Erosion and sediment control lead, WSDOT
Low bidders on WSDOT contracts carried a median of $100.00 per DAY for this item, over the 24 months to 07 OCT 2026, across 1 low bids. Half of all 3 bids fell between $87.50 and $550.00.
- Owner
- Washington State DOT
- Item
- No code published
- Unit
- DAY
- Data through
- 07 OCT 2026
WSDOT prints this item as “ESC LEAD”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2001 | 2 | 1 | $40.00 | 17 | $100.00 |
| 2002 | 14 | 12 | $75.00 | 73 | $110.00 |
| 2003 | 19 | 15 | $60.00 | 79 | $125.00 |
| 2004 | 34 | 25 | $100.00 | 153 | $100.00 |
| 2005 | 43 | 40 | $52.50 | 164 | $100.00 |
| 2006 | 29 | 29 | $109.00 | 102 | $100.00 |
| 2007 | 43 | 37 | $150.00 | 177 | $135.00 |
| 2008 | 36 | 32 | $124.38 | 164 | $150.00 |
| 2009 | 44 | 38 | $82.50 | 272 | $100.00 |
| 2010 | 45 | 38 | $100.00 | 237 | $100.00 |
| 2011 | 38 | 32 | $85.15 | 184 | $100.00 |
| 2012 | 30 | 25 | $100.00 | 169 | $100.00 |
| 2013 | 45 | 40 | $100.00 | 193 | $100.00 |
| 2014 | 20 | 20 | $90.00 | 95 | $100.00 |
| 2015 | 25 | 25 | $75.00 | 97 | $100.00 |
| 2016 | 29 | 29 | $120.00 | 111 | $150.00 |
| 2017 | 38 | 37 | $125.00 | 140 | $124.19 |
| 2018 | 40 | 40 | $100.00 | 154 | $150.00 |
| 2019 | 26 | 25 | $200.00 | 79 | $150.00 |
| 2020 | 14 | 14 | $100.00 | 48 | $132.50 |
| 2021 | 25 | 23 | $106.77 | 86 | $124.50 |
| 2022 | 23 | 23 | $160.00 | 70 | $200.00 |
| 2023 | 22 | 22 | $100.00 | 85 | $150.00 |
| 2026 | 1 | 1 | $100.00 | 3 | $100.00 |
Bid prices as published, not adjusted for inflation.
By region
| Region | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| NWR region | 229 | $100.00 | 1,112 | $100.00 |
| OR region | 94 | $100.00 | 492 | $119.33 |
| SWR region | 78 | $100.00 | 366 | $100.00 |
| ER region | 97 | $150.00 | 350 | $150.00 |
| NCR region | 71 | $100.00 | 295 | $100.00 |
| SCR region | 45 | $125.00 | 291 | $120.00 |
| Region 9 | 7 | $87.00 | 25 | $60.00 |
Regions with at least three low bids, over all lettings.
By quantity
| Quantity (DAY) | Low bids | Low-bid median |
|---|---|---|
| 2 to 8 | 155 | $150.00 |
| 8 to 18 | 156 | $100.00 |
| 18 to 40 | 156 | $100.00 |
| 40 to 1,303 | 156 | $100.00 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Granite Construction Company | 126 | 78 (62%) |
| Lakeside Industries, Inc. | 90 | 31 (34%) |
| Wilder Construction Company | 65 | 31 (48%) |
| Central Washington Asphalt, In | 36 | 21 (58%) |
| Ceccanti, Inc. | 26 | 18 (69%) |
| Tucci & Sons, Inc. | 47 | 17 (36%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | Region | Quantity | Low bidder's price | Median | Estimate | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|---|
| 07 OCT 2026 | XE3770 | NCR region | 6 | $100.00 | $100.00 | $90.00 | 3 | Skycorp, LTD | WSDOT |
| 29 MAR 2023 | 009941 | OR region | 25 | $100.00 | $30.00 | $150.00 | 5 | Johansen Construction Company, | WSDOT |
| 29 MAR 2023 | 009954 | NWR region | 14 | $10.00 | $55.00 | $200.00 | 2 | Granite Construction Company | WSDOT |
| 29 MAR 2023 | 009953 | NCR region | 20 | $175.00 | $212.50 | $100.00 | 4 | M2 Industrial Inc. | WSDOT |
| 22 MAR 2023 | 009950 | NWR region | 15 | $50.00 | $300.00 | $221.00 | 2 | Combined Construction, Inc. | WSDOT |
| 08 MAR 2023 | 009942 | NWR region | 9 | $235.00 | $235.00 | $160.00 | 3 | Penhall Company | WSDOT |
| 01 MAR 2023 | 009935 | NWR region | 4 | $445.00 | $200.00 | $100.00 | 5 | Faber Construction Corp. | WSDOT |
| 01 MAR 2023 | 009938 | ER region | 30 | $100.00 | $155.00 | $300.00 | 2 | Central Washington Asphalt, In | WSDOT |
| 23 FEB 2023 | 009932 | NWR region | 39 | $112.00 | $106.00 | $135.00 | 4 | Faber Construction Corp. | WSDOT |
| 23 FEB 2023 | 009934 | NCR region | 25 | $82.00 | $82.00 | $150.00 | 3 | Central Washington Asphalt, Inc.Interstate Concrete & Asphalt | WSDOT |
| 01 FEB 2023 | 009916 | NWR region | 16 | $10.00 | $35.00 | $110.00 | 2 | Granite Construction Company | WSDOT |
| 01 FEB 2023 | 009930 | SWR region | 12 | $100.00 | $250.00 | $250.00 | 5 | Selby Bridge Company, Inc. | WSDOT |
| 01 FEB 2023 | 009921 | NCR region | 17 | $176.50 | $238.25 | $125.00 | 4 | Johansen Construction Company, | WSDOT |
| 25 JAN 2023 | 009910 | NWR region | 17 | $330.00 | $300.00 | $160.00 | 5 | Acme Concrete Paving, Inc. | WSDOT |
| 25 JAN 2023 | 009926 | OR region | 3 | $100.00 | $400.00 | $224.00 | 7 | Rognlin'S, Inc. | WSDOT |
Filter this item by your own quantity, region and period, or check your price against it, in the WSDOT explorer.
How these prices were read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are WSDOT's own: this item is compared with WSDOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the WSDOT letting of 07 OCT 2026 and was rebuilt on 26 NOV 2026.