WisDOT contract 20251014006 bid tabulation
6995-04-74. Let by Wisconsin DOT on October 14, 2025, Dodge. 8 bids received; low bid $3,389,627 by Advance Construction, Inc..
- Owner
- Wisconsin DOT
- Letting
- 14 OCT 2025
- Pay items
- 163
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Advance Construction, Inc. | $3,389,627 | Low |
| 2 | Lalonde Contractors Incorporated | $3,657,181 | +8.0% |
| 3 | Zignego Company, Inc. | $3,818,716 | +13% |
| 4 | James Peterson Sons, Inc. | $4,047,290 | +19% |
| 5 | Vinton Construction Company | $4,057,690 | +20% |
| 6 | Rock Road Companies, Inc. | $4,692,834 | +38% |
| 7 | Musson Bros., Inc. | $4,879,137 | +44% |
| 8 | Parisi Construction, LLC | $4,944,913 | +46% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Advance Construction, Inc. | 2. Lalonde Contractors Incorporated | 3. Zignego Company, Inc. | 4. James Peterson Sons, Inc. | 5. Vinton Construction Company | 6. Rock Road Companies, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing (201.0120) | ID | 277 | $25.00 | $31.65 | $31.65 | $25.00 | $31.65 | $31.65 |
| 2 | Grubbing (201.0220) | ID | 277 | $22.00 | $12.66 | $12.66 | $20.00 | $12.66 | $12.66 |
| 3 | Removing concrete pavement (204.0100) | SY | 11,520 | $4.67 | $0.01 | $7.39 | $10.44 | $2.00 | $10.87 |
| 4 | Removing curb & gutter (204.0150) | LF | 145 | $5.00 | $6.00 | $10.00 | $10.00 | $10.00 | $9.02 |
| 5 | Removing concrete sidewalk (204.0155) | SY | 2,635 | $3.50 | $5.98 | $6.00 | $3.50 | $7.85 | $16.63 |
| 6 | Removing guardrail (204.0165) | LF | 12.50 | $15.00 | $15.00 | $15.00 | $20.00 | $3.00 | $10.00 |
| 7 | Removing manholes (204.0210) | EACH | 2 | $600.00 | $300.00 | $300.00 | $500.00 | $672.50 | $487.96 |
| 8 | Removing inlets (204.0220) | EACH | 10 | $400.00 | $350.00 | $350.00 | $400.00 | $495.80 | $365.98 |
| 9 | Removing storm sewer (size) 01. 12-inch or less (204.0245) | LF | 862 | $20.00 | $5.00 | $5.00 | $24.06 | $24.38 | $14.29 |
| 10 | Removing storm sewer (size) 02. 15-inch (204.0245) | LF | 107 | $22.00 | $12.00 | $12.00 | $38.74 | $27.21 | $14.29 |
| 11 | Removing ancillary structure (structure) 01. station 121+77 (204.0246) | EACH | 1 | $10,000 | $3,140.00 | $3,140.00 | $3,140.00 | $3,140.00 | $3,140.00 |
| 12 | Sealing pipes (204.0280) | EACH | 2 | $500.00 | $400.00 | $400.00 | $250.00 | $625.00 | $1,121.97 |
| 13 | Removing (item description) 01. bollard (204.9060.S) | EACH | 1 | $100.00 | $450.00 | $1,000.00 | $200.00 | $185.00 | $240.46 |
| 14 | Excavation common (205.0100) | CY | 11,230 | $11.90 | $26.60 | $18.00 | $14.46 | $24.68 | $23.55 |
| 15 | Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S) | TON | 1,000 | $35.00 | $50.45 | $75.00 | $44.32 | $50.00 | $28.15 |
| 16 | Excavation for structures retaining walls (structure) 01. station 121+77 (206.3001) | EACH | 1 | $10,000 | $4,630.00 | $50,000 | $4,630.00 | $4,630.00 | $4,630.00 |
| 17 | Cofferdams (structure) 01. station 121+77 (206.5001) | EACH | 1 | $72,000 | $16,812 | $16,812 | $16,812 | $16,812 | $16,812 |
| 18 | Backfill structure type A (210.1500) | TON | 33 | $20.00 | $26.00 | $100.00 | $26.00 | $65.00 | $26.00 |
| 19 | Finishing roadway (project) 01. 6995-04-74 (213.0100) | EACH | 1 | $10,000 | $2,910.00 | $1,000.00 | $5,000.00 | $5,000.00 | $5,093.29 |
| 20 | Base aggregate dense 3/4-inch (305.0110) | TON | 50 | $13.00 | $33.00 | $100.00 | $22.45 | $40.00 | $30.87 |
| 21 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 5,380 | $12.47 | $17.10 | $20.32 | $16.98 | $15.00 | $24.35 |
| 22 | Base aggregate open-graded (310.0115) | CY | 10 | $40.00 | $25.00 | $200.00 | $46.81 | $69.15 | $22.92 |
| 23 | Breaker run (311.0110) | TON | 8,600 | $12.00 | $16.24 | $19.07 | $13.06 | $14.23 | $19.67 |
| 24 | Concrete pavement 8-inch (415.0080) | SY | 9,840 | $63.00 | $67.66 | $63.00 | $71.29 | $65.33 | $58.44 |
| 25 | Drilled tie bars (416.0610) | EACH | 24 | $30.00 | $14.17 | $30.00 | $9.65 | $10.00 | $14.24 |
| 26 | Drilled dowel bars (416.0620) | EACH | 144 | $30.00 | $18.06 | $30.00 | $13.89 | $17.50 | $18.24 |
| 27 | Tack coat (455.0605) | GAL | 10 | $18.10 | $18.10 | $18.10 | $18.10 | $18.10 | $4.63 |
| 28 | Asphaltic surface (465.0105) | TON | 4 | $345.00 | $345.00 | $970.00 | $345.00 | $970.00 | $1,156.51 |
| 29 | Asphaltic surface driveways and field entrances (465.0120) | TON | 7 | $345.00 | $345.00 | $970.00 | $345.00 | $970.00 | $2,050.87 |
| 30 | Removing and resetting tubular railing (structure) 01. station 121+77 (513.9006.S) | EACH | 1 | $5,000.00 | $4,900.00 | $4,900.00 | $4,900.00 | $4,900.00 | $4,900.00 |
| 31 | Rubberized membrane waterproofing (516.0500) | SY | 3 | $100.00 | $60.00 | $60.00 | $60.00 | $60.00 | $60.00 |
| 32 | Concrete curb & gutter 30-inch type A (601.0409) | LF | 2,855 | $24.40 | $33.14 | $41.50 | $25.69 | $25.00 | $29.00 |
| 33 | Concrete curb & gutter 30-inch type D (601.0411) | LF | 40 | $57.00 | $47.98 | $100.00 | $88.56 | $65.00 | $85.00 |
| 34 | Concrete curb & gutter integral 30- inch type D (601.0452) | LF | 1,800 | $28.50 | $20.82 | $26.50 | $14.95 | $25.00 | $20.00 |
| 35 | Concrete curb pedestrian (601.0600) | LF | 53 | $47.00 | $51.25 | $150.00 | $77.02 | $45.00 | $60.00 |
| 36 | Concrete sidewalk 4-inch (602.0405) | SF | 20,650 | $6.45 | $7.26 | $7.00 | $5.67 | $6.75 | $9.00 |
| 37 | Concrete sidewalk 6-inch (602.0415) | SF | 4,700 | $7.55 | $9.69 | $9.55 | $8.11 | $7.85 | $9.00 |
| 38 | Curb ramp detectable warning field yellow (602.0505) | SF | 250 | $35.00 | $44.08 | $50.00 | $53.74 | $35.00 | $45.00 |
| 39 | Curb ramp detectable warning field radial yellow (602.0605) | SF | 37.09 | $55.00 | $68.36 | $100.00 | $85.59 | $55.00 | $65.00 |
| 40 | Concrete driveway 6-inch (602.0810) | SY | 1,025 | $69.50 | $83.35 | $100.00 | $73.02 | $70.50 | $71.00 |
| 41 | Concrete steps (602.1500) | SF | 17 | $90.00 | $89.08 | $500.00 | $84.80 | $90.00 | $105.00 |
| 42 | Storm sewer pipe reinforced concrete class IV 12-inch (608.0412) | LF | 139 | $100.00 | $80.00 | $80.00 | $90.73 | $83.39 | $118.20 |
| 43 | Storm sewer pipe reinforced concrete class IV 24-inch (608.0424) | LF | 204 | $130.00 | $145.00 | $145.00 | $87.33 | $130.06 | $145.18 |
| 44 | Storm sewer pipe class III-A 12- inch (608.3012) | LF | 173 | $85.00 | $62.00 | $62.00 | $78.32 | $83.61 | $141.23 |
| 45 | Storm sewer pipe class III-A 15- inch (608.3015) | LF | 158 | $88.00 | $74.00 | $74.00 | $85.42 | $84.42 | $143.71 |
| 46 | Storm sewer pipe class III-A 18- inch (608.3018) | LF | 348 | $75.50 | $72.00 | $72.00 | $53.81 | $80.91 | $104.60 |
| 47 | Storm sewer pipe class III-A 24- inch (608.3024) | LF | 901 | $85.00 | $90.00 | $90.00 | $76.51 | $100.66 | $115.32 |
| 48 | Manhole covers type J (611.0530) | EACH | 7 | $496.00 | $800.00 | $800.00 | $1,336.99 | $517.78 | $1,156.54 |
| 49 | Inlet covers type H (611.0624) | EACH | 18 | $758.00 | $1,071.00 | $1,071.00 | $1,579.32 | $741.44 | $1,402.56 |
| 50 | Manholes 4-FT diameter (611.2004) | EACH | 5 | $2,629.00 | $3,100.00 | $3,100.00 | $2,651.48 | $4,069.39 | $3,238.48 |
| 51 | Manholes 5-FT diameter (611.2005) | EACH | 2 | $4,628.00 | $4,300.00 | $4,300.00 | $4,840.77 | $5,814.00 | $4,886.81 |
| 52 | Inlets 4-FT diameter (611.3004) | EACH | 1 | $2,194.00 | $2,800.00 | $2,800.00 | $1,834.42 | $4,070.64 | $3,059.92 |
| 53 | Inlets 2X3-FT (611.3230) | EACH | 18 | $1,881.00 | $2,100.00 | $2,100.00 | $1,412.38 | $2,679.79 | $2,651.04 |
| 54 | Pipe underdrain 6-inch (612.0106) | LF | 100 | $30.00 | $12.00 | $12.00 | $30.41 | $27.08 | $58.94 |
| 55 | Insulation board polystyrene (inch) 01. 2-inch (612.0902.S) | SY | 138.80 | $18.00 | $32.00 | $32.00 | $27.00 | $35.31 | $16.54 |
| 56 | Steel plate beam guard class A (614.0305) | LF | 12.50 | $50.00 | $50.00 | $50.00 | $50.00 | $36.00 | $100.00 |
| 57 | Fence chain link salvaged 4-FT (616.0404) | LF | 11 | $85.00 | $85.00 | $85.00 | $311.50 | $45.00 | $75.00 |
| 58 | Fence chain link salvaged 6-FT (616.0406) | LF | 8 | $100.00 | $100.00 | $100.00 | $477.50 | $60.00 | $75.00 |
| 59 | Maintenance and repair of haul roads (project) 01. 6995-04-74 (618.0100) | EACH | 1 | $10,000 | $0.01 | $1.00 | $0.01 | $0.01 | $0.01 |
| 60 | Mobilization (619.1000) | EACH | 1 | $151,295 | $142,654 | $169,500 | $288,714 | $389,000 | $348,055 |
| 61 | Water (624.0100) | MGAL | 77 | $50.00 | $43.00 | $200.00 | $40.00 | $35.00 | $0.01 |
| 62 | Topsoil (625.0100) | SY | 3,000 | $5.95 | $5.95 | $5.95 | $8.17 | $7.00 | $4.98 |
| 63 | Silt fence (628.1504) | LF | 100 | $3.00 | $3.00 | $3.00 | $3.50 | $4.00 | $5.00 |
| 64 | Silt fence maintenance (628.1520) | LF | 100 | $1.00 | $1.00 | $1.00 | $0.05 | $0.01 | $0.01 |
| 65 | Mobilizations erosion control (628.1905) | EACH | 12 | $150.00 | $150.00 | $150.00 | $200.00 | $50.00 | $100.00 |
| 66 | Mobilizations emergency erosion control (628.1910) | EACH | 6 | $150.00 | $150.00 | $150.00 | $200.00 | $50.00 | $100.00 |
| 67 | Inlet protection type A (628.7005) | EACH | 1 | $125.00 | $125.00 | $125.00 | $150.00 | $50.00 | $150.00 |
| 68 | Inlet protection type D (628.7020) | EACH | 41 | $95.00 | $95.00 | $95.00 | $125.00 | $50.00 | $120.00 |
| 69 | Tracking pads (628.7560) | EACH | 3 | $1,000.00 | $1,561.00 | $1,000.00 | $1,500.00 | $0.01 | $1,018.63 |
| 70 | Fertilizer type B (629.0210) | CWT | 2 | $15.00 | $15.00 | $15.00 | $90.00 | $75.00 | $150.00 |
| 71 | Sod water (631.0300) | MGAL | 170 | $40.00 | $40.00 | $40.00 | $75.00 | $35.00 | $100.00 |
| 72 | Sod lawn (631.1000) | SY | 3,000 | $7.95 | $7.95 | $7.95 | $12.50 | $7.00 | $10.00 |
| 73 | Posts tubular steel 2X2-inch X 14- FT (634.0814) | EACH | 22 | $220.00 | $220.00 | $220.00 | $200.00 | $215.00 | $190.00 |
| 74 | Posts tubular steel 2X2-inch X 16- FT (634.0816) | EACH | 5 | $230.00 | $230.00 | $230.00 | $250.00 | $225.00 | $210.00 |
| 75 | Signs type II reflective H (637.2210) | SF | 137.90 | $23.00 | $23.00 | $23.00 | $19.50 | $25.00 | $20.00 |
| 76 | Moving signs type II (638.2102) | EACH | 3 | $120.00 | $120.00 | $120.00 | $75.00 | $100.00 | $150.00 |
| 77 | Removing signs type II (638.2602) | EACH | 30 | $35.00 | $35.00 | $35.00 | $35.00 | $10.00 | $35.00 |
| 78 | Removing small sign supports (638.3000) | EACH | 26 | $35.00 | $35.00 | $35.00 | $35.00 | $10.00 | $35.00 |
| 79 | Moving small sign supports (638.4000) | EACH | 3 | $80.00 | $80.00 | $80.00 | $75.00 | $10.00 | $100.00 |
| 80 | Field office type B (642.5001) | EACH | 1 | $9,000.00 | $18,164 | $10,000 | $17,500 | $10,000 | $16,500 |
| 81 | Traffic control barricades type III (643.0420) | DAY | 3,200 | $0.61 | $0.61 | $0.61 | $0.61 | $0.61 | $0.61 |
| 82 | Traffic control warning lights type A (643.0705) | DAY | 6,400 | $0.21 | $0.21 | $0.21 | $0.21 | $0.21 | $0.21 |
| 83 | Traffic control signs (643.0900) | DAY | 42,500 | $0.25 | $0.25 | $0.25 | $0.25 | $0.25 | $0.25 |
| 84 | Traffic control covering signs type I (643.0910) | EACH | 3 | $107.54 | $107.54 | $107.54 | $107.54 | $107.54 | $107.54 |
| 85 | Traffic control covering signs type II (643.0920) | EACH | 7 | $69.18 | $69.18 | $69.18 | $69.18 | $69.18 | $69.18 |
| 86 | Traffic control signs PCMS (643.1050) | DAY | 14 | $73.02 | $73.02 | $73.02 | $73.02 | $73.02 | $73.02 |
| 87 | Traffic control (643.5000) | EACH | 1 | $7,293.44 | $7,293.44 | $7,293.44 | $7,293.44 | $7,293.44 | $7,293.44 |
| 88 | Temporary pedestrian surface plate (644.1430) | SF | 200 | $16.74 | $16.74 | $16.74 | $16.74 | $16.74 | $16.74 |
| 89 | Temporary pedestrian surface matting (644.1440) | SF | 400 | $12.54 | $12.54 | $12.54 | $12.54 | $12.54 | $12.54 |
| 90 | Temporary pedestrian curb ramp (644.1601) | DAY | 20 | $24.83 | $24.83 | $24.83 | $24.83 | $24.83 | $24.83 |
| 91 | Temporary pedestrian detectable warning field (644.1605) | SF | 20 | $33.98 | $33.98 | $33.98 | $33.98 | $33.98 | $33.98 |
| 92 | Temporary pedestrian barricade (644.1810) | LF | 400 | $5.31 | $5.31 | $5.31 | $5.31 | $5.31 | $5.31 |
| 93 | Geotextile type DF schedule A (645.0111) | SY | 60 | $2.00 | $1.00 | $10.00 | $6.42 | $7.68 | $0.70 |
| 94 | Geogrid type SR (645.0220) | SY | 12,400 | $2.00 | $1.92 | $2.00 | $2.05 | $1.30 | $2.16 |
| 95 | Marking line epoxy 6-inch (646.2020) | LF | 6,275 | $2.15 | $0.75 | $0.75 | $1.90 | $0.75 | $1.90 |
| 96 | Marking arrow epoxy (646.5020) | EACH | 17 | $300.00 | $225.00 | $225.00 | $240.00 | $225.00 | $240.00 |
| 97 | Marking word epoxy (646.5120) | EACH | 3 | $350.00 | $240.00 | $240.00 | $350.00 | $240.00 | $350.00 |
| 98 | Marking symbol epoxy (646.5220) | EACH | 17 | $285.00 | $350.00 | $350.00 | $240.00 | $350.00 | $240.00 |
| 99 | Marking stop line epoxy 18-inch (646.6120) | LF | 95 | $16.10 | $13.00 | $13.00 | $33.00 | $13.00 | $33.00 |
| 100 | Marking crosswalk epoxy transverse line 6-inch (646.7420) | LF | 1,055 | $9.75 | $10.00 | $10.00 | $19.00 | $10.00 | $19.00 |
| 101 | Construction staking storm sewer (650.4000) | EACH | 26 | $220.00 | $220.00 | $220.00 | $65.14 | $65.14 | $65.14 |
| 102 | Construction staking subgrade (650.4500) | LF | 2,272 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 | $0.01 |
| 103 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 93 | $5.00 | $5.00 | $5.00 | $1.25 | $1.25 | $1.25 |
| 104 | Construction staking concrete pavement (650.7000) | LF | 2,272 | $2.75 | $2.75 | $2.75 | $1.45 | $1.45 | $1.45 |
| 105 | Construction staking curb ramps (650.9000) | EACH | 28 | $100.00 | $100.00 | $100.00 | $105.84 | $105.84 | $105.84 |
| 106 | Construction staking sidewalk (project) 01. 6995-04-74 (650.9500) | EACH | 1 | $100.00 | $100.00 | $100.00 | $5,162.50 | $5,162.50 | $5,162.50 |
| 107 | Construction staking supplemental control (project) 01. 6995-04-74 (650.9911) | EACH | 1 | $10.00 | $10.00 | $10.00 | $960.39 | $960.39 | $960.39 |
| 108 | Construction staking slope stakes (650.9920) | LF | 2,272 | $2.00 | $2.00 | $2.00 | $1.10 | $1.10 | $1.10 |
| 109 | Sawing asphalt (690.0150) | LF | 810 | $3.00 | $1.75 | $1.62 | $1.75 | $3.00 | $1.85 |
| 110 | Sawing concrete (690.0250) | LF | 1,400 | $4.00 | $2.35 | $1.62 | $2.35 | $3.00 | $2.20 |
| 111 | Incentive compressive strength concrete pavement (715.0720) | DOL | 2,952 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 112 | Incentive iri ride (740.0440) | DOL | 1,721 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 113 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 2,400 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 114 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 2,120 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 | $5.00 |
| 115 | Special 01. utility line opening (ulo) (SPV.0060) | EACH | 10 | $700.00 | $300.00 | $300.00 | $700.00 | $866.90 | $975.00 |
| 116 | Special 02. reconnect storm sewer laterals (SPV.0060) | EACH | 2 | $150.00 | $300.00 | $300.00 | $172.10 | $757.38 | $891.39 |
| 117 | Special 03. inlet cover type driveway special (SPV.0060) | EACH | 1 | $719.00 | $835.00 | $835.00 | $1,381.92 | $753.05 | $1,415.33 |
| 118 | Special 04. clay dam within contaminated soils (SPV.0060) | EACH | 7 | $500.00 | $500.00 | $500.00 | $1,000.00 | $1,630.71 | $891.39 |
| 119 | Special 05. remove EX. sanitary manhole (SPV.0060) | EACH | 11 | $600.00 | $300.00 | $300.00 | $500.00 | $551.82 | $762.17 |
| 120 | Special 06. remove EX. water valve box (SPV.0060) | EACH | 19 | $250.00 | $50.00 | $50.00 | $350.00 | $196.47 | $464.34 |
| 121 | Special 07. remove EX. hydrant (SPV.0060) | EACH | 6 | $600.00 | $350.00 | $350.00 | $810.00 | $605.66 | $735.20 |
| 122 | Special 08. remove EX. water manhole (SPV.0060) | EACH | 1 | $600.00 | $400.00 | $400.00 | $500.00 | $978.99 | $1,887.13 |
| 123 | Special 09. sanitary manhole (48- inch) (SPV.0060) | EACH | 9 | $4,422.00 | $4,600.00 | $4,600.00 | $4,923.53 | $6,479.04 | $5,607.31 |
| 124 | Special 10. sanitary MH cover type J-special (SPV.0060) | EACH | 9 | $513.00 | $633.00 | $633.00 | $1,717.80 | $535.72 | $1,176.27 |
| 125 | Special 11. sanitary sewer cleanout (SPV.0060) | EACH | 2 | $977.00 | $1,000.00 | $1,000.00 | $738.43 | $1,148.26 | $1,441.39 |
| 126 | Special 12. connect to existing sanitary sewer (SPV.0060) | EACH | 5 | $350.00 | $450.00 | $450.00 | $2,104.28 | $662.11 | $2,744.78 |
| 127 | Special 13. water valve & box 4- inch (SPV.0060) | EACH | 4 | $1,614.00 | $1,765.00 | $1,765.00 | $2,224.60 | $1,982.52 | $2,410.99 |
| 128 | Special 14. water valve & box 6- inch (SPV.0060) | EACH | 8 | $1,981.00 | $2,100.00 | $2,100.00 | $2,775.85 | $2,301.33 | $2,767.10 |
| 129 | Special 15. water valve & box 8- inch (SPV.0060) | EACH | 16 | $2,812.00 | $2,700.00 | $2,700.00 | $3,831.80 | $3,099.34 | $3,662.70 |
| 130 | Special 16. fire hydrant (SPV.0060) | EACH | 6 | $6,064.00 | $7,700.00 | $7,700.00 | $8,117.85 | $6,119.65 | $7,436.23 |
| 131 | Special 17. tees 8"X4"X8" special (SPV.0060) | EACH | 4 | $795.00 | $900.00 | $900.00 | $1,113.00 | $1,475.31 | $1,320.39 |
| 132 | Special 18. tees 8"X6"X8" special (SPV.0060) | EACH | 7 | $897.00 | $940.00 | $940.00 | $1,250.20 | $1,888.01 | $1,502.84 |
| 133 | Special 19. tees 8"X8"X8" special (SPV.0060) | EACH | 6 | $921.00 | $1,006.00 | $1,006.00 | $1,234.80 | $1,850.86 | $1,461.18 |
| 134 | Special 20. bend 90-degree 4-inch special (SPV.0060) | EACH | 3 | $346.00 | $400.00 | $400.00 | $421.40 | $546.46 | $839.47 |
| 135 | Special 21. bend 90-degree 6-inch special (SPV.0060) | EACH | 2 | $523.00 | $640.00 | $640.00 | $858.20 | $714.20 | $1,026.39 |
| 136 | Special 22. bend 45-degree 8-inch special (SPV.0060) | EACH | 4 | $708.00 | $805.00 | $805.00 | $1,045.80 | $970.78 | $1,222.79 |
| 137 | Special 23. cap 4-inch special (SPV.0060) | EACH | 1 | $118.00 | $250.00 | $250.00 | $273.00 | $398.58 | $522.59 |
| 138 | Special 24. cap 8-inch special (SPV.0060) | EACH | 5 | $211.00 | $350.00 | $350.00 | $447.72 | $650.87 | $614.87 |
| 139 | Special 25. connect to existing water main (SPV.0060) | EACH | 9 | $2,882.00 | $3,000.00 | $3,000.00 | $2,846.10 | $4,289.68 | $4,484.94 |
| 140 | Special 26. sanitary wye 8-inch main (SPV.0060) | EACH | 1 | $108.00 | $170.00 | $170.00 | $229.70 | $521.30 | $617.04 |
| 141 | Special 27. sanitary wye 10-inch main (SPV.0060) | EACH | 56 | $229.00 | $258.00 | $258.00 | $431.30 | $714.98 | $651.70 |
| 142 | Special 28. sanitary lateral reconnection (SPV.0060) | EACH | 56 | $155.00 | $140.00 | $140.00 | $189.00 | $526.47 | $1,563.24 |
| 143 | Special 29. corporation, curb stop & box (set) (SPV.0060) | EACH | 56 | $775.00 | $900.00 | $900.00 | $617.01 | $1,453.03 | $1,724.30 |
| 144 | Special 30. water service reconnection (SPV.0060) | EACH | 56 | $86.00 | $150.00 | $150.00 | $197.39 | $906.00 | $1,176.03 |
| 145 | Special 31. temporary water service project 6995-04-75 (SPV.0060) | EACH | 1 | $5,000.00 | $5,000.00 | $5,000.00 | $62,000 | $0.01 | $120,161 |
| 146 | Special 32. abandon/remove sanitary sewer project 6995-04-75 (SPV.0060) | EACH | 1 | $5,000.00 | $6,000.00 | $6,000.00 | $11,725 | $8,450.00 | $11,895 |
| 147 | Special 33. abandon/remove water main project 6995-04-75 (SPV.0060) | EACH | 1 | $12,000 | $1,000.00 | $1,000.00 | $1,750.00 | $9,450.00 | $22,837 |
| 148 | Special 01. hpde water service 1 to 2-inch special (SPV.0090) | LF | 813 | $61.00 | $65.00 | $65.00 | $115.54 | $48.41 | $64.76 |
| 149 | Special 02. sanitary lateral 6-inch (SPV.0090) | LF | 1,900 | $77.00 | $90.00 | $90.00 | $119.69 | $65.76 | $95.45 |
| 150 | Special 03. sanitary sewer pipe 8- inch special (SPV.0090) | LF | 126 | $121.00 | $163.00 | $163.00 | $137.51 | $139.39 | $131.42 |
| 151 | Special 04. sanitary sewer pipe 10- inch special (SPV.0090) | LF | 2,219 | $106.00 | $115.00 | $115.00 | $121.98 | $134.82 | $147.53 |
| 152 | Special 05. sanitary sewer televising (SPV.0090) | LF | 2,345 | $3.00 | $5.00 | $5.00 | $3.13 | $5.12 | $3.75 |
| 153 | Special 06. PVC water main 4-inch special (SPV.0090) | LF | 80 | $113.00 | $95.00 | $95.00 | $106.00 | $140.81 | $124.62 |
| 154 | Special 07. PVC water main 6-inch special (SPV.0090) | LF | 80 | $119.00 | $97.00 | $97.00 | $112.43 | $140.14 | $122.40 |
| 155 | Special 08. PVC water main 8-inch special (SPV.0090) | LF | 1,330 | $94.00 | $106.00 | $106.00 | $91.07 | $109.79 | $127.67 |
| 156 | Special 09. copper water service 1 to 2-inch special (SPV.0090) | LF | 1,000 | $74.00 | $74.00 | $74.00 | $126.80 | $60.30 | $66.54 |
| 157 | Special 10. ductile iron water main with fluorocarbon gaskets 4-inch special (SPV.0090) | LF | 26 | $161.00 | $138.00 | $138.00 | $181.60 | $194.20 | $170.34 |
| 158 | Special 11. ductile iron water main with fluorocarbon gaskets 6-inch special (SPV.0090) | LF | 85 | $151.00 | $126.00 | $126.00 | $150.69 | $181.43 | $157.84 |
| 159 | Special 12. ductile iron water main with fluorocarbon gaskets 8-inch special (SPV.0090) | LF | 1,253 | $131.00 | $130.00 | $130.00 | $145.46 | $146.66 | $168.81 |
| 160 | Special 01. management of contaminated groundwater (SPV.0120) | MGAL | 10 | $200.00 | $400.00 | $400.00 | $250.00 | $2,000.00 | $600.89 |
| 161 | Special 01. precast panels for soldier pile walls (SPV.0165) | SF | 134 | $64.00 | $61.00 | $61.00 | $61.00 | $61.00 | $61.00 |
| 162 | Special 01. shredded hardwood bark mulch (SPV.0180) | SY | 10 | $25.00 | $25.00 | $25.00 | $25.00 | $40.00 | $20.00 |
| 163 | Special 02. gravel mulch (SPV.0180) | SY | 10 | $30.00 | $30.00 | $30.00 | $100.00 | $50.00 | $150.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of October 14, 2025. Compiled by Mirage Metrics.