WSDOT letting results, February 23, 2023
4 contracts let by Washington State DOT on February 23, 2023, $81,014,890 in low bids, a median of 3.5 bidders per contract. On the 4 with an engineer's estimate, the low bid came in under it 2 times; median low bid +4.0% against the estimate.
- Owner
- Washington State DOT
- Contracts
- 4
- Low bids, total
- $81,014,890
- Data through
- 07 OCT 2026
Contracts let that day
| Contract | Project | Region | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 009925 | Us 395 nsc spokane river crossing | ER region | 2 of 4 | Max J. Kuney Company | $68,633,025 | -3.0% | WSDOT | ||
| 009934 | Us 2 & us 97 leavenworth & n of blewett pass paving | NCR region | 3 | Central Washington Asphalt, Inc.Interstate Concrete & Asphalt | $9,777,000 | $10,081,827 | +3.0% | -3.0% | WSDOT |
| 009932 | Sr 530 59th ave ne & 211th pl ne intersection improvements | NWR region | 4 | Faber Construction Corp. | $1,645,171 | $1,895,124 | +15% | +10% | WSDOT |
| 009939 | Sr 525 clinton ferry terminal paving preservation | Region 9 | 3 | Lakeside Industries, Inc. | $959,695 | $1,071,967 | +12% | +50% | WSDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than WSDOT received, the others did not match their published totals and are left out.