WisDOT contract 20250211012 bid tabulation
5991-07-61. Let by Wisconsin DOT on February 11, 2025, La Crosse. 4 bids received; low bid $2,258,194 by Chippewa Concrete Services, Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 FEB 2025
- Pay items
- 167
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Chippewa Concrete Services, Inc. | $2,258,194 | Low |
| 2 | Gerke Excavating Inc | $2,302,325 | +2.0% |
| 3 | Integrity Grading and Excavating, Inc. | $2,465,875 | +9.0% |
| 4 | A-1 Excavating LLC | $2,473,701 | +10% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Chippewa Concrete Services, Inc. | 2. Gerke Excavating Inc | 3. Integrity Grading and Excavating, Inc. | 4. A-1 Excavating LLC |
|---|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 5,691 | $5.85 | $5.79 | $1.35 | $6.00 |
| 2 | Removing curb (204.0130) | LF | 154 | $1.95 | $1.93 | $8.00 | $8.00 |
| 3 | Removing curb & gutter (204.0150) | LF | 641 | $2.76 | $2.73 | $8.25 | $6.00 |
| 4 | Removing concrete sidewalk (204.0155) | SY | 561 | $3.32 | $3.28 | $6.00 | $8.00 |
| 5 | Removing concrete bases (204.0195) | EACH | 17 | $193.88 | $191.77 | $290.00 | $225.00 |
| 6 | Removing manholes (204.0210) | EACH | 7 | $554.25 | $548.22 | $700.00 | $700.00 |
| 7 | Removing catch basins (204.0215) | EACH | 12 | $492.15 | $486.80 | $700.00 | $525.00 |
| 8 | Removing storm sewer (size) 01. 12-inch (204.0245) | LF | 1,038 | $2.80 | $2.77 | $36.00 | $17.00 |
| 9 | Sealing pipes (204.0280) | EACH | 7 | $1,402.10 | $1,386.84 | $530.00 | $300.00 |
| 10 | Removing (item description) 01. bollards (204.9060.S) | EACH | 8 | $294.10 | $290.90 | $150.00 | $170.00 |
| 11 | Removing (item description) 02. LA crosse water valves (204.9060.S) | EACH | 6 | $389.78 | $385.54 | $779.00 | $370.00 |
| 12 | Removing (item description) 03. LA crosse hydrant (204.9060.S) | EACH | 2 | $1,169.34 | $1,156.62 | $2,020.00 | $670.00 |
| 13 | Removing (item description) 04. LA crosse light pole (MS) (204.9060.S) | EACH | 26 | $296.48 | $293.25 | $293.25 | $570.00 |
| 14 | Removing (item description) 05. LA crosse light pole (CH) (204.9060.S) | EACH | 5 | $306.81 | $303.47 | $303.47 | $740.00 |
| 15 | Removing (item description) 06. LA crosse lighting cabinet (204.9060.S) | EACH | 1 | $811.09 | $802.27 | $802.27 | $1,410.00 |
| 16 | Removing (item description) 07. LA crosse sanitary manhole (204.9060.S) | EACH | 3 | $646.63 | $639.59 | $31,000 | $1,640.00 |
| 17 | Removing (item description) 01. LA crosse water main (6-inch) (204.9090.S) | LF | 24 | $34.13 | $33.76 | $34.00 | $17.00 |
| 18 | Removing (item description) 02. LA crosse water main (8-inch) (204.9090.S) | LF | 17 | $48.18 | $47.66 | $36.00 | $17.00 |
| 19 | Removing (item description) 03. LA crosse water main (12-inch) (204.9090.S) | LF | 464 | $3.53 | $3.49 | $30.00 | $17.00 |
| 20 | Removing (item description) 04. LA crosse water main (20-inch) (204.9090.S) | LF | 26 | $31.50 | $31.16 | $33.00 | $28.00 |
| 21 | Removing (item description) 05. trench drain (204.9090.S) | LF | 10 | $81.91 | $81.02 | $43.00 | $23.00 |
| 22 | Excavation common (205.0100) | CY | 3,692 | $16.84 | $16.66 | $19.00 | $15.00 |
| 23 | Prepare foundation for asphaltic paving (project) 01. 5991-07-61 (211.0101) | EACH | 1 | $801.88 | $638.54 | $500.00 | $1,700.00 |
| 24 | Prepare foundation for concrete pavement (project) 01. 5991-07-61 (211.0201) | EACH | 1 | $7,582.50 | $7,890.91 | $100.00 | $9,000.00 |
| 25 | Finishing roadway (project) 01. 5991-07-61 (213.0100) | EACH | 1 | $3,538.50 | $3,879.09 | $500.00 | $500.00 |
| 26 | Base aggregate dense 3/4-inch (305.0110) | TON | 360 | $48.77 | $48.24 | $42.00 | $30.00 |
| 27 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 2,496 | $23.19 | $22.94 | $28.00 | $24.00 |
| 28 | Select crushed material (312.0110) | TON | 732 | $22.56 | $22.31 | $24.00 | $27.00 |
| 29 | Coloring concrete wisdot red (405.0100) | CY | 4 | $101.96 | $147.40 | $147.40 | $167.00 |
| 30 | Concrete pavement 7-inch (415.0070) | SY | 5,768 | $65.43 | $60.61 | $60.61 | $69.00 |
| 31 | Concrete pavement gaps (415.0210) | EACH | 1 | $505.50 | $752.16 | $752.16 | $850.00 |
| 32 | Concrete pavement hes 8-inch (415.1080) | SY | 114 | $87.81 | $62.50 | $62.50 | $71.00 |
| 33 | Drilled tie bars (416.0610) | EACH | 38 | $16.21 | $9.69 | $9.69 | $11.00 |
| 34 | Drilled dowel bars (416.0620) | EACH | 30 | $20.82 | $14.16 | $14.16 | $16.00 |
| 35 | Tack coat (455.0605) | GAL | 48 | $5.84 | $5.78 | $5.78 | $7.00 |
| 36 | Asphaltic surface (465.0105) | TON | 90 | $228.24 | $225.76 | $225.76 | $256.00 |
| 37 | Concrete collars for pipe (520.8000) | EACH | 7 | $738.14 | $730.11 | $180.00 | $900.00 |
| 38 | Concrete curb & gutter 30-inch type K (601.0417) | LF | 1,351 | $25.22 | $20.88 | $20.88 | $25.00 |
| 39 | Concrete curb & gutter 30-inch type L (601.0419) | LF | 153 | $25.22 | $24.21 | $24.21 | $29.00 |
| 40 | Concrete curb pedestrian (601.0600) | LF | 319 | $47.43 | $55.47 | $55.47 | $63.00 |
| 41 | Concrete sidewalk 5-inch (602.0410) | SF | 1,862 | $14.91 | $5.39 | $5.39 | $7.00 |
| 42 | Curb ramp detectable warning field natural patina (602.0515) | SF | 212 | $61.04 | $48.80 | $48.80 | $55.00 |
| 43 | Concrete driveway 7-inch (602.0815) | SY | 172 | $73.57 | $60.42 | $60.42 | $81.00 |
| 44 | Storm sewer pipe reinforced concrete class II 24-inch (608.0224) | LF | 194 | $98.06 | $96.94 | $100.00 | $97.00 |
| 45 | Storm sewer pipe reinforced concrete class II 27-inch (608.0227) | LF | 579.90 | $130.38 | $128.91 | $124.00 | $125.00 |
| 46 | Storm sewer pipe reinforced concrete class II 30-inch (608.0230) | LF | 84.10 | $144.80 | $143.16 | $165.00 | $152.00 |
| 47 | Storm sewer pipe reinforced concrete class III 12-inch (608.0312) | LF | 390.20 | $77.54 | $76.67 | $87.00 | $78.00 |
| 48 | Storm sewer pipe reinforced concrete class III 15-inch (608.0315) | LF | 76 | $119.30 | $117.97 | $91.00 | $84.00 |
| 49 | Storm sewer pipe reinforced concrete class III 18-inch (608.0318) | LF | 83.20 | $131.50 | $130.03 | $85.00 | $84.00 |
| 50 | Storm sewer pipe reinforced concrete class III 24-inch (608.0324) | LF | 531 | $97.00 | $95.89 | $100.00 | $90.00 |
| 51 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 48.50 | $81.42 | $80.49 | $87.00 | $79.00 |
| 52 | Storm sewer pipe reinforced concrete class IV 18-inch (608.0418) | LF | 69.90 | $83.79 | $82.85 | $85.00 | $85.00 |
| 53 | Insulation board polystyrene (inch) 01. 2-inch (612.0902.S) | SY | 18 | $43.22 | $42.75 | $21.33 | $48.00 |
| 54 | Mobilization (619.1000) | EACH | 1 | $142,566 | $278,028 | $188,000 | $212,000 |
| 55 | Water (624.0100) | MGAL | 51.40 | $37.60 | $37.19 | $40.00 | $35.00 |
| 56 | Topsoil (625.0100) | SY | 1,341 | $8.65 | $8.56 | $24.00 | $8.00 |
| 57 | Mobilizations erosion control (628.1905) | EACH | 3 | $102.11 | $101.00 | $101.00 | $115.00 |
| 58 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $203.21 | $201.00 | $201.00 | $225.00 |
| 59 | Inlet protection type A (628.7005) | EACH | 29 | $101.10 | $100.00 | $100.00 | $115.00 |
| 60 | Inlet protection type B (628.7010) | EACH | 5 | $70.77 | $70.00 | $70.00 | $79.00 |
| 61 | Inlet protection type C (628.7015) | EACH | 45 | $50.55 | $50.00 | $50.00 | $56.00 |
| 62 | Tracking pads (628.7560) | EACH | 6 | $1,786.59 | $1,767.15 | $1,000.00 | $500.00 |
| 63 | Rock bags (628.7570) | EACH | 20 | $8.09 | $8.00 | $8.00 | $9.00 |
| 64 | Fertilizer type B (629.0210) | CWT | 2 | $151.65 | $150.00 | $150.00 | $170.00 |
| 65 | Sod water (631.0300) | MGAL | 30 | $25.28 | $25.00 | $25.00 | $28.00 |
| 66 | Sod lawn (631.1000) | SY | 1,341 | $10.04 | $9.93 | $9.93 | $11.00 |
| 67 | Signs type II reflective H (637.2210) | SF | 50 | $31.34 | $31.00 | $31.00 | $35.00 |
| 68 | Moving signs type II (638.2102) | EACH | 19 | $151.65 | $150.00 | $150.00 | $170.00 |
| 69 | Removing signs type II (638.2602) | EACH | 23 | $35.39 | $35.00 | $35.00 | $40.00 |
| 70 | Removing small sign supports (638.3000) | EACH | 4 | $35.39 | $35.00 | $35.00 | $40.00 |
| 71 | Field office type C (642.5201) | EACH | 1 | $7,582.50 | $10,072 | $15,000 | $9,000.00 |
| 72 | Traffic control drums (643.0300) | DAY | 144 | $2.12 | $2.10 | $2.10 | $2.50 |
| 73 | Traffic control barricades type III (643.0420) | DAY | 2,678 | $0.51 | $0.50 | $0.50 | $0.60 |
| 74 | Traffic control warning lights type A (643.0705) | DAY | 2,678 | $0.12 | $0.12 | $0.12 | $0.15 |
| 75 | Traffic control signs (643.0900) | DAY | 3,145 | $0.56 | $0.55 | $0.55 | $0.60 |
| 76 | Traffic control signs fixed message (643.1000) | SF | 52.50 | $40.44 | $40.00 | $40.00 | $45.00 |
| 77 | Traffic control signs PCMS (643.1050) | DAY | 28 | $25.28 | $25.00 | $25.00 | $28.00 |
| 78 | Temporary marking line removable tape 6-inch (643.3180) | LF | 340 | $2.93 | $2.90 | $2.90 | $3.50 |
| 79 | Traffic control (643.5000) | EACH | 1 | $9,604.50 | $9,500.00 | $9,500.00 | $16,000 |
| 80 | Temporary pedestrian surface matting (644.1440) | SF | 962 | $5.06 | $5.00 | $5.00 | $6.00 |
| 81 | Temporary pedestrian curb ramp (644.1601) | DAY | 283 | $9.10 | $9.00 | $9.00 | $10.00 |
| 82 | Temporary pedestrian detectable warning field (644.1605) | SF | 180 | $15.17 | $15.00 | $15.00 | $17.00 |
| 83 | Temporary pedestrian barricade (644.1810) | LF | 3,234 | $5.31 | $5.25 | $5.25 | $6.00 |
| 84 | Geotextile type DF schedule A (645.0111) | SY | 554 | $2.93 | $2.90 | $1.26 | $3.00 |
| 85 | Marking curb epoxy (646.8120) | LF | 531 | $7.08 | $7.00 | $7.00 | $8.00 |
| 86 | Construction staking storm sewer (650.4000) | EACH | 41 | $101.10 | $200.00 | $100.00 | $113.00 |
| 87 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 153 | $4.04 | $4.00 | $4.00 | $5.00 |
| 88 | Construction staking concrete pavement (650.7000) | LF | 1,359 | $4.04 | $5.00 | $4.00 | $5.00 |
| 89 | Construction staking electrical installations (project) 01. 5991-07- 62 (650.8501) | EACH | 1 | $2,881.35 | $1,000.00 | $2,850.00 | $3,200.00 |
| 90 | Construction staking curb ramps (650.9000) | EACH | 8 | $111.21 | $10.00 | $110.00 | $125.00 |
| 91 | Construction staking sidewalk (project) 01. 5991-07-61 (650.9500) | EACH | 1 | $505.50 | $2,000.00 | $500.00 | $565.00 |
| 92 | Construction staking supplemental control (project) 01. 5991-07-61 (650.9911) | EACH | 1 | $1,516.50 | $3,000.00 | $1,500.00 | $1,700.00 |
| 93 | Construction staking slope stakes (650.9920) | LF | 1,359 | $1.01 | $1.00 | $1.00 | $1.20 |
| 94 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 4,237 | $7.53 | $7.45 | $7.45 | $11.00 |
| 95 | Install conduit into existing item (652.0700.S) | EACH | 19 | $477.24 | $472.05 | $472.05 | $395.00 |
| 96 | Pull boxes non-conductive 24X42- inch (653.0164) | EACH | 8 | $2,171.83 | $2,148.20 | $2,148.20 | $2,933.00 |
| 97 | Adjusting pull boxes (653.0900) | EACH | 7 | $525.35 | $519.63 | $519.63 | $508.00 |
| 98 | Removing pull boxes (653.0905) | EACH | 3 | $275.61 | $272.61 | $272.61 | $339.00 |
| 99 | Electrical wire lighting 12 AWG (655.0610) | LF | 2,846 | $4.99 | $4.94 | $4.94 | $2.00 |
| 100 | Sawing asphalt (690.0150) | LF | 169 | $1.97 | $1.69 | $1.69 | $3.00 |
| 101 | Sawing concrete (690.0250) | LF | 1,613 | $2.58 | $2.50 | $2.50 | $3.00 |
| 102 | Incentive compressive strength concrete pavement (715.0720) | DOL | 1,692 | $1.00 | $1.00 | $1.00 | $1.00 |
| 103 | Crack and damage survey 01. (17- 20174-80) (999.1501.S) | EACH | 1 | $252.75 | $1,400.00 | $1,400.00 | $1,600.00 |
| 104 | Crack and damage survey 02. (17- 20175-10) (999.1501.S) | EACH | 1 | $252.75 | $300.00 | $300.00 | $350.00 |
| 105 | Crack and damage survey 03. (17- 20175-20) (999.1501.S) | EACH | 1 | $252.75 | $2,400.00 | $2,400.00 | $2,700.00 |
| 106 | Crack and damage survey 04. (17- 20174-40) (999.1501.S) | EACH | 1 | $252.75 | $700.00 | $700.00 | $800.00 |
| 107 | Crack and damage survey 05. (17- 20176-10) (999.1501.S) | EACH | 1 | $252.75 | $700.00 | $700.00 | $800.00 |
| 108 | Crack and damage survey 06. (17- 20176-20) (999.1501.S) | EACH | 1 | $252.75 | $1,400.00 | $1,400.00 | $1,600.00 |
| 109 | Crack and damage survey 07. (17- 20176-30) (999.1501.S) | EACH | 1 | $252.75 | $900.00 | $900.00 | $1,000.00 |
| 110 | Crack and damage survey 08. (17- 20176-40) (999.1501.S) | EACH | 1 | $252.75 | $900.00 | $900.00 | $1,000.00 |
| 111 | Crack and damage survey 09. (17- 20174-10) (999.1501.S) | EACH | 1 | $252.75 | $3,000.00 | $3,000.00 | $3,400.00 |
| 112 | Crack and damage survey 10. (17- 20176-50) (999.1501.S) | EACH | 1 | $252.75 | $900.00 | $900.00 | $1,000.00 |
| 113 | Crack and damage survey 11. (17- 20176-70) (999.1501.S) | EACH | 1 | $252.75 | $500.00 | $500.00 | $600.00 |
| 114 | Crack and damage survey 12. (17- 40377-(10-234)) (999.1501.S) | EACH | 1 | $252.75 | $1,800.00 | $1,800.00 | $2,000.00 |
| 115 | Crack and damage survey 13. (17- 20164-70) (999.1501.S) | EACH | 1 | $252.75 | $700.00 | $700.00 | $800.00 |
| 116 | Crack and damage survey 14. (17- 20164-60) (999.1501.S) | EACH | 1 | $252.75 | $500.00 | $500.00 | $600.00 |
| 117 | Crack and damage survey 15. (17- 20165-20) (999.1501.S) | EACH | 1 | $252.75 | $900.00 | $900.00 | $1,000.00 |
| 118 | Crack and damage survey 16. (17- 20164-50) (999.1501.S) | EACH | 1 | $252.75 | $900.00 | $900.00 | $1,000.00 |
| 119 | Crack and damage survey 17. (17- 20165-10) (999.1501.S) | EACH | 1 | $252.75 | $900.00 | $900.00 | $1,000.00 |
| 120 | Crack and damage survey 18. (17- 20164-40) (999.1501.S) | EACH | 1 | $252.75 | $700.00 | $700.00 | $800.00 |
| 121 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,000 | $5.00 | $5.00 | $5.00 | $5.00 |
| 122 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 1,320 | $5.00 | $5.00 | $5.00 | $5.00 |
| 123 | Special 01. 4' LA crosse storm manhole (SPV.0060) | EACH | 6 | $3,744.10 | $3,703.36 | $4,800.00 | $3,900.00 |
| 124 | Special 02. 5' LA crosse storm manhole (SPV.0060) | EACH | 6 | $6,631.20 | $6,559.05 | $6,800.00 | $7,200.00 |
| 125 | Special 03. LA crosse catch basin (SPV.0060) | EACH | 29 | $3,812.04 | $3,770.56 | $4,000.00 | $3,000.00 |
| 126 | Special 04. LA crosse manhole cover (SPV.0060) | EACH | 11 | $360.81 | $356.88 | $265.00 | $800.00 |
| 127 | Special 05. LA crosse catch basin cover type A (SPV.0060) | EACH | 26 | $360.54 | $356.62 | $265.00 | $600.00 |
| 128 | Special 06. LA crosse catch basin cover type C (SPV.0060) | EACH | 3 | $362.23 | $358.29 | $265.00 | $600.00 |
| 129 | Special 07. mini-storm sewer (SPV.0060) | EACH | 1 | $2,342.47 | $2,316.98 | $12,000 | $1,100.00 |
| 130 | Special 08. LA crosse gate valve (6-inch) (SPV.0060) | EACH | 2 | $2,310.65 | $2,285.51 | $1,853.00 | $2,700.00 |
| 131 | Special 09. LA crosse gate valve (8-inch) (SPV.0060) | EACH | 3 | $3,002.13 | $2,969.47 | $2,831.00 | $3,800.00 |
| 132 | Special 10. LA crosse gate valve (12-inch) (SPV.0060) | EACH | 2 | $5,334.43 | $5,276.39 | $4,733.00 | $6,600.00 |
| 133 | Special 11. LA crosse gate valve (16-inch) (SPV.0060) | EACH | 2 | $20,445 | $20,222 | $16,000 | $18,000 |
| 134 | Special 12. LA crosse gate valve (20-inch) (SPV.0060) | EACH | 2 | $22,986 | $22,736 | $22,494 | $31,000 |
| 135 | Special 13. LA crosse hydrant and valve group (6' bury) (SPV.0060) | EACH | 2 | $6,088.10 | $6,021.86 | $7,510.00 | $7,800.00 |
| 136 | Special 15. adjust water valve (SPV.0060) | EACH | 2 | $613.00 | $606.33 | $370.00 | $300.00 |
| 137 | Special 16. adjust curb stop (SPV.0060) | EACH | 11 | $355.84 | $351.97 | $285.00 | $200.00 |
| 138 | Special 17. replace 4' LA crosse sanitary manhole (SPV.0060) | EACH | 3 | $14,924 | $14,762 | $56,000 | $36,000 |
| 139 | Special 18. outside drop (SPV.0060) | EACH | 7 | $5,878.03 | $5,814.08 | $1,080.00 | $4,000.00 |
| 140 | Special 19. reconnect sanitary lateral (SPV.0060) | EACH | 2 | $5,198.38 | $5,141.82 | $8,045.00 | $7,000.00 |
| 141 | Special 20. abandon sanitary lateral (SPV.0060) | EACH | 6 | $405.53 | $401.12 | $2,711.00 | $700.00 |
| 142 | Special 21. sanitary manhole cover (SPV.0060) | EACH | 3 | $362.23 | $358.29 | $265.00 | $1,350.00 |
| 143 | Special 22. SDR26/PS115 PVC sanitary sewer cap (12-inch) (SPV.0060) | EACH | 3 | $538.79 | $532.93 | $818.00 | $400.00 |
| 144 | Special 23. marking bike symbol grooved (epoxy) (SPV.0060) | EACH | 12 | $480.23 | $475.00 | $475.00 | $550.00 |
| 145 | Special 24. utility line opening ulo (SPV.0060) | EACH | 8 | $1,167.98 | $1,155.27 | $533.00 | $400.00 |
| 146 | Special 25. posts steel U-channel 14-FT (SPV.0060) | EACH | 10 | $328.58 | $325.00 | $325.00 | $370.00 |
| 147 | Special 26. install V-loc sign support (SPV.0060) | EACH | 10 | $151.65 | $150.00 | $150.00 | $170.00 |
| 148 | Special 27. connect to existing (SPV.0060) | EACH | 2 | $580.31 | $574.00 | $5,700.00 | $570.00 |
| 149 | Special 28. concrete base complete (MS) (SPV.0060) | EACH | 23 | $716.35 | $708.56 | $708.56 | $1,440.00 |
| 150 | Special 29. install light pole complete (MS) (SPV.0060) | EACH | 38 | $890.28 | $880.59 | $880.59 | $1,470.00 |
| 151 | Special 30. tree protection (SPV.0060) | EACH | 10 | $353.85 | $350.00 | $350.00 | $400.00 |
| 152 | Special 31. construction staking watermain system - project 5991- 07-62 (SPV.0060) | EACH | 1 | $960.45 | $2,000.00 | $950.00 | $1,100.00 |
| 153 | Special 32. construction staking sanitary sewer system - project 5991-07-62 (SPV.0060) | EACH | 1 | $505.50 | $2,000.00 | $500.00 | $600.00 |
| 154 | Special 01. marking line epoxy grooved 4-inch (SPV.0090) | LF | 446 | $4.04 | $4.00 | $4.00 | $5.00 |
| 155 | Special 02. marking line epoxy grooved 8-inch (SPV.0090) | LF | 3,298 | $5.06 | $5.00 | $5.00 | $5.70 |
| 156 | Special 03. marking crosswalk epoxy grooved transverse line 12- inch (SPV.0090) | LF | 762 | $23.25 | $23.00 | $23.00 | $26.00 |
| 157 | Special 04. marking line stop bar epoxy grooved transverse line 12- inch (SPV.0090) | LF | 170 | $23.25 | $23.00 | $23.00 | $26.00 |
| 158 | Special 05. LA crosse dip water main (6-inch) (SPV.0090) | LF | 20 | $148.91 | $147.29 | $80.00 | $115.00 |
| 159 | Special 06. LA crosse dip water main (8-inch) (SPV.0090) | LF | 28 | $506.58 | $501.07 | $195.00 | $290.00 |
| 160 | Special 07. LA crosse dip water main (12-inch) (SPV.0090) | LF | 464 | $159.78 | $158.04 | $215.00 | $130.00 |
| 161 | Special 08. LA crosse dip water main (20-inch) (SPV.0090) | LF | 26 | $1,270.78 | $1,256.95 | $1,000.00 | $1,400.00 |
| 162 | Special 09. SDR26/PS115 PVC sanitary sewer pipe (12-inch) (SPV.0090) | LF | 187 | $90.70 | $89.67 | $150.00 | $200.00 |
| 163 | Special 10. SDR26/PS115 PVC sanitary sewer pipe (20-inch) (SPV.0090) | LF | 40 | $1,029.56 | $1,018.32 | $250.00 | $900.00 |
| 164 | Special 11. reconnect LA crosse water service line (1-inch) (SPV.0090) | LF | 30 | $150.79 | $149.15 | $100.00 | $400.00 |
| 165 | Special 12. concrete curb integral type K (SPV.0090) | LF | 1,283 | $43.10 | $8.70 | $8.70 | $10.00 |
| 166 | Special 01. remove, palletize, and deliver or store brick pavers (SPV.0165) | SF | 6,160 | $3.97 | $3.93 | $3.93 | $4.50 |
| 167 | Special 02. brick paver system complete (LA crosse pattern) (SPV.0165) | SF | 4,986 | $17.72 | $17.53 | $17.53 | $20.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.