 |
| 22 | Barricades, signs and traffic handling (502-7001) | MO | 8 | $16,000 | $5,259.00 | $9,252.80 | $12,000 | $4,252.00 | $7,000.00 | $11,075 |
| 23 | Portable changeable message sign (503-7001) | DAY | 50 | $175.00 | $97.00 | $323.02 | $78.87 | $120.00 | $65.00 | $200.00 |
| 24 | TMA (stationary) (505-7001) | DAY | 160 | $260.00 | $263.00 | $475.14 | $192.78 | $330.00 | $250.00 | $200.00 |
| 25 | Rock filter dams (install) (type 2) (506-7002) | LF | 40 | $65.00 | $61.90 | $50.48 | $50.00 | $50.00 | $89.00 | |
| 26 | Rock filter dams (remove) (506-7011) | LF | 40 | $37.00 | $19.34 | $15.78 | $20.00 | $20.00 | $20.80 | |
| 27 | Construction exits (install) (type 1) (506-7020) | SY | 172 | $57.00 | $45.13 | $36.81 | $40.00 | $15.00 | $48.50 | |
| 28 | Construction exits (remove) (506-7024) | SY | 172 | $22.00 | $14.19 | $11.57 | $20.00 | $10.00 | $15.25 | |
| 29 | Temporary sediment control fence (install) (506-7039) | LF | 44 | $4.50 | $7.74 | $6.31 | $10.00 | $30.00 | $8.30 | |
| 30 | Temporary sediment control fence (remove) (506-7041) | LF | 44 | $2.00 | $2.58 | $2.11 | $5.00 | $15.00 | $2.75 | |
| 31 | Biodegradable erosion control logs (install) (12") (506-7044) | LF | 55 | $10.00 | $7.42 | $7.94 | $10.00 | $2.00 | $8.00 | |
| 32 | Biodegradable erosion control logs (install) (18") (506-7045) | LF | 200 | $6.00 | $12.00 | $8.38 | $6.84 | $12.00 | $2.00 | $9.00 |
| 33 | Biodegradable erosion control logs (remove) (506-7046) | LF | 255 | $3.00 | $3.00 | $1.61 | $1.32 | $3.00 | $0.50 | $1.75 |
| 34 | Concrete curb (type II) (529-7002) | LF | 30 | $45.00 | $49.35 | $40.25 | $75.00 | $80.00 | $53.00 | |
| 35 | Driveways (concrete) (hes) (530-7007) | SY | 475 | $139.00 | $152.33 | $124.22 | $190.00 | $220.00 | $165.00 | |
| 36 | Concrete sidewalks (6") (531-7003) | SY | 20 | $154.00 | $168.51 | $137.42 | $150.00 | $175.00 | $180.00 | |
| 37 | Curb ramps (type 10) (531-7011) | EACH | 2 | $2,930.00 | $3,223.78 | $2,628.79 | $3,850.00 | $4,300.00 | $3,460.00 | |
| 38 | Curb ramps (type 21) (531-7013) | EACH | 1 | $2,930.00 | $3,223.78 | $2,628.79 | $6,000.00 | $6,800.00 | $3,460.00 | |
| 39 | Mill rumble strips (asphalt) (shoulder) (533-7001) | LF | 3,620 | $3.20 | $1.07 | $0.79 | $2.00 | $3.00 | $1.05 | |
| 40 | Conduit (PVC) (schedule 40) (2") (618-7030) | LF | 109 | $27.00 | $20.00 | $19.49 | $20.22 | $24.00 | $29.00 | $14.40 |
| 41 | Conduit (PVC) (schedule 40) (2") (bore) (618-7031) | LF | 175 | $36.00 | $32.24 | $53.54 | $30.00 | $58.00 | $44.90 | |
| 42 | Conduit (PVC) (schedule 40) (3") (618-7036) | LF | 867 | $35.00 | $24.00 | $22.40 | $21.35 | $25.00 | $31.00 | $17.50 |
| 43 | Conduit (PVC) (schedule 40) (3") (bore) (618-7037) | LF | 594 | $40.00 | $24.00 | $32.24 | $53.64 | $32.00 | $59.00 | $47.35 |
| 44 | Conduit (PVC) (schedule 40) (4") (618-7040) | LF | 82 | $30.00 | $21.92 | $38.22 | $30.00 | $32.00 | $19.55 | |
| 45 | Conduit (PVC) (schedule 40) (4") (bore) (618-7041) | LF | 145 | $32.00 | $38.69 | $65.33 | $37.00 | $61.00 | $59.70 | |
| 46 | Conduit (PVC) (schedule 80) (2") (618-7054) | LF | 98 | $30.00 | $22.00 | $23.45 | $43.14 | $26.00 | $31.00 | $18.05 |
| 47 | Electrical conductor (no.12) insulated (620-7004) | LF | 960 | $2.50 | $1.40 | $0.76 | $2.54 | $3.00 | $2.00 | $1.75 |
| 48 | Electrical conductor (no.8) insulated (620-7008) | LF | 4,208 | $3.00 | $2.00 | $1.41 | $3.03 | $3.50 | $3.00 | $2.25 |
| 49 | Electrical conductor (no.6) bare (620-7009) | LF | 1,909 | $3.00 | $2.50 | $1.54 | $3.21 | $3.50 | $4.00 | $2.25 |
| 50 | Electrical conductor (no.6) insulated (620-7010) | LF | 558 | $3.50 | $2.50 | $2.06 | $3.45 | $3.50 | $4.00 | $2.75 |
| 51 | Electrical conductor (no.4) insulated (620-7012) | LF | 399 | $4.00 | $4.00 | $2.96 | $4.24 | $4.50 | $5.00 | $3.90 |
| 52 | Ground box type C (162911)W/apron (624-7006) | EACH | 20 | $2,000.00 | $1,738.00 | $1,518.34 | $2,618.27 | $1,485.00 | $2,425.00 | $2,185.00 |
| 53 | Ground box type D (162922)W/apron (624-7008) | EACH | 7 | $2,100.00 | $1,738.00 | $1,649.79 | $2,670.85 | $2,214.00 | $2,490.00 | $1,930.00 |
| 54 | Zinc-coat steel wire strand (3/16") (625-7001) | LF | 666 | $3.00 | $10.09 | $6.00 | $3.50 | $5.00 | $3.30 | |
| 55 | Zinc-coat steel wire strand (5/16") (625-7003) | LF | 1,003 | $4.00 | $11.45 | $6.31 | $4.00 | $5.00 | $3.65 | |
| 56 | Elc SRV type D 120/240 070(NS)SS(E)PS(U) (628-7190) | EACH | 5 | $11,500 | $6,712.00 | $8,881.64 | $7,668.68 | $8,885.00 | $11,000 | $10,600 |
| 57 | Aluminum signs (type A) (636-7001) | SF | 307.25 | $44.00 | $47.00 | $61.66 | $33.74 | $40.00 | $50.00 | $33.80 |
| 58 | Install small roadside sign support and assembly type 10BWG(1)SA(P) (644-7001) | EACH | 1 | $1,300.00 | $1,172.00 | $999.37 | $802.59 | $1,010.00 | $1,450.00 | $1,000.00 |
| 59 | Install small roadside sign support and assembly type 10BWG(1)SA(T) (644-7004) | EACH | 2 | $1,172.00 | $1,102.53 | $847.96 | $1,214.00 | $1,450.00 | $1,157.00 | |
| 60 | Remove SM RD SN sup&AM (644-7073) | EACH | 2 | $230.00 | $120.00 | $161.19 | $141.96 | $350.00 | $400.00 | $900.00 |
| 61 | Work zone pavement marking non-removing (Y)6"(solid) (662-7038) | LF | 1,300 | $1.30 | $0.84 | $0.69 | $9.00 | $7.00 | $0.90 | |
| 62 | Work zone pavement marking SHT terminal (tab)type Y-2 (662-7114) | EACH | 386 | $0.50 | $6.45 | $1.06 | $4.00 | $3.00 | $9.00 | |
| 63 | Reflectorized pavement marking type I (W)8"(DOT)(100MIL) (666-7018) | LF | 60 | $42.00 | $3.87 | $3.16 | $3.00 | $2.00 | $4.15 | |
| 64 | Reflectorized pavement marking type I (W)8"(solid)(100MIL) (666-7024) | LF | 1,406 | $2.50 | $1.00 | $1.35 | $1.11 | $3.00 | $2.00 | $1.45 |
| 65 | Reflectorized pavement marking type I (W)24"(solid)(100MIL) (666-7036) | LF | 95 | $12.00 | $8.71 | $7.10 | $12.00 | $9.00 | $9.35 | |
| 66 | Reflectorized pavement marking type I (W)(arrow)(100MIL) (666-7042) | EACH | 5 | $223.00 | $251.46 | $205.05 | $250.00 | $220.00 | $1,350.00 | |
| 67 | Reflectorized pavement marking type I(W)(double arrow)(100MIL) (666-7045) | EACH | 1 | $340.00 | $470.67 | $383.81 | $300.00 | $240.00 | $503.35 | |
| 68 | Reflectorized pavement marking type I (W)(word)(100MIL) (666-7066) | EACH | 6 | $276.00 | $277.25 | $226.08 | $300.00 | $220.00 | $300.00 | |
| 69 | Pavement sler 6" (666-7347) | LF | 9,191 | $0.50 | $0.37 | $0.22 | $0.18 | $0.30 | $0.20 | $0.25 |
| 70 | Pavement sler 8" (666-7348) | LF | 1,466 | $0.50 | $0.60 | $0.22 | $0.18 | $0.50 | $0.30 | $0.25 |
| 71 | Pavement sler 24" (666-7352) | LF | 463 | $2.00 | $2.10 | $0.65 | $0.53 | $3.00 | $3.00 | $0.70 |
| 72 | Pavement sler (arrow) (666-7353) | EACH | 17 | $47.00 | $88.00 | $25.79 | $21.04 | $24.00 | $20.00 | $27.70 |
| 73 | Pavement sler (word) (666-7354) | EACH | 18 | $63.00 | $88.00 | $25.79 | $21.04 | $32.00 | $25.00 | $27.70 |
| 74 | Pavement sler (double arrow) (666-7356) | EACH | 1 | $88.00 | $38.69 | $31.55 | $40.00 | $30.00 | $42.00 | |
| 75 | Reflectorized pavement marking type I (W)6"(solid)(100MIL) (666-7411) | LF | 2,925 | $1.00 | $1.60 | $0.84 | $0.69 | $2.00 | $1.50 | $0.90 |
| 76 | Reflectorized pavement marking type I (Y)6"(solid)(100MIL) (666-7423) | LF | 6,266 | $1.50 | $1.50 | $0.84 | $0.69 | $2.00 | $1.50 | $0.90 |
| 77 | Prefabricated PM type C (W)(24")(solid) (668-7089) | LF | 368 | $19.00 | $16.00 | $16.44 | $13.41 | $25.00 | $25.00 | $17.65 |
| 78 | Prefabricated PM type C (W)(arrow) (668-7091) | EACH | 12 | $300.00 | $264.00 | $315.93 | $257.63 | $280.00 | $300.00 | $340.00 |
| 79 | Prefabricated PM type C (W)(word) (668-7103) | EACH | 12 | $450.00 | $323.00 | $341.72 | $278.66 | $285.00 | $315.00 | $367.00 |
| 80 | Reflectorized pavement marker type I-C (672-7002) | EACH | 70 | $6.00 | $8.20 | $6.45 | $5.26 | $5.00 | $5.00 | $7.00 |
| 81 | Reflectorized pavement marker type II-A-A (672-7004) | EACH | 306 | $7.00 | $8.50 | $5.09 | $4.16 | $5.00 | $5.00 | $5.50 |
| 82 | Eliminating existing PM & markers (4") (677-7001) | LF | 1,455 | $1.20 | $0.71 | $0.58 | $1.20 | $1.00 | $0.75 | |
| 83 | Eliminating existing PM & markers (6") (677-7002) | LF | 60 | $1.00 | $1.50 | $0.84 | $0.69 | $2.00 | $1.00 | $0.90 |
| 84 | Eliminating existing PM & markers (8") (677-7004) | LF | 144 | $1.00 | $3.00 | $1.16 | $0.95 | $2.50 | $2.00 | $1.25 |
| 85 | Eliminating existing PM & markers (24") (677-7008) | LF | 22 | $4.00 | $4.84 | $3.95 | $6.00 | $5.00 | $5.20 | |
| 86 | Eliminating existing PM & markers (arrow) (677-7009) | EACH | 10 | $50.00 | $118.00 | $70.92 | $57.84 | $55.00 | $60.00 | $76.00 |
| 87 | Eliminating existing PM & markers (word) (677-7015) | EACH | 4 | $50.00 | $118.00 | $70.92 | $57.84 | $65.00 | $70.00 | $76.00 |
| 88 | Pavement surface preparation for marking (6") (678-7002) | LF | 6,816 | $0.40 | $0.30 | $0.13 | $0.11 | $0.10 | $0.10 | $0.15 |
| 89 | Pavement surface preparation for marking (8") (678-7004) | LF | 1,406 | $0.40 | $0.50 | $0.13 | $0.11 | $0.25 | $0.15 | $0.15 |
| 90 | Pavement surface preparation for marking (24") (678-7008) | LF | 463 | $0.40 | $2.00 | $0.39 | $0.32 | $1.50 | $1.00 | $0.40 |
| 91 | Pavement surface preparation for marking (arrow) (678-7009) | EACH | 17 | $40.00 | $59.00 | $12.90 | $10.52 | $15.00 | $14.00 | $13.85 |
| 92 | Pavement surface preparation for marking (double arrow) (678-7010) | EACH | 1 | $59.00 | $19.34 | $15.78 | $25.00 | $28.00 | $20.80 | |
| 93 | Pavement surface preparation for marking (word) (678-7016) | EACH | 18 | $40.00 | $59.00 | $12.90 | $10.52 | $20.00 | $21.00 | $13.85 |
| 94 | Pavement surface preparation for marking (RPM) (678-7033) | EACH | 264 | $2.00 | $1.00 | $0.32 | $0.27 | $1.00 | $0.10 | $0.35 |
| 95 | Install highway traffic signal (isolated) (680-7002) | EACH | 5 | $50,000 | $36,000 | $31,751 | $37,085 | $60,387 | $50,000 | $36,800 |
| 96 | Vehicle signal section (12")LED(green) (682-7001) | EACH | 32 | $420.00 | $224.00 | $286.10 | $331.23 | $378.00 | $700.00 | $381.00 |
| 97 | Vehicle signal section (12")LED(green arrow) (682-7002) | EACH | 9 | $420.00 | $224.00 | $280.36 | $331.23 | $378.00 | $700.00 | $381.00 |
| 98 | Vehicle signal section (12")LED(yel) (682-7003) | EACH | 32 | $420.00 | $224.00 | $286.10 | $331.23 | $378.00 | $700.00 | $381.00 |
| 99 | Vehicle signal section (12")LED(yel arrow) (682-7004) | EACH | 10 | $420.00 | $224.00 | $280.55 | $331.23 | $378.00 | $700.00 | $381.00 |
| 100 | Vehicle signal section (12")LED(red) (682-7005) | EACH | 32 | $420.00 | $224.00 | $286.10 | $331.23 | $378.00 | $700.00 | $381.00 |
| 101 | Vehicle signal section (12")LED(red arrow) (682-7006) | EACH | 10 | $420.00 | $224.00 | $280.55 | $331.23 | $378.00 | $700.00 | $381.00 |
| 102 | Pedestrian signal section (LED)(countdown) (682-7018) | EACH | 6 | $416.00 | $715.54 | $525.76 | $378.00 | $1,250.00 | $765.00 | |
| 103 | Backplate W/ref border(3 sec)(vent)aluminum (682-7042) | EACH | 28 | $250.00 | $121.00 | $390.36 | $210.31 | $310.00 | $250.00 | $280.00 |
| 104 | Backplate W/ref border(4 sec)(vent)aluminum (682-7043) | EACH | 4 | $350.00 | $187.00 | $372.32 | $220.82 | $320.00 | $270.00 | $295.00 |
| 105 | Backplate W/ref border(5 sec)(vent)aluminum (682-7044) | EACH | 5 | $400.00 | $199.00 | $403.90 | $241.85 | $340.00 | $290.00 | $324.00 |
| 106 | Traffic signal CBL (type A)(14 AWG)(3 conductor) (684-7029) | LF | 10 | $3.00 | $1.96 | $2.79 | $3.00 | $3.00 | $2.20 | |
| 107 | Traffic signal CBL (type A)(14 AWG)(5 conductor) (684-7031) | LF | 1,074 | $4.00 | $3.00 | $2.07 | $3.21 | $3.50 | $3.00 | $2.65 |
| 108 | Traffic signal CBL (type A)(14 AWG)(7 conductor) (684-7033) | LF | 1,218 | $4.50 | $3.00 | $2.39 | $3.57 | $4.00 | $3.00 | $3.55 |
| 109 | Traffic signal CBL (type A)(14 AWG)(16 conductor) (684-7042) | LF | 1,445 | $7.00 | $4.69 | $6.11 | $6.00 | $7.00 | $5.80 | |
| 110 | Traffic signal CBL (type A)(14 AWG)(20 conductor) (684-7046) | LF | 829 | $8.00 | $8.00 | $6.24 | $7.02 | $7.00 | $8.00 | $8.00 |
| 111 | Traffic signal CBL (type C)(12 AWG)(2 conductor) (684-7079) | LF | 766 | $3.00 | $1.83 | $2.79 | $3.00 | $3.00 | $2.40 | |
| 112 | Ins traffic signal PL AM (S)STR(type B)lum (686-7008) | EACH | 4 | $8,492.00 | $8,648.34 | $9,715.98 | $8,760.00 | $9,600.00 | $16,632 | |
| 113 | Ins traffic signal PL AM(S)1 arm(24')lum (686-7027) | EACH | 1 | $9,742.00 | $12,644 | $10,633 | $9,982.00 | $15,000 | $20,950 | |
| 114 | Ins traffic signal PL AM(S)1 arm(28')lum (686-7031) | EACH | 3 | $9,595.00 | $12,755 | $11,470 | $10,376 | $15,300 | $21,265 | |
| 115 | Ins traffic signal PL AM(S)1 arm(32')lum (686-7035) | EACH | 2 | $10,901 | $13,093 | $12,353 | $11,566 | $15,800 | $21,810 | |
| 116 | Ins traffic signal PL AM(S)1 arm(36')lum (686-7039) | EACH | 1 | $16,500 | $11,729 | $14,616 | $13,331 | $12,846 | $17,100 | $23,160 |
| 117 | Ins traffic signal PL AM(S)1 arm(40')lum (686-7043) | EACH | 3 | $17,000 | $12,108 | $15,802 | $14,418 | $13,510 | $18,000 | $24,325 |
| 118 | Ins traffic signal PL AM(S)1 arm(44')lum (686-7047) | EACH | 2 | $17,500 | $12,311 | $15,611 | $14,804 | $14,227 | $18,400 | $24,700 |
| 119 | Pedestrian pole assembly (687-7001) | EACH | 4 | $2,145.00 | $4,201.73 | $3,375.36 | $3,399.00 | $5,500.00 | $5,042.00 | |
| 120 | Pedestrian detect push button (APS) (688-7001) | EACH | 6 | $1,195.00 | $945.56 | $774.97 | $1,199.00 | $1,050.00 | $1,082.00 | |
| 121 | Pedestrian detector controller unit (688-7003) | EACH | 1 | $3,858.98 | $3,991.04 | $3,611.95 | $4,574.00 | $5,500.00 | $4,330.00 | |
| 122 | Bbu system (external battery cabinet) (6007-7001) | EACH | 5 | $8,500.00 | $9,344.00 | $9,296.94 | $7,565.64 | $7,999.00 | $9,000.00 | $8,120.00 |
| 123 | RVDS (presence detection only) (6008-7001) | EACH | 13 | $12,000 | $10,947 | $11,274 | $9,637.12 | $9,950.00 | $12,400 | $7,415.00 |
| 124 | RVDS (advance detection only) (6008-7002) | EACH | 9 | $12,500 | $8,413.00 | $9,824.06 | $8,435.24 | $8,650.00 | $11,250 | $8,550.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of March 5, 2026. Compiled by Mirage Metrics.