Selby Bridge Company, Inc.: WSDOT bid record
Selby Bridge Company, Inc. submitted 15 bids on Washington State DOT contracts in the data, from 18 DEC 2002 to 01 FEB 2023, and was the low bidder on 5 of them (33%). When it was not low, its total sat a median +17% above the low bid.
- Owner
- Washington State DOT
- Low bid volume
- $7,970,400
- Latest bid
- 01 FEB 2023
- Data through
- 07 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2002 | 1 | 0 | 0% |
| 2005 | 1 | 1 | 100% |
| 2006 | 1 | 1 | 100% |
| 2009 | 2 | 0 | 0% |
| 2011 | 2 | 0 | 0% |
| 2012 | 1 | 0 | 0% |
| 2013 | 2 | 1 | 50% |
| 2014 | 1 | 1 | 100% |
| 2019 | 1 | 0 | 0% |
| 2020 | 1 | 0 | 0% |
| 2022 | 1 | 0 | 0% |
| 2023 | 1 | 1 | 100% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| SWR region | 11 | 4 | 36% |
| OR region | 3 | 1 | 33% |
| SCR region | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Inlet protection | EACH | 11 | 5 (45%) | $95.00 | $95.00 | |
| Construction signs class A | SF | 12 | 4 (33%) | $25.00 | $16.21 | |
| Flexible guide post | EACH | 7 | 4 (57%) | $30.00 | $33.23 | |
| Beam guardrail type 31 non-flared terminal | EACH | 7 | 4 (57%) | $2,300.00 | $2,700.00 | |
| Paint line | LF | 12 | 3 (25%) | $1.00 | $0.25 | |
| Structure excavation class B including haul | CY | 8 | 3 (38%) | $12.50 | $15.00 | |
| Silt fence | LF | 8 | 3 (38%) | $2.50 | $4.50 | |
| Bridge approach slab | SY | 6 | 3 (50%) | $195.00 | $258.00 | |
| Removing guardrail | LF | 5 | 3 (60%) | $4.00 | $5.00 | |
| Erosion and sediment control lead | DAY | 12 | 2 (17%) | $65.00 | $100.00 | |
| Roadway excavation including haul | CY | 10 | 2 (20%) | $21.50 | $20.00 | |
| Structure excavation class A including haul | CY | 9 | 2 (22%) | $25.00 | $23.50 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Cascade Bridge LLC | 11 | 8 of 11 |
| Quigg Bros., Inc. | 9 | 5 of 9 |
| Mowat Construction Company | 5 | 4 of 5 |
| Rognlin'S, Inc. | 4 | 2 of 4 |
| Hamilton Construction Co. | 4 | 1 of 4 |
| Wildish Standard Paving Co. | 4 | 1 of 4 |
| SB Structures, LLC | 4 | 2 of 4 |
| Carter & Company, Inc. DBA Car | 3 | 2 of 3 |
| Rotschy, Inc. | 3 | 2 of 3 |
| Tri-State Construction, Inc. | 3 | 1 of 3 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 01 FEB 2023 | 009930 | SWR region | I-5 koontz road bridge emergency bridge repair | 1 of 5 | $954,590 | Low, 6.0% under the second |
| 06 APR 2022 | 009795 | SWR region | Sr 506 1.5 miles n of frontage rd to i-5 emergency bridge repair | 3 of 8 | $851,557 | +2.0% |
| 01 APR 2020 | 009530 | SCR region | I-82 sr 397 interchange eb - bridge repair | 2 of 4 | $616,902 | +41% |
| 10 APR 2019 | 009419 | SWR region | Sr 506 lacamas creek bridge replacement | 7 of 8 | $4,137,787 | +28% |
| 03 DEC 2014 | 008685 | OR region | Sr 162 puyallup river bridge bridge replacement 13c521 | 1 of 15 | $5,482,395 | Low, 3.0% under the second |
| 24 APR 2013 | 008464 | SWR region | Sr 6 willapa river bridge replace bridge | 3 of 8 | $4,544,038 | +11% |
| 17 APR 2013 | 008456 | SWR region | Sr 411 tenant way to lincoln st concrete rehabilitation | 1 of 3 | $267,920 | Low, 21% under the second |
| 25 APR 2012 | 008272 | SWR region | I-5 mellen street to blakeslee junction-stage 1 | 8 of 9 | $23,679,240 | +10% |
| 02 MAR 2011 | 008079 | SWR region | Sr 500 st. johns blvd - interchange | 4 of 9 | $28,878,767 | +6.0% |
| 05 JAN 2011 | 008047 | OR region | I-5 exit 111 lacey vic. noise walls | 14 of 17 | $3,617,787 | +26% |
| 01 APR 2009 | 007681 | SWR region | Vancouver rail project 39th street bridge city of vancouver | 6 of 14 | $12,363,473 | +7.0% |
| 25 MAR 2009 | 007688 | SWR region | I5 north fork lewis river bridge southbound expansion joint | 7 of 8 | $403,683 | +23% |
| 09 FEB 2006 | 007095 | SWR region | Sr 14 lieser road bridge repair | 1 of 4 | $549,693 | Low, 3.0% under the second |
| 02 MAR 2005 | 006917 | SWR region | I-5 salmon creek to ne 129th street noise wall | 1 of 5 | $715,803 | Low, 2.0% under the second |
| 18 DEC 2002 | 006474 | OR region | Point brown bridge replacement city of ocean shores | 9 of 9 | $1,688,060 | +22% |
How this record was read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Every bid counted here matched its published total to within one dollar; WSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.