WisDOT contract 20250311048 bid tabulation
C Milwaukee, Water St; Milwaukee River Bridge B40-548 (LOC STR, Milwaukee County C Milwaukee, Water St). Let by Wisconsin DOT on March 11, 2025, Milwaukee. 4 bids received; low bid $2,686,786 by Lunda Construction Company.
- Owner
- Wisconsin DOT
- Letting
- 11 MAR 2025
- Pay items
- 62
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Lunda Construction Company | $2,686,786 | Low |
| 2 | Drax Inc. | $2,838,205 | +6.0% |
| 3 | Zenith Tech., Inc. - Waukesha | $2,842,842 | +6.0% |
| 4 | Granite Construction Company | $2,999,682 | +12% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Lunda Construction Company | 2. Drax Inc. | 3. Zenith Tech., Inc. - Waukesha | 4. Granite Construction Company |
|---|---|---|---|---|---|---|---|
| 1 | Removing structure over waterway minimal debris (structure) 001. B- 40-548 (203.0260) | EACH | 1 | $250,000 | $200,000 | $375,000 | $1.00 |
| 2 | Removing concrete pavement (204.0100) | SY | 161 | $30.00 | $22.65 | $67.75 | $50.00 |
| 3 | Excavation common (205.0100) | CY | 32 | $50.00 | $59.89 | $142.61 | $160.00 |
| 4 | Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S) | TON | 61 | $139.00 | $130.00 | $192.91 | $89.00 |
| 5 | Excavation for structures bridges (structure) 001. B-40-548 (206.1001) | EACH | 1 | $1,000.00 | $5,000.00 | $15,000 | $13,000 |
| 6 | Backfill structure type A (210.1500) | TON | 172 | $62.00 | $50.00 | $30.00 | $50.00 |
| 7 | Base aggregate dense 3/4-inch (305.0110) | TON | 65 | $45.00 | $50.00 | $67.55 | $85.00 |
| 8 | Concrete pavement approach slab (415.0410) | SY | 161 | $250.00 | $250.00 | $231.17 | $231.17 |
| 9 | Drilled dowel bars (416.0620) | EACH | 96 | $25.00 | $26.00 | $20.44 | $20.44 |
| 10 | Compression joint sealer preformed elastomeric (width) 1 1/4-inch (502.2000) | LF | 120 | $40.00 | $70.00 | $85.00 | $50.00 |
| 11 | Protective surface treatment (502.3200) | SY | 404 | $6.00 | $6.00 | $5.75 | $10.00 |
| 12 | Protective surface treatment reseal (502.3215) | SY | 142 | $12.50 | $6.00 | $16.00 | $10.00 |
| 13 | Bar steel reinforcement HS coated structures (505.0600) | LB | 1,050 | $7.65 | $1.50 | $5.85 | $3.85 |
| 14 | Structural steel HS (506.0605) | LB | 470 | $160.00 | $50.00 | $100.00 | $100.00 |
| 15 | Preparation decks type 1 (509.0301) | SY | 3 | $350.00 | $300.00 | $575.00 | $3,000.00 |
| 16 | Preparation decks type 2 (509.0302) | SY | 2 | $320.00 | $300.00 | $575.00 | $3,000.00 |
| 17 | Sawing pavement deck preparation areas (509.0310.S) | LF | 60 | $10.00 | $40.00 | $15.00 | $10.00 |
| 18 | Joint repair (509.1000) | SY | 28 | $2,100.00 | $1,685.00 | $3,425.00 | $2,500.00 |
| 19 | Curb repair (509.1200) | LF | 9 | $55.00 | $85.00 | $225.00 | $500.00 |
| 20 | Concrete surface repair (509.1500) | SF | 148 | $200.00 | $50.00 | $315.00 | $300.00 |
| 21 | Concrete masonry deck repair (509.2100.S) | CY | 9 | $675.00 | $1,000.00 | $1,500.00 | $6,500.00 |
| 22 | Epoxy crack sealing (509.9020.S) | LF | 535 | $9.00 | $10.00 | $32.15 | $55.00 |
| 23 | Epoxy injection crack repair (509.9025.S) | LF | 199 | $40.00 | $68.00 | $120.00 | $85.00 |
| 24 | Cored holes 2-inch diameter (509.9026.S) | EACH | 4 | $250.00 | $500.00 | $600.00 | $1,800.00 |
| 25 | Rubberized membrane waterproofing (516.0500) | SY | 34 | $35.00 | $75.00 | $100.00 | $100.00 |
| 26 | Preparation and coating of top flanges (structure) 001. B-40-548 (517.0901.S) | EACH | 1 | $9,000.00 | $5,000.00 | $9,000.00 | $9,000.00 |
| 27 | Structure repainting recycled abrasive (structure) 001. B-40-548 (517.1801.S) | EACH | 1 | $600,000 | $745,000 | $600,000 | $676,000 |
| 28 | Negative pressure containment and collection of waste materials (structure) 001. B-40-548 (517.4501.S) | EACH | 1 | $270,000 | $135,000 | $270,000 | $335,000 |
| 29 | Portable decontamination facility (517.6001.S) | EACH | 1 | $1,000.00 | $500.00 | $1,000.00 | $1,000.00 |
| 30 | Mobilization (619.1000) | EACH | 1 | $203,419 | $522,158 | $240,000 | $300,000 |
| 31 | Inlet protection type C (628.7015) | EACH | 1 | $300.00 | $350.00 | $400.00 | $61.00 |
| 32 | Field office type C (642.5201) | EACH | 1 | $8,000.00 | $10,000 | $15,000 | $25,000 |
| 33 | Traffic control drums (643.0300) | DAY | 3,380 | $0.54 | $0.50 | $0.50 | $0.50 |
| 34 | Traffic control barricades type III (643.0420) | DAY | 2,208 | $0.86 | $1.00 | $1.00 | $1.00 |
| 35 | Traffic control flexible tubular marker posts (643.0500) | EACH | 51 | $20.00 | $20.00 | $20.00 | $20.00 |
| 36 | Traffic control flexible tubular marker bases (643.0600) | EACH | 51 | $20.00 | $10.00 | $10.00 | $10.00 |
| 37 | Traffic control warning lights type A (643.0705) | DAY | 2,208 | $0.15 | $0.15 | $0.15 | $0.15 |
| 38 | Traffic control warning lights type C (643.0715) | DAY | 3,380 | $0.14 | $0.15 | $0.15 | $0.15 |
| 39 | Traffic control signs (643.0900) | DAY | 5,048 | $0.35 | $0.55 | $0.55 | $0.55 |
| 40 | Traffic control signs PCMS (643.1050) | DAY | 14 | $30.00 | $75.00 | $75.00 | $75.00 |
| 41 | Temporary marking line removable tape 4-inch (643.3150) | LF | 9,890 | $1.80 | $1.00 | $1.00 | $1.00 |
| 42 | Traffic control (643.5000) | EACH | 1 | $13,000 | $2,793.67 | $25,000 | $2,793.67 |
| 43 | Marking line epoxy 4-inch (646.1020) | LF | 650 | $6.15 | $6.15 | $5.00 | $6.10 |
| 44 | Marking removal line 4-inch (646.9000) | LF | 650 | $1.00 | $1.65 | $1.65 | $1.00 |
| 45 | Construction staking structure layout (structure) 001. B-40-548 (650.6501) | EACH | 1 | $6,500.00 | $6,500.00 | $5,000.00 | $6,500.00 |
| 46 | Sawing concrete (690.0250) | LF | 156 | $2.35 | $7.00 | $2.25 | $2.35 |
| 47 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 800 | $5.00 | $5.00 | $5.00 | $5.00 |
| 48 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 3,600 | $5.00 | $5.00 | $5.00 | $5.00 |
| 49 | Special 001. adjusting sanitary manhole (SPV.0060) | EACH | 1 | $3,900.00 | $3,250.00 | $3,900.00 | $3,900.00 |
| 50 | Special 002. adjusting water valve boxes (SPV.0060) | EACH | 1 | $1,500.00 | $600.00 | $1,500.00 | $1,500.00 |
| 51 | Special 553. expansion joints at rear break (SPV.0060) | EACH | 2 | $115,000 | $124,500 | $67,500 | $175,000 |
| 52 | Special 560. heel block refurbishment (SPV.0060) | EACH | 1 | $49,000 | $34,000 | $50,000 | $100,000 |
| 53 | Special 561. traffic gates replacement (SPV.0060) | EACH | 4 | $44,650 | $42,875 | $50,000 | $44,650 |
| 54 | Special 562. bridge electrical work (SPV.0060) | EACH | 1 | $60,000 | $60,000 | $100,000 | $150,000 |
| 55 | Special 563. centerlock adjustments (SPV.0060) | EACH | 1 | $56,000 | $71,000 | $12,000 | $50,000 |
| 56 | Special 565. anchor assemblies traffic gates (SPV.0060) | EACH | 4 | $3,450.00 | $2,500.00 | $2,000.00 | $2,200.00 |
| 57 | Special 597. protecting utilities (SPV.0060) | EACH | 1 | $8,000.00 | $2,000.00 | $5,000.00 | $25,000 |
| 58 | Special 540. urethane injection crack repair (SPV.0090) | LF | 20 | $105.00 | $68.00 | $93.00 | $250.00 |
| 59 | Special 706. marking stop line epoxy 24-inch (SPV.0090) | LF | 46 | $36.90 | $36.90 | $50.00 | $37.00 |
| 60 | Special 501. removing and reinstalling metal plates for bike lanes (SPV.0165) | SF | 909 | $100.00 | $62.00 | $65.00 | $60.00 |
| 61 | Special 502. fiberglass sidewalk floor plates (SPV.0165) | SF | 1,928 | $150.00 | $154.00 | $155.00 | $135.00 |
| 62 | Special 596. power washing (SPV.0165) | SF | 7,129 | $1.50 | $0.50 | $1.50 | $1.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of March 11, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.