Tucci & Sons, Inc.: WSDOT bid record
Tucci & Sons, Inc. submitted 75 bids on Washington State DOT contracts in the data, from 01 MAR 2000 to 07 OCT 2026, and was the low bidder on 33 of them (44%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- Washington State DOT
- Low bid volume
- $77,485,381
- Latest bid
- 07 OCT 2026
- Data through
- 07 OCT 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2000 | 2 | 1 | 50% |
| 2001 | 2 | 1 | 50% |
| 2002 | 2 | 0 | 0% |
| 2003 | 2 | 0 | 0% |
| 2004 | 6 | 1 | 17% |
| 2005 | 4 | 2 | 50% |
| 2006 | 2 | 2 | 100% |
| 2007 | 3 | 2 | 67% |
| 2008 | 1 | 1 | 100% |
| 2009 | 5 | 1 | 20% |
| 2010 | 4 | 1 | 25% |
| 2011 | 4 | 2 | 50% |
| 2012 | 1 | 0 | 0% |
| 2013 | 2 | 1 | 50% |
| 2014 | 2 | 1 | 50% |
| 2015 | 5 | 2 | 40% |
| 2016 | 7 | 2 | 29% |
| 2017 | 4 | 3 | 75% |
| 2018 | 4 | 4 | 100% |
| 2019 | 5 | 2 | 40% |
| 2021 | 1 | 0 | 0% |
| 2022 | 3 | 3 | 100% |
| 2023 | 3 | 1 | 33% |
| 2026 | 1 | 0 | 0% |
By region
| Region | Bids | Low bids | Win rate |
|---|---|---|---|
| OR region | 48 | 19 | 40% |
| NWR region | 24 | 14 | 58% |
| SCR region | 2 | 0 | 0% |
| Region 8 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Plastic drainage marking | EACH | 58 | 39 (67%) | $30.00 | $34.00 | |
| Plastic traffic arrow | EACH | 56 | 39 (70%) | $127.50 | $135.00 | |
| Plastic stop line | LF | 50 | 35 (70%) | $9.50 | $10.00 | |
| Paint line | LF | 50 | 33 (66%) | $0.17 | $0.25 | |
| Raised pavement marker type 2 | HUND | 48 | 31 (65%) | $400.00 | $478.00 | |
| Plastic crosswalk line | SF | 40 | 27 (68%) | $5.38 | $6.00 | |
| Flexible guide post | EACH | 50 | 24 (48%) | $37.00 | $33.23 | |
| Recessed pavement marker | HUND | 33 | 20 (61%) | $988.00 | $1,500.00 | |
| Temporary pavement marking | LF | 30 | 20 (67%) | $0.10 | $0.20 | |
| Profiled plastic line | LF | 30 | 20 (67%) | $0.75 | $1.25 | |
| Plastic junction box marking | EACH | 34 | 19 (56%) | $31.00 | $37.00 | |
| Plastic traffic letter | EACH | 28 | 18 (64%) | $81.25 | $65.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Lakeside Industries, Inc. | 39 | 7 of 39 |
| Miles Resources, LLC | 23 | 3 of 23 |
| Woodworth & Company, Inc | 21 | 7 of 21 |
| Granite Construction Company | 14 | 4 of 14 |
| Icon Materials DBA CPM Develop | 13 | 3 of 13 |
| Ceccanti, Inc. | 12 | 5 of 12 |
| Wilder Construction Company | 11 | 4 of 11 |
| Scarsella Bros., Inc. | 11 | 9 of 11 |
| Watson Asphalt Paving Company, | 10 | 1 of 10 |
| Tri-State Construction, Inc. | 10 | 8 of 10 |
Latest bids
| Let | Contract | Region | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 07 OCT 2026 | XE3773 | OR region | Sr 20 Us 101 I/S To N Of Fairmount Rd Hfst | 4 of 6 | $497,932 | +40% |
| 29 MAR 2023 | 009941 | OR region | Sr 166 bay st./bethel ave./maple ave. intersection - roundabout | 2 of 6 | $1,518,347 | +5.0% |
| 08 MAR 2023 | 009942 | NWR region | I 5 nb 206th st vic to sr 516 pavement repair | 3 of 3 | $976,491 | +42% |
| 01 FEB 2023 | 009928 | OR region | Sr 7 unnamed tribs to s creek remove fish barriers & paving | 1 of 4 | $5,316,023 | Low, 5.0% under the second |
| 13 APR 2022 | 009781 | NWR region | Sr 18 & sr 99 & sr 516 jenkins ck vic & tukwila vic & sr 181 vic paving & deck rehab & ada | 1 of 4 | $8,793,458 | Low, 9.0% under the second |
| 23 MAR 2022 | 009771 | OR region | Sr 7 sr 507 to s of s 38th st paving | 1 of 3 | $1,623,410 | Low, 3.0% under the second |
| 02 MAR 2022 | 009772 | OR region | Us 101 delphi rd to i-5 paving and concrete barrier | 1 of 3 | $1,602,396 | Low, 9.0% under the second |
| 24 MAR 2021 | 009636 | OR region | Sr 167 sr 410 to sr 18 congestion management | 2 of 4 | $25,439,952 | +12% |
| 03 APR 2019 | 009411 | OR region | Sr 8 us 12 to w of wilson rd paving | 3 of 3 | $4,375,177 | +24% |
| 13 MAR 2019 | 009384 | OR region | I-5 plum st to s tacoma way paving | 2 of 3 | $2,490,373 | +11% |
| 06 MAR 2019 | 009397 | NWR region | Sr 99 pierce county line to s 359th st vic paving | 1 of 4 | $868,800 | Low, 13% under the second |
| 30 JAN 2019 | 009373 | OR region | Sr 507 n of rainier to jct sr 7 paving | 2 of 4 | $2,786,204 | +19% |
| 16 JAN 2019 | 009371 | OR region | Kitsap area paving and ada compliance - 2019 | 1 of 4 | $5,710,465 | Low, 16% under the second |
| 04 APR 2018 | 009239 | NWR region | Sr 99 & sr 509 s cloverdale st to duwamish river paving and ada compliance | 1 of 3 | $4,747,016 | Low, 9.0% under the second |
| 04 APR 2018 | 009230 | OR region | Sr 167 milwaukee ave to s of pierce co line - paving | 1 of 4 | $1,319,062 | Low, 4.0% under the second |
| 22 FEB 2018 | 009212 | NWR region | Sr 18 et al wb w valley hwy vic to se 231st st paving & ada compliance | 1 of 4 | $6,632,869 | Low, 13% under the second |
| 14 FEB 2018 | 009182 | NWR region | Sr 164 sr 18 to 17th st se paving and ada compliance | 1 of 5 | $2,373,741 | Low, 12% under the second |
| 12 APR 2017 | 009056 | OR region | Sr 162 sr 410 to s of 96th st e paving and ada compliance | 1 of 3 | $1,433,934 | Low, 6.0% under the second |
| 29 MAR 2017 | 009051 | NWR region | Sr 509 s 168th st to s 112th st vic - nb paving and ada compliance | 1 of 2 | $3,246,925 | Low, 23% under the second |
| 23 FEB 2017 | 009021 | OR region | I-5 n of maytown rd to martin way paving | 1 of 4 | $4,013,437 | Low, 5.0% under the second |
| 05 JAN 2017 | 009000 | OR region | Sr 167 sw of grandview ave to w of 87th ave e - paving | 2 of 4 | $794,821 | +6.0% |
| 21 DEC 2016 | 008994 | NWR region | Sr 410 white river bridge to sr 164 paving & ada compliance | 1 of 4 | $1,477,308 | Low, 35% under the second |
| 21 DEC 2016 | 008993 | OR region | I-5 mounts rd to center dr auxiliary lane extension | 2 of 9 | $7,892,350 | 0.0% |
| 20 APR 2016 | 008883 | NWR region | I-5 s 200th st / military rd intersection improvements 15a011 | 2 of 6 | $2,202,504 | 0.0% |
| 13 APR 2016 | 008872 | OR region | Sr 509 and i-705 schuster parkway to e 11th st paving 15c519 | 1 of 1 | $1,562,279 | Low |
How this record was read
WSDOT bid tabulation PDFs, one per contract: 2026 tabulations from wsdot.wa.gov and the legacy Bid Check and Bid Tabulation reports of 1999 to 2023. 2000 to 2003 lettings use metric units. Only bids matching their published total are kept.
- Every bid counted here matched its published total to within one dollar; WSDOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.