WisDOT contract 20250408029 bid tabulation

C Chippewa Falls, Bay Street; High Street to Bridge Street (STH 124, Chippewa County STH 124). Let by Wisconsin DOT on April 8, 2025, Chippewa. 2 bids received; low bid $2,560,809 by Chippewa Concrete Services, Inc..

Owner
Wisconsin DOT
Letting
08 APR 2025
Pay items
116
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Chippewa Concrete Services, Inc.$2,560,809Low
2Pember Companies, Inc.$2,685,075+5.0%
WisDOT contract 20250408029: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Chippewa Concrete Services, Inc.2. Pember Companies, Inc.
1Removing concrete pavement butt joints (204.0105)SY303$13.35$14.00
2Removing concrete surface partial depth (204.0109.S)SF13,560$0.98$1.00
3Removing asphaltic surface (204.0110)SY989$18.00$10.85
4Removing asphaltic surface butt joints (204.0115)SY617$25.17$26.40
5Removing asphaltic surface milling (204.0120)SY21,760$7.36$8.95
6Removing curb & gutter (204.0150)LF3,438$8.40$10.85
7Removing concrete sidewalk (204.0155)SY1,720$14.00$20.70
8Removing concrete bases (204.0195)EACH2$390.00$775.00
9Removing manholes (204.0210)EACH1$2,800.00$1,070.00
10Removing catch basins (204.0215)EACH2$2,100.00$800.00
11Removing storm sewer (size) 01. 12-inch (204.0245)LF55$59.50$24.00
12Excavation common (205.0100)CY1,022$20.50$120.00
13Prepare foundation for asphaltic paving (project) 01. 8610-02-74 (211.0101)EACH1$85,956$90,250
14Finishing roadway (project) 01. 8610-02-74 (213.0100)EACH1$2,500.00$1,000.00
15Base aggregate dense 1 1/4-inch (305.0120)TON312$46.00$112.00
16Removing pavement for base patching (390.0100)CY45$269.47$170.00
17Base patching concrete shes (390.0405)CY45$269.47$225.00
18Drilled tie bars (416.0610)EACH68$16.03$8.80
19Drilled dowel bars (416.0620)EACH272$20.59$12.25
20HMA cold weather paving (450.4000)TON650$3.77$3.95
21Tack coat (455.0605)GAL3,804$6.66$7.00
22Incentive density HMA pavement (460.2000)DOL3,180$1.00$1.00
23HMA pavement 5 MT 58-34 V (460.6645)TON4,656$126.00$132.35
24Material transfer vehicle (460.9000.S)EACH1$19,680$20,665
25Asphaltic surface (465.0105)TON234$319.21$335.20
26Asphaltic surface patching (465.0110)TON66$388.18$407.60
27Concrete curb & gutter 18-inch type D (601.0407)LF88$59.86$30.40
28Concrete curb & gutter 30-inch type A (601.0409)LF90$62.09$36.75
29Concrete curb & gutter 30-inch type D (601.0411)LF3,546$45.73$30.90
30Concrete curb pedestrian (601.0600)LF1,077$48.50$24.75
31Concrete sidewalk 5-inch (602.0410)SF14,508$14.43$7.75
32Curb ramp detectable warning field yellow (602.0505)SF972$62.51$48.50
33Concrete driveway 7-inch (602.0815)SY108$93.06$79.90
34Concrete driveway hes 8-inch (602.0870)SY44$98.73$93.85
35Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF49$150.00$117.30
36Inlet covers type H (611.0624)EACH2$1,150.00$1,130.00
37Inlets 2X3-FT (611.3230)EACH2$4,450.00$2,470.00
38Adjusting manhole covers (611.8110)EACH44$1,500.00$1,100.00
39Adjusting inlet covers (611.8115)EACH39$525.00$570.00
40Cover plates temporary (611.8120.S)EACH44$795.00$660.00
41Mobilization (619.1000)EACH1$289,600$333,925
42Water (624.0100)MGAL5.20$40.00$99.00
43Topsoil (625.0100)SY288$16.00$19.10
44Mobilizations erosion control (628.1905)EACH21$50.00$50.00
45Mobilizations emergency erosion control (628.1910)EACH6$50.00$50.00
46Inlet protection type A (628.7005)EACH2$140.00$148.50
47Inlet protection type C (628.7015)EACH62$74.00$78.50
48Fertilizer type A (629.0205)CWT1.70$95.00$101.00
49Sod water (631.0300)MGAL4.80$100.00$106.00
50Sod lawn (631.1000)SY288$15.00$15.90
51Field office type B (642.5001)EACH1$7,500.00$7,825.00
52Traffic control drums (643.0300)DAY59,677$0.15$0.15
53Traffic control barricades type III (643.0420)DAY1,600$0.80$0.75
54Traffic control warning lights type A (643.0705)DAY640$0.13$0.15
55Traffic control signs (643.0900)DAY19,897$0.22$0.25
56Traffic control signs PCMS (643.1050)DAY32$28.40$30.10
57Temporary marking line epoxy 6- inch (643.3170)LF5,979$0.85$0.50
58Temporary marking crosswalk removable tape 6-inch (643.3350)LF3,350$2.17$2.30
59Traffic control (643.5000)EACH1$16,256$100,000
60Temporary pedestrian surface matting (644.1440)SF1,675$9.80$10.40
61Temporary pedestrian curb ramp (644.1601)DAY2,382$1.67$1.80
62Temporary pedestrian detectable warning field (644.1605)SF1,220$4.18$4.45
63Temporary pedestrian barricade (644.1810)LF6,510$1.50$1.60
64Marking line grooved wet ref epoxy 6-inch (646.2040)LF3,861$2.50$1.50
65Marking line grooved wet ref epoxy 10-inch (646.4040)LF241$4.25$3.00
66Marking line same day epoxy 6- inch (646.4720)LF2,794$1.85$1.40
67Marking arrow epoxy (646.5020)EACH10$350.00$350.00
68Marking word epoxy (646.5120)EACH2$350.00$400.00
69Marking stop line epoxy 18-inch (646.6120)LF689$18.00$14.90
70Cold weather marking epoxy 6-inch (646.6466)LF3,861$0.01$0.50
71Cold weather marking epoxy 10- inch (646.6470)LF241$0.01$1.15
72Marking diagonal epoxy 12-inch (646.7120)LF689$8.25$14.25
73Marking crosswalk epoxy transverse line 6-inch (646.7420)LF4,012$13.25$13.80
74Marking crosswalk epoxy block style 24-inch (646.7520)LF36$20.00$24.10
75Marking parking stall epoxy (646.8320)LF2,528$4.25$5.60
76Construction staking storm sewer (650.4000)EACH2$200.00$210.00
77Construction staking curb gutter and curb & gutter (650.5500)LF3,724$0.85$0.90
78Construction staking resurfacing reference (650.8000)LF4,760$0.10$0.10
79Construction staking curb ramps (650.9000)EACH91$10.00$10.60
80Construction staking sidewalk (project) 01. 8610-02-74 (650.9500)EACH1$100.00$105.00
81Construction staking supplemental control (project) 01. 8610-02-74 (650.9911)EACH1$10,000$10,600
82Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF65$15.00$15.80
83Install conduit into existing item (652.0700.S)EACH6$260.00$275.00
84Adjusting pull boxes (653.0900)EACH20$200.00$205.00
85Concrete bases type 10 (654.0110)EACH2$9,570.00$10,050
86Concrete bases type 10-special (654.0120)EACH4$11,885$12,500
87Cable traffic signal 5-14 AWG (655.0230)LF545$1.50$1.60
88Cable traffic signal 7-14 AWG (655.0240)LF573$2.00$2.15
89Cable traffic signal 12-14 AWG (655.0260)LF63$4.75$5.00
90Electrical wire traffic signals 10 AWG (655.0515)LF762$1.65$1.75
91Traffic signal evp detector cable (655.0900)LF546$1.50$1.60
92Poles type 9 (657.0345)EACH2$8,500.00$8,950.00
93Poles type 9-special (657.0347)EACH4$10,990$11,550
94Monotube arms 20-FT (657.0520)EACH1$4,125.00$4,325.00
95Monotube arms 25-FT (657.0525)EACH1$4,450.00$4,675.00
96Monotube arms 35-FT-special (657.0536)EACH4$6,550.00$6,875.00
97Traffic signal face 3S 12-inch (658.0173)EACH11$975.00$1,025.00
98Pedestrian signal face 16-inch (658.0416)EACH2$1,230.00$1,290.00
99Signal mounting hardware (location) 01. STH 124/bay street & river street (658.5070)EACH1$1,750.00$1,850.00
100Signal mounting hardware (location) 02. STH 124/bay street & spring street (658.5070)EACH1$1,350.00$1,420.00
101Signal mounting hardware (location) 03. STH 124/bay street & central street (658.5070)EACH1$1,350.00$1,420.00
102Signal mounting hardware (location) 04. STH 124/bay street & grand avenue (658.5070)EACH1$1,350.00$1,420.00
103Signal mounting hardware (location) 05. STH 124/bay street & columbia street (658.5070)EACH1$1,350.00$1,420.00
104Sawing asphalt (690.0150)LF3,827$1.95$1.75
105Sawing concrete (690.0250)LF2,954$2.55$2.65
106Incentive iri ride (740.0440)DOL3,606$1.00$1.00
107On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS200$5.00$5.00
108On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS300$5.00$5.00
109Special 01. temporary audible message devices (SPV.0045)DAY3,561$1.66$1.80
110Special 01. salvaging traffic signals equipment STH 124/bay street & river street (SPV.0060)EACH1$2,275.00$2,400.00
111Special 02. salvaging traffic signal head (SPV.0060)EACH4$425.00$445.00
112Special 03. salvaging and reinstalling evp detectors STH 124/bay street & river street (SPV.0060)EACH1$1,250.00$1,315.00
113Special 04. temporary skid type traffic signal pole (SPV.0060)EACH1$2,500.00$2,630.00
114Special 01. salvage and reinstall brick pavers (SPV.0165)SF87$20.00$60.00
115Special 01. removing distressed pavement milling (SPV.0180)SY100$28.15$29.60
116Special 02. prepare topsoil for lawn type turf (SPV.0180)SY288$2.00$2.15
WisDOT contract 20250408029: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of April 8, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy