WisDOT contract 20250211012 bid tabulation

5991-07-61. Let by Wisconsin DOT on February 11, 2025, La Crosse. 4 bids received; low bid $2,258,194 by Chippewa Concrete Services, Inc..

Owner
Wisconsin DOT
Letting
11 FEB 2025
Pay items
167
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Chippewa Concrete Services, Inc.$2,258,194Low
2Gerke Excavating Inc$2,302,325+2.0%
3Integrity Grading and Excavating, Inc.$2,465,875+9.0%
4A-1 Excavating LLC$2,473,701+10%
WisDOT contract 20250211012: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Chippewa Concrete Services, Inc.2. Gerke Excavating Inc3. Integrity Grading and Excavating, Inc.4. A-1 Excavating LLC
1Removing concrete pavement (204.0100)SY5,691$5.85$5.79$1.35$6.00
2Removing curb (204.0130)LF154$1.95$1.93$8.00$8.00
3Removing curb & gutter (204.0150)LF641$2.76$2.73$8.25$6.00
4Removing concrete sidewalk (204.0155)SY561$3.32$3.28$6.00$8.00
5Removing concrete bases (204.0195)EACH17$193.88$191.77$290.00$225.00
6Removing manholes (204.0210)EACH7$554.25$548.22$700.00$700.00
7Removing catch basins (204.0215)EACH12$492.15$486.80$700.00$525.00
8Removing storm sewer (size) 01. 12-inch (204.0245)LF1,038$2.80$2.77$36.00$17.00
9Sealing pipes (204.0280)EACH7$1,402.10$1,386.84$530.00$300.00
10Removing (item description) 01. bollards (204.9060.S)EACH8$294.10$290.90$150.00$170.00
11Removing (item description) 02. LA crosse water valves (204.9060.S)EACH6$389.78$385.54$779.00$370.00
12Removing (item description) 03. LA crosse hydrant (204.9060.S)EACH2$1,169.34$1,156.62$2,020.00$670.00
13Removing (item description) 04. LA crosse light pole (MS) (204.9060.S)EACH26$296.48$293.25$293.25$570.00
14Removing (item description) 05. LA crosse light pole (CH) (204.9060.S)EACH5$306.81$303.47$303.47$740.00
15Removing (item description) 06. LA crosse lighting cabinet (204.9060.S)EACH1$811.09$802.27$802.27$1,410.00
16Removing (item description) 07. LA crosse sanitary manhole (204.9060.S)EACH3$646.63$639.59$31,000$1,640.00
17Removing (item description) 01. LA crosse water main (6-inch) (204.9090.S)LF24$34.13$33.76$34.00$17.00
18Removing (item description) 02. LA crosse water main (8-inch) (204.9090.S)LF17$48.18$47.66$36.00$17.00
19Removing (item description) 03. LA crosse water main (12-inch) (204.9090.S)LF464$3.53$3.49$30.00$17.00
20Removing (item description) 04. LA crosse water main (20-inch) (204.9090.S)LF26$31.50$31.16$33.00$28.00
21Removing (item description) 05. trench drain (204.9090.S)LF10$81.91$81.02$43.00$23.00
22Excavation common (205.0100)CY3,692$16.84$16.66$19.00$15.00
23Prepare foundation for asphaltic paving (project) 01. 5991-07-61 (211.0101)EACH1$801.88$638.54$500.00$1,700.00
24Prepare foundation for concrete pavement (project) 01. 5991-07-61 (211.0201)EACH1$7,582.50$7,890.91$100.00$9,000.00
25Finishing roadway (project) 01. 5991-07-61 (213.0100)EACH1$3,538.50$3,879.09$500.00$500.00
26Base aggregate dense 3/4-inch (305.0110)TON360$48.77$48.24$42.00$30.00
27Base aggregate dense 1 1/4-inch (305.0120)TON2,496$23.19$22.94$28.00$24.00
28Select crushed material (312.0110)TON732$22.56$22.31$24.00$27.00
29Coloring concrete wisdot red (405.0100)CY4$101.96$147.40$147.40$167.00
30Concrete pavement 7-inch (415.0070)SY5,768$65.43$60.61$60.61$69.00
31Concrete pavement gaps (415.0210)EACH1$505.50$752.16$752.16$850.00
32Concrete pavement hes 8-inch (415.1080)SY114$87.81$62.50$62.50$71.00
33Drilled tie bars (416.0610)EACH38$16.21$9.69$9.69$11.00
34Drilled dowel bars (416.0620)EACH30$20.82$14.16$14.16$16.00
35Tack coat (455.0605)GAL48$5.84$5.78$5.78$7.00
36Asphaltic surface (465.0105)TON90$228.24$225.76$225.76$256.00
37Concrete collars for pipe (520.8000)EACH7$738.14$730.11$180.00$900.00
38Concrete curb & gutter 30-inch type K (601.0417)LF1,351$25.22$20.88$20.88$25.00
39Concrete curb & gutter 30-inch type L (601.0419)LF153$25.22$24.21$24.21$29.00
40Concrete curb pedestrian (601.0600)LF319$47.43$55.47$55.47$63.00
41Concrete sidewalk 5-inch (602.0410)SF1,862$14.91$5.39$5.39$7.00
42Curb ramp detectable warning field natural patina (602.0515)SF212$61.04$48.80$48.80$55.00
43Concrete driveway 7-inch (602.0815)SY172$73.57$60.42$60.42$81.00
44Storm sewer pipe reinforced concrete class II 24-inch (608.0224)LF194$98.06$96.94$100.00$97.00
45Storm sewer pipe reinforced concrete class II 27-inch (608.0227)LF579.90$130.38$128.91$124.00$125.00
46Storm sewer pipe reinforced concrete class II 30-inch (608.0230)LF84.10$144.80$143.16$165.00$152.00
47Storm sewer pipe reinforced concrete class III 12-inch (608.0312)LF390.20$77.54$76.67$87.00$78.00
48Storm sewer pipe reinforced concrete class III 15-inch (608.0315)LF76$119.30$117.97$91.00$84.00
49Storm sewer pipe reinforced concrete class III 18-inch (608.0318)LF83.20$131.50$130.03$85.00$84.00
50Storm sewer pipe reinforced concrete class III 24-inch (608.0324)LF531$97.00$95.89$100.00$90.00
51Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF48.50$81.42$80.49$87.00$79.00
52Storm sewer pipe reinforced concrete class IV 18-inch (608.0418)LF69.90$83.79$82.85$85.00$85.00
53Insulation board polystyrene (inch) 01. 2-inch (612.0902.S)SY18$43.22$42.75$21.33$48.00
54Mobilization (619.1000)EACH1$142,566$278,028$188,000$212,000
55Water (624.0100)MGAL51.40$37.60$37.19$40.00$35.00
56Topsoil (625.0100)SY1,341$8.65$8.56$24.00$8.00
57Mobilizations erosion control (628.1905)EACH3$102.11$101.00$101.00$115.00
58Mobilizations emergency erosion control (628.1910)EACH4$203.21$201.00$201.00$225.00
59Inlet protection type A (628.7005)EACH29$101.10$100.00$100.00$115.00
60Inlet protection type B (628.7010)EACH5$70.77$70.00$70.00$79.00
61Inlet protection type C (628.7015)EACH45$50.55$50.00$50.00$56.00
62Tracking pads (628.7560)EACH6$1,786.59$1,767.15$1,000.00$500.00
63Rock bags (628.7570)EACH20$8.09$8.00$8.00$9.00
64Fertilizer type B (629.0210)CWT2$151.65$150.00$150.00$170.00
65Sod water (631.0300)MGAL30$25.28$25.00$25.00$28.00
66Sod lawn (631.1000)SY1,341$10.04$9.93$9.93$11.00
67Signs type II reflective H (637.2210)SF50$31.34$31.00$31.00$35.00
68Moving signs type II (638.2102)EACH19$151.65$150.00$150.00$170.00
69Removing signs type II (638.2602)EACH23$35.39$35.00$35.00$40.00
70Removing small sign supports (638.3000)EACH4$35.39$35.00$35.00$40.00
71Field office type C (642.5201)EACH1$7,582.50$10,072$15,000$9,000.00
72Traffic control drums (643.0300)DAY144$2.12$2.10$2.10$2.50
73Traffic control barricades type III (643.0420)DAY2,678$0.51$0.50$0.50$0.60
74Traffic control warning lights type A (643.0705)DAY2,678$0.12$0.12$0.12$0.15
75Traffic control signs (643.0900)DAY3,145$0.56$0.55$0.55$0.60
76Traffic control signs fixed message (643.1000)SF52.50$40.44$40.00$40.00$45.00
77Traffic control signs PCMS (643.1050)DAY28$25.28$25.00$25.00$28.00
78Temporary marking line removable tape 6-inch (643.3180)LF340$2.93$2.90$2.90$3.50
79Traffic control (643.5000)EACH1$9,604.50$9,500.00$9,500.00$16,000
80Temporary pedestrian surface matting (644.1440)SF962$5.06$5.00$5.00$6.00
81Temporary pedestrian curb ramp (644.1601)DAY283$9.10$9.00$9.00$10.00
82Temporary pedestrian detectable warning field (644.1605)SF180$15.17$15.00$15.00$17.00
83Temporary pedestrian barricade (644.1810)LF3,234$5.31$5.25$5.25$6.00
84Geotextile type DF schedule A (645.0111)SY554$2.93$2.90$1.26$3.00
85Marking curb epoxy (646.8120)LF531$7.08$7.00$7.00$8.00
86Construction staking storm sewer (650.4000)EACH41$101.10$200.00$100.00$113.00
87Construction staking curb gutter and curb & gutter (650.5500)LF153$4.04$4.00$4.00$5.00
88Construction staking concrete pavement (650.7000)LF1,359$4.04$5.00$4.00$5.00
89Construction staking electrical installations (project) 01. 5991-07- 62 (650.8501)EACH1$2,881.35$1,000.00$2,850.00$3,200.00
90Construction staking curb ramps (650.9000)EACH8$111.21$10.00$110.00$125.00
91Construction staking sidewalk (project) 01. 5991-07-61 (650.9500)EACH1$505.50$2,000.00$500.00$565.00
92Construction staking supplemental control (project) 01. 5991-07-61 (650.9911)EACH1$1,516.50$3,000.00$1,500.00$1,700.00
93Construction staking slope stakes (650.9920)LF1,359$1.01$1.00$1.00$1.20
94Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF4,237$7.53$7.45$7.45$11.00
95Install conduit into existing item (652.0700.S)EACH19$477.24$472.05$472.05$395.00
96Pull boxes non-conductive 24X42- inch (653.0164)EACH8$2,171.83$2,148.20$2,148.20$2,933.00
97Adjusting pull boxes (653.0900)EACH7$525.35$519.63$519.63$508.00
98Removing pull boxes (653.0905)EACH3$275.61$272.61$272.61$339.00
99Electrical wire lighting 12 AWG (655.0610)LF2,846$4.99$4.94$4.94$2.00
100Sawing asphalt (690.0150)LF169$1.97$1.69$1.69$3.00
101Sawing concrete (690.0250)LF1,613$2.58$2.50$2.50$3.00
102Incentive compressive strength concrete pavement (715.0720)DOL1,692$1.00$1.00$1.00$1.00
103Crack and damage survey 01. (17- 20174-80) (999.1501.S)EACH1$252.75$1,400.00$1,400.00$1,600.00
104Crack and damage survey 02. (17- 20175-10) (999.1501.S)EACH1$252.75$300.00$300.00$350.00
105Crack and damage survey 03. (17- 20175-20) (999.1501.S)EACH1$252.75$2,400.00$2,400.00$2,700.00
106Crack and damage survey 04. (17- 20174-40) (999.1501.S)EACH1$252.75$700.00$700.00$800.00
107Crack and damage survey 05. (17- 20176-10) (999.1501.S)EACH1$252.75$700.00$700.00$800.00
108Crack and damage survey 06. (17- 20176-20) (999.1501.S)EACH1$252.75$1,400.00$1,400.00$1,600.00
109Crack and damage survey 07. (17- 20176-30) (999.1501.S)EACH1$252.75$900.00$900.00$1,000.00
110Crack and damage survey 08. (17- 20176-40) (999.1501.S)EACH1$252.75$900.00$900.00$1,000.00
111Crack and damage survey 09. (17- 20174-10) (999.1501.S)EACH1$252.75$3,000.00$3,000.00$3,400.00
112Crack and damage survey 10. (17- 20176-50) (999.1501.S)EACH1$252.75$900.00$900.00$1,000.00
113Crack and damage survey 11. (17- 20176-70) (999.1501.S)EACH1$252.75$500.00$500.00$600.00
114Crack and damage survey 12. (17- 40377-(10-234)) (999.1501.S)EACH1$252.75$1,800.00$1,800.00$2,000.00
115Crack and damage survey 13. (17- 20164-70) (999.1501.S)EACH1$252.75$700.00$700.00$800.00
116Crack and damage survey 14. (17- 20164-60) (999.1501.S)EACH1$252.75$500.00$500.00$600.00
117Crack and damage survey 15. (17- 20165-20) (999.1501.S)EACH1$252.75$900.00$900.00$1,000.00
118Crack and damage survey 16. (17- 20164-50) (999.1501.S)EACH1$252.75$900.00$900.00$1,000.00
119Crack and damage survey 17. (17- 20165-10) (999.1501.S)EACH1$252.75$900.00$900.00$1,000.00
120Crack and damage survey 18. (17- 20164-40) (999.1501.S)EACH1$252.75$700.00$700.00$800.00
121On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,000$5.00$5.00$5.00$5.00
122On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,320$5.00$5.00$5.00$5.00
123Special 01. 4' LA crosse storm manhole (SPV.0060)EACH6$3,744.10$3,703.36$4,800.00$3,900.00
124Special 02. 5' LA crosse storm manhole (SPV.0060)EACH6$6,631.20$6,559.05$6,800.00$7,200.00
125Special 03. LA crosse catch basin (SPV.0060)EACH29$3,812.04$3,770.56$4,000.00$3,000.00
126Special 04. LA crosse manhole cover (SPV.0060)EACH11$360.81$356.88$265.00$800.00
127Special 05. LA crosse catch basin cover type A (SPV.0060)EACH26$360.54$356.62$265.00$600.00
128Special 06. LA crosse catch basin cover type C (SPV.0060)EACH3$362.23$358.29$265.00$600.00
129Special 07. mini-storm sewer (SPV.0060)EACH1$2,342.47$2,316.98$12,000$1,100.00
130Special 08. LA crosse gate valve (6-inch) (SPV.0060)EACH2$2,310.65$2,285.51$1,853.00$2,700.00
131Special 09. LA crosse gate valve (8-inch) (SPV.0060)EACH3$3,002.13$2,969.47$2,831.00$3,800.00
132Special 10. LA crosse gate valve (12-inch) (SPV.0060)EACH2$5,334.43$5,276.39$4,733.00$6,600.00
133Special 11. LA crosse gate valve (16-inch) (SPV.0060)EACH2$20,445$20,222$16,000$18,000
134Special 12. LA crosse gate valve (20-inch) (SPV.0060)EACH2$22,986$22,736$22,494$31,000
135Special 13. LA crosse hydrant and valve group (6' bury) (SPV.0060)EACH2$6,088.10$6,021.86$7,510.00$7,800.00
136Special 15. adjust water valve (SPV.0060)EACH2$613.00$606.33$370.00$300.00
137Special 16. adjust curb stop (SPV.0060)EACH11$355.84$351.97$285.00$200.00
138Special 17. replace 4' LA crosse sanitary manhole (SPV.0060)EACH3$14,924$14,762$56,000$36,000
139Special 18. outside drop (SPV.0060)EACH7$5,878.03$5,814.08$1,080.00$4,000.00
140Special 19. reconnect sanitary lateral (SPV.0060)EACH2$5,198.38$5,141.82$8,045.00$7,000.00
141Special 20. abandon sanitary lateral (SPV.0060)EACH6$405.53$401.12$2,711.00$700.00
142Special 21. sanitary manhole cover (SPV.0060)EACH3$362.23$358.29$265.00$1,350.00
143Special 22. SDR26/PS115 PVC sanitary sewer cap (12-inch) (SPV.0060)EACH3$538.79$532.93$818.00$400.00
144Special 23. marking bike symbol grooved (epoxy) (SPV.0060)EACH12$480.23$475.00$475.00$550.00
145Special 24. utility line opening ulo (SPV.0060)EACH8$1,167.98$1,155.27$533.00$400.00
146Special 25. posts steel U-channel 14-FT (SPV.0060)EACH10$328.58$325.00$325.00$370.00
147Special 26. install V-loc sign support (SPV.0060)EACH10$151.65$150.00$150.00$170.00
148Special 27. connect to existing (SPV.0060)EACH2$580.31$574.00$5,700.00$570.00
149Special 28. concrete base complete (MS) (SPV.0060)EACH23$716.35$708.56$708.56$1,440.00
150Special 29. install light pole complete (MS) (SPV.0060)EACH38$890.28$880.59$880.59$1,470.00
151Special 30. tree protection (SPV.0060)EACH10$353.85$350.00$350.00$400.00
152Special 31. construction staking watermain system - project 5991- 07-62 (SPV.0060)EACH1$960.45$2,000.00$950.00$1,100.00
153Special 32. construction staking sanitary sewer system - project 5991-07-62 (SPV.0060)EACH1$505.50$2,000.00$500.00$600.00
154Special 01. marking line epoxy grooved 4-inch (SPV.0090)LF446$4.04$4.00$4.00$5.00
155Special 02. marking line epoxy grooved 8-inch (SPV.0090)LF3,298$5.06$5.00$5.00$5.70
156Special 03. marking crosswalk epoxy grooved transverse line 12- inch (SPV.0090)LF762$23.25$23.00$23.00$26.00
157Special 04. marking line stop bar epoxy grooved transverse line 12- inch (SPV.0090)LF170$23.25$23.00$23.00$26.00
158Special 05. LA crosse dip water main (6-inch) (SPV.0090)LF20$148.91$147.29$80.00$115.00
159Special 06. LA crosse dip water main (8-inch) (SPV.0090)LF28$506.58$501.07$195.00$290.00
160Special 07. LA crosse dip water main (12-inch) (SPV.0090)LF464$159.78$158.04$215.00$130.00
161Special 08. LA crosse dip water main (20-inch) (SPV.0090)LF26$1,270.78$1,256.95$1,000.00$1,400.00
162Special 09. SDR26/PS115 PVC sanitary sewer pipe (12-inch) (SPV.0090)LF187$90.70$89.67$150.00$200.00
163Special 10. SDR26/PS115 PVC sanitary sewer pipe (20-inch) (SPV.0090)LF40$1,029.56$1,018.32$250.00$900.00
164Special 11. reconnect LA crosse water service line (1-inch) (SPV.0090)LF30$150.79$149.15$100.00$400.00
165Special 12. concrete curb integral type K (SPV.0090)LF1,283$43.10$8.70$8.70$10.00
166Special 01. remove, palletize, and deliver or store brick pavers (SPV.0165)SF6,160$3.97$3.93$3.93$4.50
167Special 02. brick paver system complete (LA crosse pattern) (SPV.0165)SF4,986$17.72$17.53$17.53$20.00
WisDOT contract 20250211012: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of February 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy