TxDOT contract A00218968 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, IH0069E (VARIOUS ROADWAYS to VARIOUS ROADWAYS). Let by Texas DOT on June 25, 2026, Cameron, Pharr District. 3 bids received; low bid $733,936 by SCR Civil Construction, LLC, +12% against the engineer's estimate of $657,204.
- Owner
- Texas DOT
- Letting
- 25 JUN 2026
- Pay items
- 29
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | SCR Civil Construction, LLC | $733,936 | Low | +12% |
| 2 | Taylor Bridge LLC | $802,873 | +9.0% | +22% |
| 3 | Lucania Contractors LLC | $811,735 | +11% | +24% |
Engineer's estimate: $657,204.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. SCR Civil Construction, LLC | 2. Taylor Bridge LLC | 3. Lucania Contractors LLC |
|---|---|---|---|---|---|---|---|
| 1 | Cem stabil BKFL (400-7010) | CY | 20 | $130.00 | $825.00 | $550.00 | $350.00 |
| 2 | Concrete paint finish (427-7002) | SF | 98 | $30.00 | $25.00 | $15.00 | $35.00 |
| 3 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 148 | $115.00 | $180.00 | $300.00 | $50.00 |
| 4 | Riprap (stone protection)(18 in) (432-7043) | CY | 140 | $195.00 | $488.00 | $250.00 | $400.00 |
| 5 | Elastomeric bearing (plain) (434-7001) | EACH | 35 | $1,000.00 | $230.00 | $1,000.00 | $2,000.00 |
| 6 | Cleaning and sealing existing joints (438-7001) | LF | 5,574 | $37.00 | $30.00 | $45.00 | $45.00 |
| 7 | Cleaning & sealing existing joint (SEJ) (438-7013) | LF | 1,919 | $50.00 | $57.00 | $80.00 | $55.00 |
| 8 | STR steel (pedestal) (442-7010) | LB | 1,715 | $16.00 | $37.55 | $15.00 | $35.00 |
| 9 | Spot clean & paint existing structure(special protection sys) (446-7019) | LS | 1 | $15,000 | $28,000 | $30,000 | $18,000 |
| 10 | Joint sealant (454-7010) | LF | 228 | $45.00 | $40.00 | $10.00 | $30.00 |
| 11 | Mobilization (500-7001) | LS | 1 | $58,956 | $73,300 | $70,000 | $85,000 |
| 12 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $5,000.00 | $4,000.00 | $1.00 | $500.00 |
| 13 | Portable changeable message sign (503-7002) | EACH | 2 | $1,500.00 | $5,100.00 | $1.00 | $15,000 |
| 14 | TMA (stationary) (505-7001) | DAY | 240 | $150.00 | $50.00 | $1.00 | $1.00 |
| 15 | Driftwood removal (735-7060) | CY | 20 | $80.00 | $350.00 | $300.00 | $180.00 |
| 16 | Replace rail element (W-beam) (770-7001) | LF | 675 | $21.00 | $40.00 | $30.00 | $22.00 |
| 17 | Replace timber post W/O concrete FND (770-7006) | EACH | 1 | $100.00 | $350.00 | $1,000.00 | $800.00 |
| 18 | Replace steel post W/O concrete FND (770-7007) | EACH | 2 | $150.00 | $460.00 | $1,000.00 | $850.00 |
| 19 | Replace blockout (770-7018) | EACH | 2 | $50.00 | $230.00 | $500.00 | $650.00 |
| 20 | Reset SGT impact head (770-7020) | EACH | 2 | $250.00 | $600.00 | $500.00 | $850.00 |
| 21 | Replace SGT cable assembly (770-7023) | EACH | 2 | $200.00 | $600.00 | $4,000.00 | $850.00 |
| 22 | Repair (steel rail) (776-7001) | LF | 50 | $25.00 | $213.00 | $250.00 | $23.00 |
| 23 | Repair (steel post W/base plate) (776-7002) | EACH | 3 | $500.00 | $1,000.00 | $500.00 | $1,100.00 |
| 24 | Concrete rail repair (in-kind) (778-7001) | LF | 11 | $250.00 | $1,200.00 | $2,000.00 | $1,750.00 |
| 25 | Concrete CRCK repair(discrete)(rout and seal) (780-7003) | LF | 1,285 | $45.00 | $25.00 | $40.00 | $35.00 |
| 26 | Rep steel bridge MBR (anchor bolt nuts) (784-7021) | EACH | 5 | $50.00 | $100.00 | $100.00 | $100.00 |
| 27 | Rep steel bridge MBR (weld repair) (784-7022) | EACH | 1 | $500.00 | $2,200.00 | $500.00 | $850.00 |
| 28 | Bridge joint repair (header) (785-7002) | LF | 17 | $250.00 | $550.00 | $750.00 | $350.00 |
| 29 | Bent cap/abutment cap cleaning (7001-7002) | EACH | 4 | $1,000.00 | $1,300.00 | $750.00 | $1,700.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 25, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.