WisDOT contract 20250513021 bid tabulation

USH 141, V Crivitz; Owl Lane - S Junction Old Hwy 141 (USH 141, Marinette County USH 141, V Crivitz). Let by Wisconsin DOT on May 13, 2025, Marinette. 2 bids received; low bid $1,940,359 by Northeast Asphalt, Inc.

Owner
Wisconsin DOT
Letting
13 MAY 2025
Pay items
151
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Northeast Asphalt, Inc$1,940,359Low
2Relyco Plus, LLC$2,019,963+4.0%
WisDOT contract 20250513021: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Northeast Asphalt, Inc2. Relyco Plus, LLC
1Removing small pipe culverts (203.0100)EACH2$500.00$662.50
2Removing concrete pavement (204.0100)SY645$10.00$5.00
3Removing asphaltic surface (204.0110)SY8$75.00$20.00
4Removing asphaltic surface butt joints (204.0115)SY28$93.20$93.20
5Removing asphaltic surface milling (204.0120)SY39,710$3.90$3.90
6Removing curb (204.0130)LF230$10.00$15.00
7Removing curb & gutter (204.0150)LF825$10.00$15.00
8Removing concrete bases (204.0195)EACH9$200.00$200.00
9Removing inlets (204.0220)EACH24$1,425.50$437.00
10Removing storm sewer (size) 01. 12-inch (204.0245)LF288$17.50$19.50
11Removing (item description) 01. business sign (204.9060.S)EACH1$1,500.00$1,500.00
12Excavation common (205.0100)CY1,252$28.00$54.31
13Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S)TON80$75.00$90.00
14Prepare foundation for asphaltic paving (project) 01. 1490-40-71 (211.0101)EACH1$37,860$37,860
15Finishing roadway (project) 01. 1490-40-71 (213.0100)EACH1$1,500.00$4,000.00
16Base aggregate dense 3/4-inch (305.0110)TON105$35.00$69.27
17Base aggregate dense 1 1/4-inch (305.0120)TON2,020$22.00$25.47
18Shaping shoulders (305.0500)STA20$420.00$100.00
19Coloring concrete wisdot red (405.0100)CY18$110.00$110.00
20Drilled tie bars (416.0610)EACH145$10.00$10.00
21HMA cold weather paving (450.4000)TON3,255$3.10$3.10
22Tack coat (455.0605)GAL2,900$3.20$3.20
23Incentive density HMA pavement (460.2000)DOL3,160$1.00$1.00
24HMA pavement 4 MT 58-28 S (460.6224)TON5,000$89.60$89.60
25Asphaltic surface (465.0105)TON65$198.00$198.00
26Asphaltic surface driveways and field entrances (465.0120)TON1$587.00$587.00
27Asphaltic flumes (465.0315)SY130$78.10$78.10
28Concrete collars for pipe (520.8000)EACH2$950.00$800.00
29Cleaning culvert pipes (520.8700)EACH3$1,500.00$1,185.00
30Apron endwalls for pipe arch steel 42X29-inch (521.1242)EACH1$860.00$1,685.00
31Pipe arch corrugated steel 42X29- inch (521.3742)LF16$133.50$177.50
32Culvert pipe reinforced concrete class IV 24-inch (522.0424)LF94$175.00$142.75
33Apron endwalls for culvert pipe reinforced concrete 24-inch (522.1024)EACH2$2,221.00$1,998.00
34Apron endwalls for culvert pipe salvaged 30-inch (524.0630)EACH1$2,150.00$1,070.00
35Concrete curb & gutter 30-inch type A (601.0409)LF20$70.00$70.00
36Concrete curb & gutter 30-inch type D (601.0411)LF275$70.00$70.00
37Concrete curb & gutter 6-inch sloped 36-inch type D (601.0557)LF145$65.00$65.00
38Concrete driveway 6-inch (602.0810)SY60$110.00$110.00
39Maintenance and repair of haul roads (project) 01. 1490-40-71 (618.0100)EACH1$1.00$0.01
40Mobilization (619.1000)EACH1$364,870$410,000
41Water (624.0100)MGAL21$50.00$50.00
42Salvaged topsoil (625.0500)SY2,470$5.00$8.85
43Mulching (627.0200)SY415$1.00$1.00
44Silt fence (628.1504)LF775$2.50$2.50
45Silt fence maintenance (628.1520)LF775$0.01$0.01
46Mobilizations erosion control (628.1905)EACH6$400.00$400.00
47Mobilizations emergency erosion control (628.1910)EACH3$200.00$200.00
48Erosion mat urban class I type B (628.2008)SY2,470$2.10$2.10
49Inlet protection type C (628.7015)EACH15$70.00$70.00
50Temporary ditch checks (628.7504)LF275$7.95$7.95
51Culvert pipe checks (628.7555)EACH15$14.00$14.00
52Rock bags (628.7570)EACH140$14.00$14.00
53Fertilizer type B (629.0210)CWT1.50$150.00$150.00
54Seeding mixture no. 30 (630.0130)LB38$8.75$8.75
55Seeding mixture no. 60 (630.0160)LB3$100.00$100.00
56Seeding temporary (630.0200)LB12$5.00$5.00
57Seed water (630.0500)MGAL57$5.00$5.00
58Sod water (631.0300)MGAL6.50$5.00$5.00
59Sod erosion control (631.1100)SY206$18.00$18.00
60Markers culvert end (633.5200)EACH9$68.00$68.00
61Posts wood 4X6-inch X 14-FT (634.0614)EACH43$84.00$84.00
62Posts wood 4X6-inch X 16-FT (634.0616)EACH16$88.00$88.00
63Posts wood 4X6-inch X 18-FT (634.0618)EACH5$92.00$92.00
64Signs type II reflective H (637.2210)SF442.80$21.70$21.70
65Signs type II reflective H folding (637.2215)SF20.72$29.15$29.15
66Signs type II reflective F (637.2230)SF59.70$22.95$22.95
67Removing signs type II (638.2602)EACH53$35.00$35.00
68Removing small sign supports (638.3000)EACH52$35.00$35.00
69Field office type B (642.5001)EACH1$11,870$9,500.00
70Traffic control drums (643.0300)DAY15,091$0.35$0.75
71Traffic control barricades type III (643.0420)DAY1,228$0.65$2.50
72Traffic control flexible tubular marker posts (643.0500)EACH18$30.00$35.00
73Traffic control flexible tubular marker bases (643.0600)EACH18$8.00$15.00
74Traffic control warning lights type A (643.0705)DAY1,784$0.20$0.75
75Traffic control warning lights type C (643.0715)DAY992$0.20$1.00
76Traffic control signs (643.0900)DAY3,188$0.89$1.25
77Traffic control covering signs type II (643.0920)EACH18$85.00$99.46
78Traffic control signs fixed message (643.1000)SF158$23.00$22.00
79Traffic control signs PCMS (643.1050)DAY56$85.00$30.00
80Temporary marking line paint 6- inch (643.3165)LF22,245$0.25$0.25
81Temporary marking line removable tape 6-inch (643.3180)LF26,715$2.65$1.95
82Temporary marking line removable tape 10-inch (643.3280)LF40$10.00$3.55
83Temporary marking stop line paint 18-inch (643.3805)LF11$5.50$5.50
84Temporary marking stop line removable tape 18-inch (643.3850)LF11$15.00$6.50
85Traffic control (643.5000)EACH1$19,500$47,350
86Geotextile type sas (645.0140)SY150$7.00$5.00
87Marking line grooved wet ref epoxy 6-inch (646.2040)LF35,210$1.75$1.75
88Marking line grooved wet ref epoxy 10-inch (646.4040)LF990$3.60$3.60
89Marking arrow epoxy (646.5020)EACH40$346.87$346.87
90Marking word epoxy (646.5120)EACH2$398.54$398.54
91Marking railroad crossing epoxy (646.5320)EACH2$3,377.27$3,377.27
92Marking stop line epoxy 18-inch (646.6120)LF120$14.76$14.76
93Cold weather marking epoxy 6-inch (646.6466)LF35,210$0.29$0.29
94Cold weather marking epoxy 10- inch (646.6470)LF990$0.63$0.63
95Marking diagonal epoxy 12-inch (646.7120)LF310$14.17$14.17
96Marking curb epoxy (646.8120)LF90$7.00$7.00
97Marking island nose epoxy (646.8220)EACH2$273.47$273.47
98Marking removal line 4-inch (646.9000)LF4,030$0.50$0.50
99Marking removal line wide (646.9200)LF95$2.50$2.50
100Marking removal special marking (646.9300)EACH1$75.00$75.00
101Construction staking subgrade (650.4500)LF880$0.01$0.01
102Construction staking base (650.5000)LF880$1.21$1.21
103Construction staking curb gutter and curb & gutter (650.5500)LF1,065$0.72$0.72
104Construction staking pipe culverts (650.6000)EACH3$106.09$106.09
105Construction staking resurfacing reference (650.8000)LF7,630$0.24$0.24
106Construction staking electrical installations (project) 01. 1490-40- 71 (650.8501)EACH1$1,357.49$1,357.49
107Construction staking supplemental control (project) 01. 1490-40-71 (650.9911)EACH1$422.81$422.81
108Construction staking slope stakes (650.9920)LF770$0.84$0.84
109Conduit rigid nonmetallic schedule 40 2-inch (652.0225)LF390$10.00$10.00
110Conduit rigid nonmetallic schedule 40 3-inch (652.0235)LF195$14.00$14.00
111Conduit special 2-inch (652.0605)LF270$28.00$28.00
112Conduit special 3-inch (652.0615)LF630$32.00$32.00
113Conduit loop detector (652.0800)LF966$6.00$6.00
114Pull boxes non-conductive 24X42- inch (653.0164)EACH10$2,250.00$2,250.00
115Removing pull boxes (653.0905)EACH12$75.00$75.00
116Concrete bases type 1 (654.0101)EACH4$1,575.00$1,575.00
117Concrete bases type 10 (654.0110)EACH2$7,500.00$7,500.00
118Concrete bases type 10-special (654.0120)EACH2$13,750$13,750
119Concrete control cabinet bases type 9 special (654.0217)EACH1$2,200.00$2,200.00
120Cable traffic signal 5-14 AWG (655.0230)LF831$2.55$2.55
121Cable traffic signal 7-14 AWG (655.0240)LF214$2.85$2.85
122Cable traffic signal 12-14 AWG (655.0260)LF1,003$4.75$4.75
123Electrical wire traffic signals 10 AWG (655.0515)LF938$0.90$0.90
124Loop detector lead in cable (655.0700)LF1,774$2.00$2.00
125Loop detector wire (655.0800)LF2,630$0.80$0.80
126Electrical service meter breaker pedestal (location) 01. S38-0492 temporary (656.0201)EACH1$1,950.00$1,950.00
127Pedestal bases (657.0100)EACH4$260.00$260.00
128Poles type 9 (657.0345)EACH2$8,405.00$8,405.00
129Poles type 9-special (657.0347)EACH2$11,280$11,280
130Traffic signal standards aluminum 13-FT (657.0420)EACH2$545.00$545.00
131Traffic signal standards aluminum 15-FT (657.0425)EACH2$580.00$580.00
132Monotube arms 25-FT (657.0525)EACH1$4,736.00$4,736.00
133Monotube arms 30-FT (657.0530)EACH1$5,788.00$5,788.00
134Monotube arms 40-FT-special (657.0541)EACH2$5,634.00$5,634.00
135Traffic signal face 3S 12-inch (658.0173)EACH12$690.00$690.00
136Traffic signal face 4S 12-inch (658.0174)EACH4$870.00$870.00
137Signal mounting hardware (location) 01. S38-0492 temporary (658.5070)EACH1$2,500.00$2,500.00
138Signal mounting hardware (location) 02. S38-0492 future (658.5070)EACH1$3,500.00$3,500.00
139Lamp, ballast, LED, switch disposal by contractor (659.5000.S)EACH36$75.00$75.00
140Sawing asphalt (690.0150)LF1,605$1.95$1.85
141Sawing concrete (690.0250)LF610$2.95$2.95
142Incentive iri ride (740.0440)DOL16,900$1.00$1.00
143On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS600$5.00$5.00
144On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS1,200$5.00$5.00
145Special 01. inlet adjustment ring replacement (SPV.0060)EACH2$1,550.00$817.50
146Special 02. remove traffic signal (ush 141 & CTH W) (SPV.0060)EACH1$8,500.00$8,500.00
147Special 03. utility line opening (ulo) (SPV.0060)EACH5$1,500.00$826.50
148Special 04. temporary traffic signal (ush 141 & CTH W) (SPV.0060)EACH1$9,500.00$9,500.00
149Special 01. concrete curb & gutter shes 30-inch type D (SPV.0090)LF900$62.00$62.00
150Special 01. concrete median sloped nose shes (SPV.0165)SF320$25.00$25.00
151Special 01. concrete truck apron shes 12-inch (SPV.0180)SY57$280.00$280.00
WisDOT contract 20250513021: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of May 13, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy