Northeast Electric, LLC: WSDOT bid record
Northeast Electric, LLC submitted 44 bids on Washington State DOT contracts in the data, from 22 FEB 2007 to 19 JAN 2023, and was the low bidder on 21 of them (48%). When it was not low, its total sat a median +13% above the low bid.
- Owner
- Washington State DOT
- Low bid volume
- $14,868,679
- Latest bid
- 19 JAN 2023
- Data through
- 07 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2007 | 1 | 1 | 100% |
| 2008 | 1 | 0 | 0% |
| 2009 | 2 | 1 | 50% |
| 2011 | 1 | 1 | 100% |
| 2012 | 6 | 2 | 33% |
| 2013 | 7 | 1 | 14% |
| 2014 | 2 | 1 | 50% |
| 2015 | 1 | 1 | 100% |
| 2016 | 2 | 0 | 0% |
| 2017 | 2 | 2 | 100% |
| 2018 | 2 | 1 | 50% |
| 2019 | 6 | 2 | 33% |
| 2020 | 4 | 3 | 75% |
| 2021 | 5 | 3 | 60% |
| 2022 | 1 | 1 | 100% |
| 2023 | 1 | 1 | 100% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| SWR region | 10 | 6 | 60% |
| NCR region | 8 | 4 | 50% |
| OR region | 8 | 5 | 63% |
| NWR region | 7 | 2 | 29% |
| ER region | 7 | 2 | 29% |
| SCR region | 3 | 2 | 67% |
| Region 0 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion and sediment control lead | DAY | 26 | 6 (23%) | $200.00 | $100.00 | |
| Silt fence | LF | 6 | 6 (100%) | $4.19 | $4.50 | |
| Inlet protection | EACH | 17 | 5 (29%) | $150.00 | $95.00 | |
| Crushed surfacing base course | TON | 11 | 5 (45%) | $55.00 | $26.44 | |
| Beam guardrail type 31 non-flared terminal | EACH | 10 | 4 (40%) | $2,900.00 | $2,700.00 | |
| Beam guardrail type 31 | LF | 9 | 4 (44%) | $30.00 | $26.32 | |
| Directional boring | LF | 7 | 4 (57%) | $50.00 | $60.00 | |
| Plastic wide lane line | LF | 5 | 4 (80%) | $22.00 | $3.23 | |
| Plastic stop line | LF | 12 | 3 (25%) | $14.00 | $10.00 | |
| Beam guardrail anchor type 10 | EACH | 10 | 3 (30%) | $1,100.00 | $894.00 | |
| Seeding and fertilizing by hand | SY | 6 | 3 (50%) | $18.50 | $3.00 | |
| Construction signs class A | SF | 9 | 2 (22%) | $25.00 | $16.21 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Transportation Systems, Inc. | 18 | 1 of 18 |
| Mill Plain Electric, Inc. | 14 | 6 of 14 |
| Totem Electric of Tacoma, Inc. | 13 | 3 of 13 |
| Colvico, Inc. | 11 | 4 of 11 |
| Elcon Corporation | 8 | 3 of 8 |
| Aztech Electric, Inc. | 6 | 3 of 6 |
| Valley Electric Co. of MT. Ver | 5 | 2 of 5 |
| Neppel Electrical & Controls, | 5 | 3 of 5 |
| Titan Earthwork LLC | 5 | 0 of 5 |
| Signal Electric Inc. | 3 | 1 of 3 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 19 JAN 2023 | 009918 | SCR region | Sr 240 columbia center blvd - upgrade signal & illumination | 1 of 3 | $1,220,204 | Low, 34% under the second |
| 02 MAR 2022 | 009773 | NWR region | I-5 jackson st & s forest st vic fiber repair | 1 of 2 | $490,000 | Low, 31% under the second |
| 07 APR 2021 | 009665 | SWR region | I-205 sr 500 to i-205 nb ramp meter modification | 1 of 2 | $94,614 | Low, 64% under the second |
| 17 MAR 2021 | 009657 | NWR region | I-5 et al nw regionwide camera replacement | 3 of 4 | $1,824,678 | +16% |
| 24 FEB 2021 | 009644 | OR region | I-5 56th st nb on ramp meter congestion management | 1 of 4 | $372,840 | Low, 6.0% under the second |
| 03 FEB 2021 | 009645 | SWR region | I-205 nb mill plain on-ramp ramp meter | 2 of 2 | $383,151 | +3.0% |
| 21 JAN 2021 | 009637 | NCR region | Us 97 eastside oroville rd railroad crossing improvements | 1 of 3 | $288,043 | Low, 4.0% under the second |
| 15 APR 2020 | 009547 | NWR region | I-5 & sr 526 sign structure and vms replacements | 1 of 2 | $1,717,573 | Low, 10% under the second |
| 01 APR 2020 | 009538 | NWR region | I-90 highpoint to sr 18 fiber extension | 3 of 4 | $880,645 | +12% |
| 05 FEB 2020 | 009515 | OR region | Sr 512 i-5 to sr 7 eb congestion management | 1 of 7 | $406,736 | Low, 1.0% under the second |
| 08 JAN 2020 | 009507 | ER region | I-90 us 2 garden springs to broadway ave - ramp meters | 1 of 3 | $2,873,829 | Low, 3.0% under the second |
| 18 DEC 2019 | 009504 | OR region | Sr16 snake lake and union ave vms replacement | 1 of 5 | $432,110 | Low, 6.0% under the second |
| 17 APR 2019 | 009422 | NCR region | Ncr intersection improvements 2019 | 2 of 3 | $989,898 | +6.0% |
| 17 APR 2019 | 009427 | NCR region | Us 97a ped. activated warning system and improvements | 3 of 3 | $265,483 | +41% |
| 02 APR 2019 | 009420 | OR region | I-5 olympia area southbound congestion management | 1 of 2 | $927,777 | Low, 27% under the second |
| 13 MAR 2019 | 009370 | Region 0 | I-5 i-5/silver lake sb rv dump station rehabilitation - nwr | 2 of 2 | $100,000 | +27% |
| 27 FEB 2019 | 009387 | NCR region | Sr155 grand coulee bridge upgrade illumination | 2 of 4 | $380,503 | +57% |
| 28 MAR 2018 | 009240 | ER region | Sr 20 et al er curve warning sign update 2017-19 | 5 of 6 | $951,204 | +30% |
| 18 JAN 2018 | 009190 | SCR region | Sr 240 kingsgate way signalize intersection | 1 of 2 | $430,761 | Low, 29% under the second |
| 08 MAR 2017 | 009033 | NCR region | Ncr 15-17 electrical service and safety upgrade | 1 of 3 | $185,207 | Low, 24% under the second |
| 11 JAN 2017 | 009003 | SWR region | Us 97 centerville rd to yakima co variable message signs | 1 of 4 | $356,929 | Low, 6.0% under the second |
| 20 APR 2016 | 008891 | SCR region | Sr 22 sr 221 and sr 223 intersections - replace lighting systems | 2 of 2 | $118,922 | +50% |
| 06 APR 2016 | 008852 | ER region | Us 2 spotted rd to i-90 - its 16z008 | 2 of 3 | $396,542 | +5.0% |
| 07 JAN 2015 | 008695 | NCR region | Ncr its power backup and vms replacement 15b004 | 1 of 2 | $493,453 | Low, 12% under the second |
| 03 DEC 2014 | 008681 | OR region | Sr 16 vms rehabilitation update variable message signs 14c507 | 1 of 5 | $489,250 | Low, 7.0% under the second |
How this record was read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Every bid counted here matched its published total to within one dollar; WSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.