VDOT contract C0000125211N01 bid tabulation
Clear zone improvements. Let by Virginia DOT on April 22, 2026, Scott, Bristol. 2 bids received; low bid $1,155,140 by King General Contractors, Inc..
- Owner
- Virginia DOT
- Letting
- 22 APR 2026
- Pay items
- 25
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | King General Contractors, Inc. | $1,155,140 | Low |
| 2 | Glass Machinery and Excavation, Inc. | $1,393,882 | +21% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. King General Contractors, Inc. | 2. Glass Machinery and Excavation, Inc. |
|---|---|---|---|---|---|
| 0001-0010 | Endwall EW-12 (302SD20-0013) | EACH | 1 | $2,449.06 | $2,850.00 |
| 0001-0020 | NS drop inlet precast top unit (DI-5) (302SX20-0026) | EACH | 14 | $4,318.59 | $4,800.00 |
| 0001-0030 | Check dam sediment retention roll 18" (303SD20-0024) | EACH | 82 | $211.13 | $320.00 |
| 0001-0040 | Siltation control excavation (303SD20-0029) | CY | 183 | $3.02 | $12.00 |
| 0001-0050 | Inlet protection type A (303SD20-0030) | EACH | 28 | $518.77 | $385.00 |
| 0001-0060 | Temp. silt fence type A (303SD20-0034) | LF | 100 | $22.32 | $7.00 |
| 0001-0070 | Aggr. matl. no. 21B (308SD20-0007) | TON | 15 | $124.26 | $65.00 |
| 0001-0080 | Asphalt concrete TY. SM- 12.5A const (315SD20-0001) | TON | 50 | $301.61 | $250.00 |
| 0001-0090 | Rumble strip cylindrical asphalt (315SD20-0015) | LF | 26,900 | $0.66 | $0.95 |
| 0001-0100 | Liquid asphalt coating (rumble strip) (315SD20-0016) | SY | 5,000 | $1.65 | $4.00 |
| 0001-0110 | Saw-cut asphalt concrete full depth (315SD20-0104) | LF | 480 | $18.70 | $4.90 |
| 0001-0120 | Outlet pipe (501SD20-0009) | LF | 10 | $34.13 | $65.00 |
| 0001-0130 | Underdrain UD-7 (501SD20-0010) | LF | 100 | $74.20 | $75.00 |
| 0001-0140 | Paved ditch PG-2A (502SD20-0003) | SY | 227.10 | $121.85 | $154.00 |
| 0001-0150 | Fixed object attach. GR- foa-1 TY. II (505SD20-0046) | EACH | 1 | $5,790.87 | $8,976.00 |
| 0001-0160 | Median barrier MB-3 (505SD20-0059) | LF | 12,850 | $58.51 | $59.56 |
| 0001-0170 | Remove existing guardrail (505SD20-0073) | LF | 190 | $12.06 | $27.15 |
| 0001-0180 | NS guardrail matt - SS 6287 transition (505SX20-0058) | EACH | 1 | $6,032.16 | $9,240.00 |
| 0001-0190 | NS guardrail median attenuating trend terminal (matt) (505SX20-0058) | EACH | 1 | $21,113 | $25,740 |
| 0001-0200 | Demo. of pavement flexible (508SD20-0004) | SY | 200 | $24.91 | $9.00 |
| 0001-0210 | Maintenance of traffic temporary traffic control (512SP20-0002) | LS | 1 | $83,364 | $197,438 |
| 0001-0220 | Mobilization (513SD20-0001) | LS | 1 | $78,418 | $145,500 |
| 0001-0230 | Flexible pave.planing 0"-2" (515SD20-0004) | SY | 250 | $14.48 | $12.00 |
| 0001-0240 | Rolled erosion CTRL product EC-2 type 4 (606SD20-0004) | SY | 918 | $6.03 | $10.00 |
| 0001-0250 | Type B class I PVMT line MRKG 6" (704SD20-0007) | LF | 450 | $16.11 | $17.85 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from VDOT's tabulation for this contract. VDOT bid tabulation PDFs for October 2025 to October 2026 (all bidders, awarded contracts), and VDOT yearly bid tab workbooks for 2002 to 2021, which list only the three lowest bids on each contract. The workbooks store numbers in single precision, so their bids are checked to within $1 or 0.0001% of the total, whichever is larger.
Every contract let that day: VDOT letting of April 22, 2026. Compiled by Mirage Metrics.