TxDOT contract A00222277 bid tabulation
BRIDGE PREVENTATIVE MAINTENANCE, IH0002 (VARIOUS ROADWAYS to VARIOUS ROADWAYS). Let by Texas DOT on June 4, 2026, Hidalgo, Pharr District. 5 bids received; low bid $566,461 by Digg Commercial, LLC, -2.7% against the engineer's estimate of $582,161.
- Owner
- Texas DOT
- Letting
- 04 JUN 2026
- Pay items
- 26
- Data through
- 19 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Digg Commercial, LLC | $566,461 | Low | -3.0% |
| 2 | Icos Management, LLC | $680,895 | +20% | +17% |
| 3 | GHB Equipment Company, L.L.C. | $842,250 | +49% | +45% |
| 4 | Rhino Equity, LLC | $889,870 | +57% | +53% |
| 5 | Rear Contractors LLC | $1,322,070 | +133% | +127% |
Engineer's estimate: $582,161.
Bid tabulation
| Line | Pay item | Unit | Quantity | Estimate | 1. Digg Commercial, LLC | 2. Icos Management, LLC | 3. GHB Equipment Company, L.L.C. | 4. Rhino Equity, LLC | 5. Rear Contractors LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Removing concrete (riprap) (104-7006) | SY | 133 | $37.00 | $13.00 | $55.00 | $18.00 | $40.00 | $100.00 |
| 2 | Removing concrete (sawcut) (104-7020) | LF | 20 | $120.00 | $50.00 | $220.00 | $7.50 | $50.00 | $100.00 |
| 3 | Embankment (final)(OC)(type C) (132-7005) | CY | 117 | $40.00 | $50.00 | $44.00 | $40.00 | $50.00 | $250.00 |
| 4 | Cem stabil BKFL (400-7010) | CY | 165 | $100.00 | $150.00 | $203.50 | $275.00 | $250.00 | $500.00 |
| 5 | Flowable backfill (401-7001) | CY | 15 | $240.00 | $500.00 | $330.00 | $500.00 | $300.00 | $1,000.00 |
| 6 | Concrete structure repair (vertical & overhead) (429-7007) | SF | 625 | $110.00 | $150.00 | $110.00 | $150.00 | $230.00 | $500.00 |
| 7 | Riprap (concrete)(5 in) (432-7002) | CY | 29 | $650.00 | $646.00 | $650.00 | $525.00 | $900.00 | $1,000.00 |
| 8 | Riprap (stone protection)(12 in) (432-7041) | CY | 226 | $195.00 | $210.00 | $231.00 | $340.00 | $230.00 | $400.00 |
| 9 | Riprap (stone protection)(18 in) (432-7043) | CY | 995 | $195.00 | $177.00 | $231.00 | $414.00 | $250.00 | $400.00 |
| 10 | Cleaning and sealing existing joints (438-7001) | LF | 2,129 | $40.00 | $20.00 | $55.00 | $24.00 | $70.00 | $60.00 |
| 11 | RC pipe (CL III)(18 in) (464-7003) | LF | 24 | $110.00 | $80.00 | $220.00 | $50.00 | $110.00 | $100.00 |
| 12 | RC pipe (CL III)(24 in) (464-7005) | LF | 14 | $135.00 | $94.00 | $242.00 | $125.00 | $120.00 | $300.00 |
| 13 | Set (type II) (18 in) (RCP) (4: 1) (C) (467-7306) | EACH | 1 | $1,100.00 | $1,287.00 | $1,650.00 | $1,000.00 | $1,800.00 | $2,500.00 |
| 14 | Removing structure (headwall) (496-7006) | EACH | 1 | $500.00 | $1,304.00 | $2,200.00 | $1,500.00 | $800.00 | $15,000 |
| 15 | Removing structure (pipe) (496-7007) | LF | 32 | $13.00 | $18.00 | $22.00 | $30.00 | $40.00 | $1,500.00 |
| 16 | Mobilization (500-7001) | LS | 1 | $52,924 | $40,000 | $55,000 | $40,000 | $80,000 | $50,000 |
| 17 | Barricades, signs and traffic handling (502-7001) | MO | 6 | $5,000.00 | $9,000.00 | $1.00 | $5,500.00 | $6,000.00 | $10.00 |
| 18 | Portable changeable message sign (503-7002) | EACH | 2 | $2,200.00 | $7,793.00 | $5,500.00 | $4,000.00 | $5,000.00 | $10.00 |
| 19 | TMA (stationary) (505-7001) | DAY | 240 | $80.00 | $1.00 | $1.00 | $25.00 | $200.00 | $10.00 |
| 20 | Driftwood removal (735-7060) | CY | 135 | $55.00 | $71.00 | $66.00 | $100.00 | $100.00 | $100.00 |
| 21 | Tree removal (4" - 12" diameter) (752-7005) | EACH | 10 | $45.00 | $400.00 | $495.00 | $300.00 | $200.00 | $500.00 |
| 22 | Ditch cleaning and reshaping (foot) (760-7001) | LF | 460 | $15.00 | $1.36 | $44.00 | $25.00 | $15.00 | $50.00 |
| 23 | Reset SGT impact head (770-7020) | EACH | 1 | $200.00 | $51.00 | $3,300.00 | $1,000.00 | $1,000.00 | $2,500.00 |
| 24 | Replace(steel rail) (776-7024) | LF | 22 | $280.00 | $305.00 | $220.00 | $50.00 | $70.00 | $400.00 |
| 25 | Concrete rail repair (in-kind) (778-7001) | LF | 22 | $200.00 | $416.00 | $715.00 | $400.00 | $200.00 | $2,000.00 |
| 26 | CNC crack repair (discrete)(inject) (780-7002) | LF | 10 | $60.00 | $64.00 | $132.00 | $100.00 | $80.00 | $100.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from TxDOT's tabulation for this contract. TxDOT Bid Tabulations open-data export (data.texas.gov) from September 2024, read 21 November 2026, and TxDOT's legacy Tabulation of Bids pages for January 2020 to August 2024. The legacy pages are a large sample, not every contract: their file names were reused from year to year. Their district is the one TxDOT gives the county. Bids that did not match their published total are left out.
Every contract let that day: TxDOT letting of June 4, 2026. Compiled by Mirage Metrics.