WisDOT contract 20250311012 bid tabulation

1410-11-71. Let by Wisconsin DOT on March 11, 2025, Washington. 5 bids received; low bid $3,118,153 by Zignego Company, Inc..

Owner
Wisconsin DOT
Letting
11 MAR 2025
Pay items
204
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Zignego Company, Inc.$3,118,153Low
2Zenith Tech., Inc. - Waukesha$3,135,195+1.0%
3Wandel Contractors Inc$3,205,046+3.0%
4Lalonde Contractors Incorporated$3,321,133+7.0%
5Vinton Construction Company$3,517,930+13%
WisDOT contract 20250311012: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Zignego Company, Inc.2. Zenith Tech., Inc. - Waukesha3. Wandel Contractors Inc4. Lalonde Contractors Incorporated5. Vinton Construction Company
1Clearing (201.0120)ID10$40.00$150.00$80.00$180.00$100.00
2Grubbing (201.0220)ID10$37.00$50.60$80.00$20.00$100.00
3Removing concrete pavement (204.0100)SY6,807$13.00$8.00$9.00$14.20$2.50
4Removing curb (204.0130)LF110$20.00$7.10$10.00$15.27$15.00
5Removing curb & gutter (204.0150)LF479$20.00$7.10$5.91$15.15$10.00
6Removing concrete sidewalk (204.0155)SY1,794$10.00$4.00$4.81$14.00$18.58
7Removing concrete bases (204.0195)EACH31$500.00$150.00$400.00$460.02$300.00
8Removing catch basins (204.0215)EACH8$375.00$715.00$900.00$900.00$410.00
9Removing storm sewer (size) 01. 12-inch (204.0245)LF23$20.00$50.50$20.00$20.00$23.00
10Removing (item description) 01. traffic signals - washington ST & 18TH ave (204.9060.S)EACH1$10,890$10,890$10,890$10,890$10,890
11Removing (item description) 02. traffic signals - washington ST & 7TH ave (204.9060.S)EACH1$8,167.50$8,167.50$8,167.50$8,167.50$8,167.50
12Removing (item description) 03. traffic signals - washington ST & river RD (204.9060.S)EACH1$5,445.00$5,445.00$5,445.00$5,445.00$5,445.00
13Removing (item description) 04. loop detector & lead-in cable - washington ST & 18TH ave (204.9060.S)EACH1$1,089.00$1,089.00$1,089.00$1,089.00$1,089.00
14Removing (item description) 05. loop detector & lead-in cable - washington ST & 7TH ave (204.9060.S)EACH1$818.40$818.40$818.40$818.40$818.40
15Removing (item description) 06. loop detector & lead-in cable - washington ST & river RD (204.9060.S)EACH1$1,633.50$1,663.50$1,633.50$1,633.50$1,633.50
16Excavation common (205.0100)CY4,593$25.00$24.00$24.21$25.63$41.50
17Finishing roadway (project) 01. 1410-11-71 (213.0100)EACH1$1,000.00$1,301.87$2,500.00$2,104.00$4,000.00
18Finishing roadway (project) 02. 1410-11-72 (213.0100)EACH1$1,000.00$1,301.87$2,500.00$2,104.00$4,000.00
19Finishing roadway (project) 03. 1410-11-73 (213.0100)EACH1$1,000.00$1,301.87$2,500.00$2,104.00$4,000.00
20Base aggregate dense 1 1/4-inch (305.0120)TON3,276$30.00$25.30$20.72$28.34$29.23
21Base aggregate open-graded (310.0110)TON881$30.00$35.40$70.00$70.00$30.02
22Concrete pavement 8-inch (415.0080)SY177$90.00$92.24$87.34$80.76$90.80
23Concrete pavement 9-inch (415.0090)SY2,692$93.00$92.70$87.60$89.27$90.80
24Concrete pavement 10-inch (415.0100)SY2,312$100.00$102.32$97.87$98.85$95.45
25Drilled tie bars (416.0610)EACH2,603$10.00$5.59$9.00$16.96$9.00
26Drilled dowel bars (416.0620)EACH559$10.00$10.13$18.00$20.92$16.50
27Tack coat (455.0605)GAL2$2.50$6.37$2.50$2.50$2.50
28Asphaltic surface (465.0105)TON4$925.00$934.85$925.00$925.00$925.00
29Asphaltic surface temporary (465.0125)TON5$925.00$934.85$925.00$925.00$925.00
30Concrete collars for pipe (520.8000)EACH3$750.00$1,010.00$650.00$650.00$850.00
31Concrete curb & gutter 18-inch type A (601.0405)LF4,613$16.92$27.14$30.95$31.64$24.56
32Concrete curb pedestrian (601.0600)LF377$71.12$51.46$39.92$49.85$46.55
33Concrete sidewalk 5-inch (602.0410)SF22,401$5.84$7.95$7.68$10.62$7.69
34Curb ramp detectable warning field yellow (602.0505)SF556$53.33$35.65$40.00$43.76$32.26
35Concrete driveway 8-inch (602.0820)SY49$76.37$100.50$96.28$84.33$92.92
36Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF37$200.00$150.00$124.00$124.00$124.00
37Inlet covers type BW (611.0610)EACH2$1,300.00$1,018.75$1,013.00$1,013.00$868.00
38Inlet covers type HM (611.0627)EACH1$1,100.00$998.00$894.00$894.00$852.00
39Inlet covers type S (611.0651)EACH1$1,100.00$993.45$989.00$989.00$845.00
40Inlet covers type Z (611.0666)EACH1$1,100.00$1,010.70$1,005.00$1,005.00$862.00
41Catch basins 3-FT diameter (611.1003)EACH1$5,000.00$2,307.78$2,932.00$2,932.00$4,645.00
42Catch basins 4-FT diameter (611.1004)EACH1$5,500.00$2,911.22$3,791.00$3,791.00$5,095.00
43Catch basins 6-FT diameter (611.1006)EACH1$8,500.00$6,899.50$6,788.00$6,788.00$7,845.00
44Catch basins 2X3-FT (611.1230)EACH6$5,000.00$2,301.80$2,862.00$2,862.00$4,705.00
45Manholes 4-FT diameter (611.2004)EACH1$5,500.00$2,565.23$3,299.00$3,299.00$4,665.00
46Adjusting catch basin covers (611.8105)EACH7$650.00$1,500.00$1,045.00$616.00$450.00
47Pipe underdrain 6-inch (612.0106)LF1,842$20.00$12.00$69.00$69.00$16.89
48Mobilization (619.1000)EACH1$238,000$217,289$130,000$116,792$548,000
49Concrete corrugated median (620.0100)SF664$19.38$29.02$28.64$17.20$26.25
50Concrete median sloped nose (620.0300)SF1,117$10.17$16.95$24.76$17.25$15.33
51Water (624.0100)MGAL75$100.00$80.00$100.00$54.40$0.01
52Topsoil (625.0100)SY1,443$4.80$9.55$4.80$4.80$7.90
53Mulching (627.0200)SY100$0.55$2.00$0.55$0.55$2.00
54Silt fence (628.1504)LF744$1.95$2.25$1.95$1.95$2.25
55Silt fence maintenance (628.1520)LF378$0.01$0.10$0.01$0.01$0.10
56Mobilizations erosion control (628.1905)EACH9$50.00$100.00$50.00$50.00$100.00
57Mobilizations emergency erosion control (628.1910)EACH6$50.00$70.00$50.00$50.00$70.00
58Erosion mat urban class I type B (628.2008)SY1,443$1.80$1.89$1.80$1.80$1.89
59Inlet protection type B (628.7010)EACH2$50.00$60.00$50.00$50.00$60.00
60Inlet protection type C (628.7015)EACH22$52.00$40.00$52.00$52.00$40.00
61Inlet protection type D (628.7020)EACH31$85.00$77.10$85.00$85.00$77.10
62Rock bags (628.7570)EACH50$10.00$8.90$10.00$10.00$8.90
63Fertilizer type B (629.0210)CWT1.10$80.00$125.00$80.00$80.00$125.00
64Seeding mixture no. 40 (630.0140)LB68$12.00$9.25$12.00$12.00$9.25
65Seeding temporary (630.0200)LB37$3.25$7.00$3.25$3.25$7.00
66Seeding borrow pit (630.0300)LB65$8.75$8.00$8.75$8.75$8.00
67Seed water (630.0500)MGAL35$12.00$12.00$12.00$12.00$12.00
68Delineator posts steel (633.0100)EACH3$35.00$51.10$35.00$35.00$51.10
69Delineator reflectors (633.0500)EACH3$9.00$19.00$9.00$9.00$19.00
70Posts tubular steel 2X2-inch X 8-FT (634.0808)EACH6$155.00$90.00$155.00$155.00$90.00
71Posts tubular steel 2X2-inch X 11- FT (634.0811)EACH26$165.00$180.00$165.00$165.00$180.00
72Posts tubular steel 2X2-inch X 12- FT (634.0812)EACH29$170.00$195.00$170.00$170.00$195.00
73Posts tubular steel 2X2-inch X 14- FT (634.0814)EACH13$175.00$210.00$175.00$175.00$210.00
74Posts tubular steel 2X2-inch X 18- FT (634.0818)EACH4$225.00$260.00$225.00$225.00$260.00
75Signs type II reflective H (637.2210)SF881.38$20.00$19.00$20.00$20.00$19.00
76Signs type II reflective H folding (637.2215)SF158.52$24.00$26.10$24.00$24.00$26.10
77Signs type II reflective F (637.2230)SF114$22.00$20.00$22.00$22.00$20.00
78Removing signs type II (638.2602)EACH90$28.00$21.00$28.00$28.00$21.00
79Removing small sign supports (638.3000)EACH20$28.00$20.00$28.00$28.00$20.00
80Traffic control drums (643.0300)DAY23,971$0.15$0.15$0.15$0.15$0.15
81Traffic control barricades type III (643.0420)DAY4,553$0.65$0.65$1.00$0.65$0.65
82Traffic control flexible tubular marker posts (643.0500)EACH30$35.00$35.00$25.00$35.00$35.00
83Traffic control flexible tubular marker bases (643.0600)EACH30$5.00$5.00$7.00$5.00$5.00
84Traffic control warning lights type A (643.0705)DAY9,104$0.10$0.10$0.20$0.10$0.10
85Traffic control warning lights type C (643.0715)DAY9,595$0.10$0.10$0.20$0.10$0.10
86Traffic control arrow boards (643.0800)DAY783$8.00$8.00$15.00$8.00$8.00
87Traffic control signs (643.0900)DAY36,492$0.35$0.35$0.15$0.35$0.35
88Traffic control covering signs type II (643.0920)EACH17$25.00$25.00$20.00$25.00$25.00
89Traffic control signs fixed message (643.1000)SF281.50$12.00$12.00$18.00$12.00$12.00
90Traffic control signs PCMS (643.1050)DAY56$25.00$25.00$35.00$25.00$25.00
91Traffic control cones 42-inch (643.1070)DAY22,119$0.10$0.10$0.20$0.10$0.10
92Temporary marking line removable tape 4-inch (643.3150)LF19,250$0.82$0.82$1.00$0.82$0.82
93Temporary marking line removable tape 8-inch (643.3250)LF7,059$0.82$0.82$2.00$0.82$0.82
94Temporary marking crosswalk removable tape 6-inch (643.3350)LF2,351$1.50$1.50$1.10$1.50$1.50
95Temporary marking arrow removable tape (643.3550)EACH19$75.00$75.00$75.00$75.00$75.00
96Temporary marking word removable tape (643.3650)EACH5$75.00$75.00$100.00$75.00$75.00
97Temporary marking stop line removable tape 18-inch (643.3850)LF358$4.00$4.00$5.00$4.00$4.00
98Temporary marking removable mask out tape 6-inch (643.3960)LF1,340$1.25$1.25$1.25$1.25$1.25
99Temporary marking removable mask out tape 8-inch (643.3980)LF421$2.00$2.00$1.50$2.00$2.00
100Traffic control (643.5000)EACH1$42,814$42,814$25,000$42,814$42,814
101Temporary pedestrian surface matting (644.1440)SF1,081$2.00$2.00$8.00$2.00$2.00
102Temporary pedestrian curb ramp (644.1601)DAY364$4.00$4.00$16.00$4.00$4.00
103Temporary pedestrian detectable warning field (644.1605)SF238$4.00$4.00$3.30$4.00$4.00
104Temporary pedestrian barricade (644.1810)LF3,534$4.00$4.00$5.00$4.00$4.00
105Geotextile type DF schedule A (645.0111)SY1,025$4.00$6.00$16.00$16.00$3.00
106Marking line epoxy 4-inch (646.1020)LF1,616$0.55$0.80$0.55$0.55$0.80
107Marking line epoxy 8-inch (646.3020)LF4,857$0.70$1.55$0.70$0.70$1.55
108Marking arrow epoxy (646.5020)EACH38$295.00$250.00$295.00$295.00$250.00
109Marking word epoxy (646.5120)EACH6$325.00$250.00$325.00$325.00$250.00
110Marking stop line epoxy 18-inch (646.6120)LF444$12.75$14.00$12.75$12.75$14.00
111Marking diagonal epoxy 12-inch (646.7120)LF63$10.25$12.50$10.25$10.25$12.50
112Marking crosswalk epoxy block style 24-inch (646.7520)LF884$17.10$20.00$17.10$17.10$20.00
113Marking corrugated median epoxy (646.8020)SF339$10.50$10.00$10.50$10.50$10.00
114Marking curb epoxy (646.8120)LF1,537$10.50$9.00$10.50$10.50$9.00
115Marking island nose epoxy (646.8220)EACH14$225.00$300.00$225.00$225.00$300.00
116Marking removal line water blasting 4-inch (646.9010)LF479$2.00$2.00$1.00$2.00$2.00
117Marking removal line water blasting 6-inch (646.9012)LF1,391$2.00$2.00$1.00$2.00$2.00
118Marking removal line water blasting 8-inch (646.9110)LF574$3.00$3.00$1.00$3.00$3.00
119Marking removal line water blasting wide (646.9210)LF222$5.50$5.50$2.00$5.50$5.50
120Marking removal special marking water blasting (646.9310)EACH22$250.00$250.00$45.00$250.00$250.00
121Construction staking storm sewer (650.4000)EACH9$42.55$42.55$42.55$184.00$42.55
122Construction staking subgrade (650.4500)LF2,042$0.01$8.35$8.35$2.26$0.01
123Construction staking concrete pavement (650.7000)LF2,042$1.25$1.25$1.25$2.26$1.25
124Construction staking electrical installations (project) 01. 1410-11- 71 (650.8501)EACH2$1,711.46$1,711.46$1,711.46$600.00$1,711.46
125Construction staking electrical installations (project) 01. 1410-11- 73 (650.8501)EACH1$1,590.93$1,590.93$1,590.93$750.00$1,590.93
126Construction staking curb ramps (650.9000)EACH55$140.00$140.00$140.00$78.20$140.00
127Construction staking sidewalk (project) 01. 1410-11-71 (650.9500)EACH1$827.05$827.05$827.05$1,700.00$827.05
128Construction staking sidewalk (project) 02. 1410-11-72 (650.9500)EACH1$976.46$976.46$976.46$1,700.00$976.46
129Construction staking sidewalk (project) 03. 1410-11-73 (650.9500)EACH1$1,198.23$1,198.23$1,198.23$1,700.00$1,198.23
130Construction staking supplemental control (project) 01. 1410-11-71 (650.9911)EACH1$433.96$433.96$433.96$1,000.00$433.96
131Construction staking supplemental control (project) 02. 1410-11-72 (650.9911)EACH1$433.96$433.96$433.96$1,000.00$433.96
132Construction staking supplemental control (project) 03. 1410-11-73 (650.9911)EACH1$433.96$433.96$433.96$1,000.00$433.96
133Construction staking slope stakes (650.9920)LF2,042$0.87$0.87$0.87$2.11$0.87
134Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF242$9.06$9.06$9.06$9.06$9.06
135Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF1,209$10.59$10.59$10.59$10.59$10.59
136Conduit special 3-inch (652.0615)LF2,362$30.73$30.73$30.73$30.73$30.73
137Pull boxes steel 24X42-inch (653.0140)EACH34$1,348.50$1,348.50$1,348.50$1,348.50$1,348.50
138Removing pull boxes (653.0905)EACH65$205.00$205.00$205.00$205.00$205.00
139Concrete bases type 1 (654.0101)EACH24$990.00$990.00$990.00$990.00$990.00
140Concrete bases type 10-special (654.0120)EACH12$10,329$10,329$10,329$10,329$10,329
141Concrete control cabinet bases type 9 special (654.0217)EACH3$2,933.50$2,933.50$2,933.50$2,933.50$2,933.50
142Cable traffic signal 5-14 AWG (655.0230)LF2,713$1.73$1.73$1.73$1.73$1.73
143Cable traffic signal 7-14 AWG (655.0240)LF3,250$2.22$2.22$2.22$2.22$2.22
144Cable traffic signal 12-14 AWG (655.0260)LF4,165$3.19$3.19$3.19$3.19$3.19
145Cable traffic signal 15-14 AWG (655.0270)LF1,399$3.94$3.94$3.94$3.94$3.94
146Cable traffic signal 21-14 AWG (655.0290)LF466$4.61$4.61$4.61$4.61$4.61
147Electrical wire traffic signals 10 AWG (655.0515)LF4,181$1.44$1.44$1.44$1.44$1.44
148Electrical service meter breaker pedestal (location) 01. washington ST & 18TH ave (656.0201)EACH1$1,510.00$1,510.00$1,510.00$1,510.00$1,510.00
149Electrical service meter breaker pedestal (location) 02. washington ST & 7TH ave (656.0201)EACH1$1,510.00$1,510.00$1,510.00$1,510.00$1,510.00
150Electrical service meter breaker pedestal (location) 03. washington ST & river RD (656.0201)EACH1$1,510.00$1,510.00$1,510.00$1,510.00$1,510.00
151Pedestal bases (657.0100)EACH24$238.50$238.50$238.50$238.50$238.50
152Poles type 9-special (657.0347)EACH12$10,755$10,755$10,755$10,755$10,755
153Traffic signal standards aluminum 3.5-FT (657.0405)EACH6$239.00$239.00$239.00$239.00$239.00
154Traffic signal standards aluminum 13-FT (657.0420)EACH2$549.50$549.50$549.50$549.50$549.50
155Traffic signal standards aluminum 15-FT (657.0425)EACH13$586.50$586.50$586.50$586.50$586.50
156Traffic signal standards aluminum 10-FT (657.0430)EACH3$500.50$500.50$500.50$500.50$500.50
157Monotube arms 35-FT-special (657.0536)EACH2$6,040.00$6,040.00$6,040.00$6,040.00$6,040.00
158Monotube arms 40-FT-special (657.0541)EACH1$6,328.50$6,328.50$6,328.50$6,328.50$6,328.50
159Monotube arms 45-FT-special (657.0546)EACH9$6,505.00$6,505.00$6,505.00$6,505.00$6,505.00
160Traffic signal face 3S 12-inch (658.0173)EACH42$917.00$917.00$917.00$917.00$917.00
161Traffic signal face 4S 12-inch (658.0174)EACH30$1,226.00$1,226.00$1,226.00$1,226.00$1,226.00
162Pedestrian signal face 16-inch (658.0416)EACH24$665.60$665.60$665.60$665.60$665.60
163Pedestrian push buttons (658.0500)EACH34$430.20$430.20$430.20$430.20$430.20
164Signal mounting hardware (location) 01. washington ST & 18TH ave (658.5070)EACH1$8,663.00$8,663.00$8,663.00$8,663.00$8,663.00
165Signal mounting hardware (location) 02. washington ST & 7TH ave (658.5070)EACH1$8,101.00$8,101.00$8,101.00$8,101.00$8,101.00
166Signal mounting hardware (location) 03. washington ST & river RD (658.5070)EACH1$8,101.00$8,101.00$8,101.00$8,101.00$8,101.00
167Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH69$10.00$10.00$10.00$10.00$10.00
168Temporary traffic signals for intersections (location) 01. washington ST & 18TH ave (661.0201)EACH1$59,344$59,344$59,344$59,344$59,344
169Temporary traffic signals for intersections (location) 02. washington ST & river RD (661.0201)EACH1$56,678$56,678$56,678$56,678$56,678
170Generators (661.0300)DAY2$195.00$195.00$195.00$195.00$195.00
171Sawing asphalt (690.0150)LF545$1.10$1.10$1.10$1.39$3.00
172Sawing concrete (690.0250)LF7,265$1.90$2.10$1.85$2.00$3.00
173Incentive compressive strength concrete pavement (715.0720)DOL1,828$1.00$1.00$1.00$1.00$1.00
174On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS1,800$5.00$5.00$5.00$5.00$5.00
175On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS4,800$5.00$5.00$5.00$5.00$5.00
176Special 01. traffic signal cabinet & controller - washington ST & 18TH ave (SPV.0060)EACH1$27,068$27,068$27,068$27,068$27,068
177Special 02. traffic signal cabinet & controller - washington ST & 7TH ave (SPV.0060)EACH1$27,068$27,068$27,068$27,068$27,068
178Special 03. traffic signal cabinet & controller - washington ST & river RD (SPV.0060)EACH1$27,068$27,068$27,068$27,068$27,068
179Special 04. emergency vehicle preemption system - washington ST & 18TH ave (SPV.0060)EACH1$8,555.00$8,555.00$8,555.00$8,555.00$8,555.00
180Special 05. emergency vehicle preemption system - washington ST & 7TH ave (SPV.0060)EACH1$8,555.00$8,555.00$8,555.00$8,555.00$8,555.00
181Special 06. emergency vehicle preemption system - washington ST & river RD (SPV.0060)EACH1$8,555.00$8,555.00$8,555.00$8,555.00$8,555.00
182Special 07. temporary infrared evp system - washington ST & 18TH ave (SPV.0060)EACH1$4,632.50$4,632.50$4,632.50$4,632.50$4,632.50
183Special 09. temporary infrared evp system - washington ST & river RD (SPV.0060)EACH1$4,632.50$4,632.50$4,632.50$4,632.50$4,632.50
184Special 10. video detection system - washington ST & 18TH ave (SPV.0060)EACH1$29,340$29,340$29,340$29,340$29,340
185Special 11. video detection system - washington ST & 7TH ave (SPV.0060)EACH1$29,340$29,340$29,340$29,340$29,340
186Special 12. video detection system - washington ST & river RD (SPV.0060)EACH1$29,340$29,340$29,340$29,340$29,340
187Special 13. remove, salvage, and reinstall traffic signal interconnect - washington ST & (SPV.0060)EACH1$5,568.00$5,568.00$5,568.00$5,568.00$5,568.00
188Special 14. remove, salvage, and reinstall traffic signal interconnect - washington ST & (SPV.0060)EACH1$5,568.00$5,568.00$5,568.00$5,568.00$5,568.00
189Special 15. remove, salvage, and reinstall traffic signal interconnect - washington ST & (SPV.0060)EACH1$5,568.00$5,568.00$5,568.00$5,568.00$5,568.00
190Special 16. remove and cap existing drainage structure (SPV.0060)EACH1$3,000.00$3,000.00$4,660.00$4,660.00$3,410.00
191Special 17. abandoning pull boxes (SPV.0060)EACH25$372.00$372.00$372.00$372.00$372.00
192Special 18. RMV & reinstall emgy veh preemption cable - washington ST & 7TH ave/main ST (SPV.0060)EACH1$3,170.00$3,170.00$3,170.00$3,170.00$3,170.00
193Special 19. remove & reinstall wireless comm equipment - washington ST & 7TH ave/main ST (SPV.0060)EACH1$4,011.00$4,011.00$4,011.00$4,011.00$4,011.00
194Special 20. adjusting water valve box (SPV.0060)EACH6$650.00$200.00$200.00$304.50$400.00
195Special 21. adjusting sanitary sewer manhole (SPV.0060)EACH3$1,000.00$1,800.00$1,953.00$1,612.00$1,660.00
196Special 22. inlet covers type WB (SPV.0060)EACH6$1,350.00$1,003.80$350.00$350.00$885.00
197Special 23. manhole covers type WB (SPV.0060)EACH1$1,200.00$1,015.30$350.00$350.00$899.00
198Special 24. cutting and capping existing sprinkler system (SPV.0060)EACH1$250.00$325.00$400.00$813.00$1,200.00
199Special 01. concrete curb & gutter 6-inch sloped 24-inch type A (SPV.0090)LF93$82.51$49.05$58.00$44.30$44.38
200Special 02. concrete curb & gutter 24-inch type A (SPV.0090)LF1,963$18.20$39.39$31.32$33.62$35.64
201Special 01. concrete raised median (SPV.0165)SF1,874$23.76$25.25$25.57$19.02$22.84
202Special 02. remove brick pavers (SPV.0165)SF495$3.00$1.90$3.00$3.00$1.90
203Special 01. excavate haul & disposal of petroleum contaminated soil (SPV.0195)TON265$76.00$50.00$130.14$64.97$75.00
204Special 02. excavate haul & disposal of cvoc contaminated soil (SPV.0195)TON16$100.00$75.00$150.00$106.34$150.00
WisDOT contract 20250311012: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy