WisDOT contract 20250311009 bid tabulation
Town of Washington, Village Road; Hill Point Creek Bridge B-56-0250 (LOC STR, Sauk County Town of Washington, Village Road). Let by Wisconsin DOT on March 11, 2025, Sauk. 5 bids received; low bid $518,561 by Larson Construction Co., Inc..
- Owner
- Wisconsin DOT
- Letting
- 11 MAR 2025
- Pay items
- 73
- Data through
- 10 NOV 2026
4 of the 5 bids matched their published totals to within a dollar and are shown; the others are left out.
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Larson Construction Co., Inc. | $518,561 | Low |
| 2 | Radtke Contractors Inc. | $535,189 | +3.0% |
| 3 | Concrete Structures, Inc. | $581,589 | +12% |
| 5 | Lunda Construction Company | $687,072 | +32% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Larson Construction Co., Inc. | 2. Radtke Contractors Inc. | 3. Concrete Structures, Inc. | 4. Lunda Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Grubbing (201.0205) | STA | 3 | $10.00 | $400.00 | $10.00 | $10.00 |
| 2 | Removing structure over waterway minimal debris (structure) 01. P-56- 928 (203.0260) | EACH | 1 | $23,840 | $34,321 | $42,800 | $90,000 |
| 3 | Removing storm sewer (size) 01. 12" (204.0245) | LF | 59 | $15.00 | $10.00 | $15.00 | $15.00 |
| 4 | Excavation common (205.0100) | CY | 900 | $21.00 | $20.50 | $21.00 | $21.00 |
| 5 | Excavation for structures bridges (structure) 01. B-56-250 (206.1001) | EACH | 1 | $13,700 | $28,783 | $10,000 | $10,000 |
| 6 | Borrow (208.0100) | CY | 910 | $17.50 | $24.00 | $17.50 | $17.50 |
| 7 | Backfill structure type A (210.1500) | TON | 220 | $30.00 | $42.08 | $18.00 | $28.00 |
| 8 | Finishing roadway (project) 01. 5855-00-73 (213.0100) | EACH | 1 | $500.00 | $1,000.00 | $500.00 | $500.00 |
| 9 | Base aggregate dense 3/4-inch (305.0110) | TON | 210 | $27.00 | $24.50 | $27.00 | $27.00 |
| 10 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 280 | $22.75 | $24.50 | $22.75 | $22.75 |
| 11 | Tack coat (455.0605) | GAL | 14 | $3.02 | $3.02 | $3.02 | $3.02 |
| 12 | Asphaltic surface (465.0105) | TON | 63 | $113.77 | $113.77 | $113.77 | $113.77 |
| 13 | Concrete masonry bridges (502.0100) | CY | 167 | $685.00 | $673.25 | $1,050.00 | $900.00 |
| 14 | Protective surface treatment (502.3200) | SY | 195 | $4.00 | $3.88 | $7.00 | $5.00 |
| 15 | Bar steel reinforcement HS structures (505.0400) | LB | 3,400 | $1.40 | $1.33 | $1.30 | $1.11 |
| 16 | Bar steel reinforcement HS coated structures (505.0600) | LB | 22,770 | $1.40 | $1.42 | $1.40 | $1.21 |
| 17 | Railing tubular type M (513.4061) | LF | 147 | $290.00 | $261.90 | $276.00 | $235.00 |
| 18 | Rubberized membrane waterproofing (516.0500) | SY | 12 | $65.00 | $69.77 | $37.00 | $25.00 |
| 19 | Culvert pipe temporary 24-inch (520.2024) | LF | 50 | $40.00 | $35.00 | $40.00 | $40.00 |
| 20 | Apron endwalls for culvert pipe reinforced concrete 12-inch (522.1012) | EACH | 1 | $1,350.00 | $1,000.00 | $1,350.00 | $1,350.00 |
| 21 | Temporary structure (station) 01. sta 21+60 (526.0101) | EACH | 1 | $50,000 | $35,234 | $52,500 | $100,000 |
| 22 | Piling steel HP 10-inch X 42 LB (550.1100) | LF | 250 | $49.90 | $35.54 | $60.00 | $40.00 |
| 23 | Riprap heavy (606.0300) | CY | 180 | $74.00 | $78.72 | $72.00 | $72.00 |
| 24 | Storm sewer pipe reinforced concrete class II 12-inch (608.0212) | LF | 62 | $75.00 | $70.00 | $75.00 | $75.00 |
| 25 | Manhole covers type J (611.0530) | EACH | 1 | $775.00 | $850.00 | $775.00 | $775.00 |
| 26 | Manholes 3-FT diameter (611.2003) | EACH | 1 | $2,875.00 | $3,000.00 | $2,875.00 | $2,875.00 |
| 27 | Pipe underdrain wrapped 6-inch (612.0406) | LF | 180 | $5.50 | $4.28 | $8.00 | $5.00 |
| 28 | Maintenance and repair of haul roads (project) 01. 5855-00-73 (618.0100) | EACH | 1 | $500.00 | $250.00 | $500.00 | $1.00 |
| 29 | Mobilization (619.1000) | EACH | 1 | $74,000 | $80,110 | $45,348 | $95,062 |
| 30 | Water (624.0100) | MGAL | 8 | $0.01 | $10.00 | $0.01 | $0.01 |
| 31 | Salvaged topsoil (625.0500) | SY | 320 | $2.75 | $2.00 | $2.75 | $2.75 |
| 32 | Mulching (627.0200) | SY | 2,100 | $0.50 | $0.50 | $2.00 | $0.30 |
| 33 | Silt fence (628.1504) | LF | 580 | $2.30 | $2.30 | $4.00 | $3.00 |
| 34 | Silt fence maintenance (628.1520) | LF | 1,160 | $0.07 | $0.07 | $0.01 | $0.25 |
| 35 | Mobilizations erosion control (628.1905) | EACH | 5 | $378.00 | $378.00 | $500.00 | $250.00 |
| 36 | Mobilizations emergency erosion control (628.1910) | EACH | 3 | $225.00 | $225.00 | $500.00 | $300.00 |
| 37 | Turbidity barriers (628.6005) | SY | 390 | $40.50 | $40.50 | $40.00 | $65.00 |
| 38 | Temporary ditch checks (628.7504) | LF | 24 | $8.06 | $8.06 | $20.00 | $10.00 |
| 39 | Fertilizer type B (629.0210) | CWT | 3 | $86.40 | $86.40 | $200.00 | $90.00 |
| 40 | Seeding mixture no. 20 (630.0120) | LB | 20 | $11.70 | $11.70 | $20.00 | $30.00 |
| 41 | Seeding mixture no. 60 (630.0160) | LB | 20 | $23.37 | $23.37 | $20.00 | $75.00 |
| 42 | Seeding temporary (630.0200) | LB | 28 | $3.20 | $3.20 | $5.00 | $10.00 |
| 43 | Seeding borrow pit (630.0300) | LB | 20 | $11.70 | $11.70 | $20.00 | $30.00 |
| 44 | Seed water (630.0500) | MGAL | 50 | $44.10 | $44.10 | $100.00 | $75.00 |
| 45 | Delineators temporary (633.1100) | EACH | 17 | $32.31 | $32.31 | $60.00 | $50.00 |
| 46 | Markers row (633.5100) | EACH | 8 | $62.10 | $62.10 | $250.00 | $60.00 |
| 47 | Posts wood 4X6-inch X 12-FT (634.0612) | EACH | 4 | $90.00 | $90.00 | $200.00 | $75.00 |
| 48 | Signs type II reflective F (637.2230) | SF | 12 | $26.10 | $26.10 | $50.00 | $35.00 |
| 49 | Removing signs type II (638.2602) | EACH | 7 | $28.80 | $28.80 | $50.00 | $35.00 |
| 50 | Removing small sign supports (638.3000) | EACH | 6 | $30.87 | $30.87 | $50.00 | $35.00 |
| 51 | Field office type B (642.5001) | EACH | 1 | $3,250.00 | $2,887.82 | $1,500.00 | $3,500.00 |
| 52 | Traffic control drums (643.0300) | DAY | 938 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | Traffic control barricades type III (643.0420) | DAY | 1,340 | $1.00 | $1.00 | $1.00 | $1.00 |
| 54 | Traffic control warning lights type A (643.0705) | DAY | 1,742 | $0.50 | $0.50 | $0.30 | $0.30 |
| 55 | Traffic control warning lights type C (643.0715) | DAY | 938 | $0.50 | $0.50 | $0.30 | $0.30 |
| 56 | Traffic control signs (643.0900) | DAY | 2,144 | $0.50 | $0.50 | $0.65 | $0.65 |
| 57 | Traffic control (643.5000) | EACH | 1 | $3,900.00 | $6,110.00 | $8,100.00 | $8,100.00 |
| 58 | Geotextile type DF schedule A (645.0111) | SY | 50 | $5.75 | $5.05 | $8.00 | $5.00 |
| 59 | Geotextile type HR (645.0120) | SY | 305 | $3.25 | $5.77 | $6.00 | $6.00 |
| 60 | Geotextile type sas (645.0140) | SY | 1,060 | $3.60 | $3.00 | $3.60 | $3.60 |
| 61 | Construction staking storm sewer (650.4000) | EACH | 2 | $250.00 | $250.00 | $250.00 | $200.00 |
| 62 | Construction staking subgrade (650.4500) | LF | 351 | $0.01 | $0.01 | $0.01 | $0.01 |
| 63 | Construction staking base (650.5000) | LF | 90 | $0.01 | $0.01 | $0.01 | $4.00 |
| 64 | Construction staking structure layout (structure) 01. B-56-0250 (650.6501) | EACH | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $1,500.00 |
| 65 | Construction staking supplemental control (project) 01. 5855-00-73 (650.9911) | EACH | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 66 | Construction staking slope stakes (650.9920) | LF | 351 | $0.01 | $0.01 | $0.01 | $2.00 |
| 67 | Sawing asphalt (690.0150) | LF | 44 | $2.35 | $2.35 | $6.00 | $6.00 |
| 68 | Incentive strength concrete structures (715.0502) | DOL | 1,002 | $1.00 | $1.00 | $1.00 | $1.00 |
| 69 | Maintaining bird deterrent system (station) 01. sta 10+75 (999.2005.S) | EACH | 1 | $2,500.00 | $0.01 | $500.00 | $0.01 |
| 70 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 | $5.00 | $5.00 |
| 71 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 | $5.00 |
| 72 | Special 01. wetland restoration seeding mixture 95A (SPV.0085) | LB | 1 | $216.00 | $216.00 | $2,000.00 | $400.00 |
| 73 | Special 01. exploring storm sewer (SPV.0090) | LF | 15 | $1.00 | $50.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.