TxDOT letting results, March 14, 2023
22 contracts let by Texas DOT on March 14, 2023, $4,193,371 in low bids, a median of 3 bidders per contract. On the 22 with an engineer's estimate, the low bid came in under it 13 times; median low bid -3.0% against the estimate.
- Owner
- Texas DOT
- Contracts
- 22
- Low bids, total
- $4,193,371
- Data through
- 19 NOV 2026
Contracts let that day
| Contract | Project | District | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 03231701 | SH0006 Hot-mix cold-laid from VARIOUS to VARIOUS | Bryan District | 1 | Touchstone Resources, LLC | $390,000 | +62% | TxDOT | ||
| 03230709 | US0083 Limestone rock asphalt from VARIOUS LOCATIONS IN THE SAN ANGELO to VARIOUS LOCATIONS IN SAN ANGELO DIS | San Angelo District | 2 | Vulcan Construction Materials, LLC | $314,876 | $320,624 | +2.0% | +8.0% | TxDOT |
| 03230705 | US0067 Emulsion from DISTRICT WIDE to DISTRICT WIDE | San Angelo District | 2 | Ergon Asphalt & Emulsions, Inc. | $302,271 | $310,650 | +3.0% | +1.0% | TxDOT |
| 03231001 | US0069 Concrete structure repair from RUSK STATE HOSPITAL to PARKING LOT | Tyler District | 3 | Red Baron Building Company, LLC | $298,238 | $359,113 | +20% | 0.0% | TxDOT |
| 03230708 | US0067 Limestone rock asphalt from DISTRICT WIDE to DISTRICT WIDE | San Angelo District | 1 | Vulcan Construction Materials, LLC | $282,300 | +8.0% | TxDOT | ||
| 03230440 | IH0027 Hot mix from VARIOUS LOCATIONS SEE PLANS to VARIOUS LOCATIONS SEE PLANS | Amarillo District | 4 | L A Fuller & Sons Construction, LTD. | $265,490 | $277,000 | +4.0% | -8.0% | TxDOT |
| 03231802 | SH0005 Limestone rock asphalt from COLLIN COUNTY to MAINTENANCE SECTION | Dallas District | 2 | Martin Marietta Materials, Inc. | $249,875 | $260,875 | +4.0% | +11% | TxDOT |
| 03230441 | SH0015 Hot mix from VARIOUS LOCATIONS SEE PLANS to VARIOUS LOCATIONS SEE PLANS | Amarillo District | 4 | L A Fuller & Sons Construction, LTD. | $225,695 | $235,250 | +4.0% | -13% | TxDOT |
| 03230442 | US0060 Hot mix from VARIOUS LOCATIONS SEE PLANS to VARIOUS LOCATIONS SEE PLANS | Amarillo District | 4 | L A Fuller & Sons Construction, LTD. | $225,695 | $235,250 | +4.0% | -19% | TxDOT |
| 03231801 | US0380 Miscellaneous concrete repair from VARIOUS ROADWAYS IN DENTON to DENTON COUNTY MAINTENANCE SECTION | Dallas District | 4 | Garret Shields Infrastructure | $212,810 | $254,360 | +20% | +10% | TxDOT |
| 03231803 | SH0005 Aggregate from COLLIN COUNTY to MAINTENANCE SECTION | Dallas District | 2 | Touchstone Resources, LLC | $210,000 | $234,000 | +11% | -7.0% | TxDOT |
| 03230704 | FM0176 Pavement markings from VARIOUS LOCATIONS IN THE SAN ANGELO to VARIOUS LOCATIONS IN SAN ANGELO DIS | San Angelo District | 3 | L&L Company | $191,793 | $218,787 | +14% | -17% | TxDOT |
| 03230706 | US0083 Asphalt from DISTRICT WIDE to DISTRICT WIDE | San Angelo District | 2 | Wright Asphalt Products Company LLC | $171,912 | $186,960 | +9.0% | -6.0% | TxDOT |
| 03231805 | IH0030 Tree trimming and brush removal from VARIOUS ROADWAYS IN THE EAST to DALLAS COUNTY MAINTENANCE SECTIONS | Dallas District | 5 | Aza Construction Inc | $132,863 | $133,544 | +1.0% | -30% | TxDOT |
| 03230707 | US0087 Emulsion from DISTRICT WIDE to DISTRICT WIDE | San Angelo District | 1 | Ergon Asphalt & Emulsions, Inc. | $131,841 | +1.0% | TxDOT | ||
| 03230703 | RM1312 Pavement markings from DISTRICT WIDE to DISTRICT WIDE | San Angelo District | 3 | L&L Company | $130,462 | $157,609 | +21% | -51% | TxDOT |
| 03232051 | US0069 Rock/riprap from DISTRICTWIDE to DISTRICTWIDE | Beaumont District | 4 | Touchstone Resources, LLC | $121,750 | $160,625 | +32% | -8.0% | TxDOT |
| 03230603 | IH0010 Asphaltic patching material from VARIOUS to VARIOUS | Odessa District | 3 | Touchstone Resources, LLC | $104,000 | $108,300 | +4.0% | -1.0% | TxDOT |
| 03231804 | SH0005 Emulsion from COLLIN COUNTY to MAINTENANCE SECTION | Dallas District | 4 | Wright Asphalt Products Company LLC | $74,750 | $80,000 | +7.0% | 0.0% | TxDOT |
| 03230602 | IH0020 Asphaltic patching material from VARIOUS to VARIOUS | Odessa District | 3 | Touchstone Resources, LLC | $74,000 | $77,425 | +5.0% | -3.0% | TxDOT |
| 03230601 | IH0020 Asphaltic patching material from VARIOUS to VARIOUS | Odessa District | 2 | Touchstone Resources, LLC | $65,000 | $70,210 | +8.0% | -2.0% | TxDOT |
| 03230604 | IH0020 Sand from VARIOUS to VARIOUS | Odessa District | 5 | Touchstone Resources, LLC | $17,750 | $19,000 | +7.0% | -9.0% | TxDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than TxDOT received, the others did not match their published totals and are left out.