WisDOT contract 20251014006 bid tabulation

6995-04-74. Let by Wisconsin DOT on October 14, 2025, Dodge. 8 bids received; low bid $3,389,627 by Advance Construction, Inc..

Owner
Wisconsin DOT
Letting
14 OCT 2025
Pay items
163
Data through
10 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Advance Construction, Inc.$3,389,627Low
2Lalonde Contractors Incorporated$3,657,181+8.0%
3Zignego Company, Inc.$3,818,716+13%
4James Peterson Sons, Inc.$4,047,290+19%
5Vinton Construction Company$4,057,690+20%
6Rock Road Companies, Inc.$4,692,834+38%
7Musson Bros., Inc.$4,879,137+44%
8Parisi Construction, LLC$4,944,913+46%
WisDOT contract 20251014006: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Advance Construction, Inc.2. Lalonde Contractors Incorporated3. Zignego Company, Inc.4. James Peterson Sons, Inc.5. Vinton Construction Company6. Rock Road Companies, Inc.
1Clearing (201.0120)ID277$25.00$31.65$31.65$25.00$31.65$31.65
2Grubbing (201.0220)ID277$22.00$12.66$12.66$20.00$12.66$12.66
3Removing concrete pavement (204.0100)SY11,520$4.67$0.01$7.39$10.44$2.00$10.87
4Removing curb & gutter (204.0150)LF145$5.00$6.00$10.00$10.00$10.00$9.02
5Removing concrete sidewalk (204.0155)SY2,635$3.50$5.98$6.00$3.50$7.85$16.63
6Removing guardrail (204.0165)LF12.50$15.00$15.00$15.00$20.00$3.00$10.00
7Removing manholes (204.0210)EACH2$600.00$300.00$300.00$500.00$672.50$487.96
8Removing inlets (204.0220)EACH10$400.00$350.00$350.00$400.00$495.80$365.98
9Removing storm sewer (size) 01. 12-inch or less (204.0245)LF862$20.00$5.00$5.00$24.06$24.38$14.29
10Removing storm sewer (size) 02. 15-inch (204.0245)LF107$22.00$12.00$12.00$38.74$27.21$14.29
11Removing ancillary structure (structure) 01. station 121+77 (204.0246)EACH1$10,000$3,140.00$3,140.00$3,140.00$3,140.00$3,140.00
12Sealing pipes (204.0280)EACH2$500.00$400.00$400.00$250.00$625.00$1,121.97
13Removing (item description) 01. bollard (204.9060.S)EACH1$100.00$450.00$1,000.00$200.00$185.00$240.46
14Excavation common (205.0100)CY11,230$11.90$26.60$18.00$14.46$24.68$23.55
15Excavation, hauling, and disposal of petroleum contaminated soil (205.0501.S)TON1,000$35.00$50.45$75.00$44.32$50.00$28.15
16Excavation for structures retaining walls (structure) 01. station 121+77 (206.3001)EACH1$10,000$4,630.00$50,000$4,630.00$4,630.00$4,630.00
17Cofferdams (structure) 01. station 121+77 (206.5001)EACH1$72,000$16,812$16,812$16,812$16,812$16,812
18Backfill structure type A (210.1500)TON33$20.00$26.00$100.00$26.00$65.00$26.00
19Finishing roadway (project) 01. 6995-04-74 (213.0100)EACH1$10,000$2,910.00$1,000.00$5,000.00$5,000.00$5,093.29
20Base aggregate dense 3/4-inch (305.0110)TON50$13.00$33.00$100.00$22.45$40.00$30.87
21Base aggregate dense 1 1/4-inch (305.0120)TON5,380$12.47$17.10$20.32$16.98$15.00$24.35
22Base aggregate open-graded (310.0115)CY10$40.00$25.00$200.00$46.81$69.15$22.92
23Breaker run (311.0110)TON8,600$12.00$16.24$19.07$13.06$14.23$19.67
24Concrete pavement 8-inch (415.0080)SY9,840$63.00$67.66$63.00$71.29$65.33$58.44
25Drilled tie bars (416.0610)EACH24$30.00$14.17$30.00$9.65$10.00$14.24
26Drilled dowel bars (416.0620)EACH144$30.00$18.06$30.00$13.89$17.50$18.24
27Tack coat (455.0605)GAL10$18.10$18.10$18.10$18.10$18.10$4.63
28Asphaltic surface (465.0105)TON4$345.00$345.00$970.00$345.00$970.00$1,156.51
29Asphaltic surface driveways and field entrances (465.0120)TON7$345.00$345.00$970.00$345.00$970.00$2,050.87
30Removing and resetting tubular railing (structure) 01. station 121+77 (513.9006.S)EACH1$5,000.00$4,900.00$4,900.00$4,900.00$4,900.00$4,900.00
31Rubberized membrane waterproofing (516.0500)SY3$100.00$60.00$60.00$60.00$60.00$60.00
32Concrete curb & gutter 30-inch type A (601.0409)LF2,855$24.40$33.14$41.50$25.69$25.00$29.00
33Concrete curb & gutter 30-inch type D (601.0411)LF40$57.00$47.98$100.00$88.56$65.00$85.00
34Concrete curb & gutter integral 30- inch type D (601.0452)LF1,800$28.50$20.82$26.50$14.95$25.00$20.00
35Concrete curb pedestrian (601.0600)LF53$47.00$51.25$150.00$77.02$45.00$60.00
36Concrete sidewalk 4-inch (602.0405)SF20,650$6.45$7.26$7.00$5.67$6.75$9.00
37Concrete sidewalk 6-inch (602.0415)SF4,700$7.55$9.69$9.55$8.11$7.85$9.00
38Curb ramp detectable warning field yellow (602.0505)SF250$35.00$44.08$50.00$53.74$35.00$45.00
39Curb ramp detectable warning field radial yellow (602.0605)SF37.09$55.00$68.36$100.00$85.59$55.00$65.00
40Concrete driveway 6-inch (602.0810)SY1,025$69.50$83.35$100.00$73.02$70.50$71.00
41Concrete steps (602.1500)SF17$90.00$89.08$500.00$84.80$90.00$105.00
42Storm sewer pipe reinforced concrete class IV 12-inch (608.0412)LF139$100.00$80.00$80.00$90.73$83.39$118.20
43Storm sewer pipe reinforced concrete class IV 24-inch (608.0424)LF204$130.00$145.00$145.00$87.33$130.06$145.18
44Storm sewer pipe class III-A 12- inch (608.3012)LF173$85.00$62.00$62.00$78.32$83.61$141.23
45Storm sewer pipe class III-A 15- inch (608.3015)LF158$88.00$74.00$74.00$85.42$84.42$143.71
46Storm sewer pipe class III-A 18- inch (608.3018)LF348$75.50$72.00$72.00$53.81$80.91$104.60
47Storm sewer pipe class III-A 24- inch (608.3024)LF901$85.00$90.00$90.00$76.51$100.66$115.32
48Manhole covers type J (611.0530)EACH7$496.00$800.00$800.00$1,336.99$517.78$1,156.54
49Inlet covers type H (611.0624)EACH18$758.00$1,071.00$1,071.00$1,579.32$741.44$1,402.56
50Manholes 4-FT diameter (611.2004)EACH5$2,629.00$3,100.00$3,100.00$2,651.48$4,069.39$3,238.48
51Manholes 5-FT diameter (611.2005)EACH2$4,628.00$4,300.00$4,300.00$4,840.77$5,814.00$4,886.81
52Inlets 4-FT diameter (611.3004)EACH1$2,194.00$2,800.00$2,800.00$1,834.42$4,070.64$3,059.92
53Inlets 2X3-FT (611.3230)EACH18$1,881.00$2,100.00$2,100.00$1,412.38$2,679.79$2,651.04
54Pipe underdrain 6-inch (612.0106)LF100$30.00$12.00$12.00$30.41$27.08$58.94
55Insulation board polystyrene (inch) 01. 2-inch (612.0902.S)SY138.80$18.00$32.00$32.00$27.00$35.31$16.54
56Steel plate beam guard class A (614.0305)LF12.50$50.00$50.00$50.00$50.00$36.00$100.00
57Fence chain link salvaged 4-FT (616.0404)LF11$85.00$85.00$85.00$311.50$45.00$75.00
58Fence chain link salvaged 6-FT (616.0406)LF8$100.00$100.00$100.00$477.50$60.00$75.00
59Maintenance and repair of haul roads (project) 01. 6995-04-74 (618.0100)EACH1$10,000$0.01$1.00$0.01$0.01$0.01
60Mobilization (619.1000)EACH1$151,295$142,654$169,500$288,714$389,000$348,055
61Water (624.0100)MGAL77$50.00$43.00$200.00$40.00$35.00$0.01
62Topsoil (625.0100)SY3,000$5.95$5.95$5.95$8.17$7.00$4.98
63Silt fence (628.1504)LF100$3.00$3.00$3.00$3.50$4.00$5.00
64Silt fence maintenance (628.1520)LF100$1.00$1.00$1.00$0.05$0.01$0.01
65Mobilizations erosion control (628.1905)EACH12$150.00$150.00$150.00$200.00$50.00$100.00
66Mobilizations emergency erosion control (628.1910)EACH6$150.00$150.00$150.00$200.00$50.00$100.00
67Inlet protection type A (628.7005)EACH1$125.00$125.00$125.00$150.00$50.00$150.00
68Inlet protection type D (628.7020)EACH41$95.00$95.00$95.00$125.00$50.00$120.00
69Tracking pads (628.7560)EACH3$1,000.00$1,561.00$1,000.00$1,500.00$0.01$1,018.63
70Fertilizer type B (629.0210)CWT2$15.00$15.00$15.00$90.00$75.00$150.00
71Sod water (631.0300)MGAL170$40.00$40.00$40.00$75.00$35.00$100.00
72Sod lawn (631.1000)SY3,000$7.95$7.95$7.95$12.50$7.00$10.00
73Posts tubular steel 2X2-inch X 14- FT (634.0814)EACH22$220.00$220.00$220.00$200.00$215.00$190.00
74Posts tubular steel 2X2-inch X 16- FT (634.0816)EACH5$230.00$230.00$230.00$250.00$225.00$210.00
75Signs type II reflective H (637.2210)SF137.90$23.00$23.00$23.00$19.50$25.00$20.00
76Moving signs type II (638.2102)EACH3$120.00$120.00$120.00$75.00$100.00$150.00
77Removing signs type II (638.2602)EACH30$35.00$35.00$35.00$35.00$10.00$35.00
78Removing small sign supports (638.3000)EACH26$35.00$35.00$35.00$35.00$10.00$35.00
79Moving small sign supports (638.4000)EACH3$80.00$80.00$80.00$75.00$10.00$100.00
80Field office type B (642.5001)EACH1$9,000.00$18,164$10,000$17,500$10,000$16,500
81Traffic control barricades type III (643.0420)DAY3,200$0.61$0.61$0.61$0.61$0.61$0.61
82Traffic control warning lights type A (643.0705)DAY6,400$0.21$0.21$0.21$0.21$0.21$0.21
83Traffic control signs (643.0900)DAY42,500$0.25$0.25$0.25$0.25$0.25$0.25
84Traffic control covering signs type I (643.0910)EACH3$107.54$107.54$107.54$107.54$107.54$107.54
85Traffic control covering signs type II (643.0920)EACH7$69.18$69.18$69.18$69.18$69.18$69.18
86Traffic control signs PCMS (643.1050)DAY14$73.02$73.02$73.02$73.02$73.02$73.02
87Traffic control (643.5000)EACH1$7,293.44$7,293.44$7,293.44$7,293.44$7,293.44$7,293.44
88Temporary pedestrian surface plate (644.1430)SF200$16.74$16.74$16.74$16.74$16.74$16.74
89Temporary pedestrian surface matting (644.1440)SF400$12.54$12.54$12.54$12.54$12.54$12.54
90Temporary pedestrian curb ramp (644.1601)DAY20$24.83$24.83$24.83$24.83$24.83$24.83
91Temporary pedestrian detectable warning field (644.1605)SF20$33.98$33.98$33.98$33.98$33.98$33.98
92Temporary pedestrian barricade (644.1810)LF400$5.31$5.31$5.31$5.31$5.31$5.31
93Geotextile type DF schedule A (645.0111)SY60$2.00$1.00$10.00$6.42$7.68$0.70
94Geogrid type SR (645.0220)SY12,400$2.00$1.92$2.00$2.05$1.30$2.16
95Marking line epoxy 6-inch (646.2020)LF6,275$2.15$0.75$0.75$1.90$0.75$1.90
96Marking arrow epoxy (646.5020)EACH17$300.00$225.00$225.00$240.00$225.00$240.00
97Marking word epoxy (646.5120)EACH3$350.00$240.00$240.00$350.00$240.00$350.00
98Marking symbol epoxy (646.5220)EACH17$285.00$350.00$350.00$240.00$350.00$240.00
99Marking stop line epoxy 18-inch (646.6120)LF95$16.10$13.00$13.00$33.00$13.00$33.00
100Marking crosswalk epoxy transverse line 6-inch (646.7420)LF1,055$9.75$10.00$10.00$19.00$10.00$19.00
101Construction staking storm sewer (650.4000)EACH26$220.00$220.00$220.00$65.14$65.14$65.14
102Construction staking subgrade (650.4500)LF2,272$0.01$0.01$0.01$0.01$0.01$0.01
103Construction staking curb gutter and curb & gutter (650.5500)LF93$5.00$5.00$5.00$1.25$1.25$1.25
104Construction staking concrete pavement (650.7000)LF2,272$2.75$2.75$2.75$1.45$1.45$1.45
105Construction staking curb ramps (650.9000)EACH28$100.00$100.00$100.00$105.84$105.84$105.84
106Construction staking sidewalk (project) 01. 6995-04-74 (650.9500)EACH1$100.00$100.00$100.00$5,162.50$5,162.50$5,162.50
107Construction staking supplemental control (project) 01. 6995-04-74 (650.9911)EACH1$10.00$10.00$10.00$960.39$960.39$960.39
108Construction staking slope stakes (650.9920)LF2,272$2.00$2.00$2.00$1.10$1.10$1.10
109Sawing asphalt (690.0150)LF810$3.00$1.75$1.62$1.75$3.00$1.85
110Sawing concrete (690.0250)LF1,400$4.00$2.35$1.62$2.35$3.00$2.20
111Incentive compressive strength concrete pavement (715.0720)DOL2,952$1.00$1.00$1.00$1.00$1.00$1.00
112Incentive iri ride (740.0440)DOL1,721$1.00$1.00$1.00$1.00$1.00$1.00
113On-the-job training apprentice at $5.00/HR (ASP.1T0A)HRS2,400$5.00$5.00$5.00$5.00$5.00$5.00
114On-the-job training graduate at $5.00/HR (ASP.1T0G)HRS2,120$5.00$5.00$5.00$5.00$5.00$5.00
115Special 01. utility line opening (ulo) (SPV.0060)EACH10$700.00$300.00$300.00$700.00$866.90$975.00
116Special 02. reconnect storm sewer laterals (SPV.0060)EACH2$150.00$300.00$300.00$172.10$757.38$891.39
117Special 03. inlet cover type driveway special (SPV.0060)EACH1$719.00$835.00$835.00$1,381.92$753.05$1,415.33
118Special 04. clay dam within contaminated soils (SPV.0060)EACH7$500.00$500.00$500.00$1,000.00$1,630.71$891.39
119Special 05. remove EX. sanitary manhole (SPV.0060)EACH11$600.00$300.00$300.00$500.00$551.82$762.17
120Special 06. remove EX. water valve box (SPV.0060)EACH19$250.00$50.00$50.00$350.00$196.47$464.34
121Special 07. remove EX. hydrant (SPV.0060)EACH6$600.00$350.00$350.00$810.00$605.66$735.20
122Special 08. remove EX. water manhole (SPV.0060)EACH1$600.00$400.00$400.00$500.00$978.99$1,887.13
123Special 09. sanitary manhole (48- inch) (SPV.0060)EACH9$4,422.00$4,600.00$4,600.00$4,923.53$6,479.04$5,607.31
124Special 10. sanitary MH cover type J-special (SPV.0060)EACH9$513.00$633.00$633.00$1,717.80$535.72$1,176.27
125Special 11. sanitary sewer cleanout (SPV.0060)EACH2$977.00$1,000.00$1,000.00$738.43$1,148.26$1,441.39
126Special 12. connect to existing sanitary sewer (SPV.0060)EACH5$350.00$450.00$450.00$2,104.28$662.11$2,744.78
127Special 13. water valve & box 4- inch (SPV.0060)EACH4$1,614.00$1,765.00$1,765.00$2,224.60$1,982.52$2,410.99
128Special 14. water valve & box 6- inch (SPV.0060)EACH8$1,981.00$2,100.00$2,100.00$2,775.85$2,301.33$2,767.10
129Special 15. water valve & box 8- inch (SPV.0060)EACH16$2,812.00$2,700.00$2,700.00$3,831.80$3,099.34$3,662.70
130Special 16. fire hydrant (SPV.0060)EACH6$6,064.00$7,700.00$7,700.00$8,117.85$6,119.65$7,436.23
131Special 17. tees 8"X4"X8" special (SPV.0060)EACH4$795.00$900.00$900.00$1,113.00$1,475.31$1,320.39
132Special 18. tees 8"X6"X8" special (SPV.0060)EACH7$897.00$940.00$940.00$1,250.20$1,888.01$1,502.84
133Special 19. tees 8"X8"X8" special (SPV.0060)EACH6$921.00$1,006.00$1,006.00$1,234.80$1,850.86$1,461.18
134Special 20. bend 90-degree 4-inch special (SPV.0060)EACH3$346.00$400.00$400.00$421.40$546.46$839.47
135Special 21. bend 90-degree 6-inch special (SPV.0060)EACH2$523.00$640.00$640.00$858.20$714.20$1,026.39
136Special 22. bend 45-degree 8-inch special (SPV.0060)EACH4$708.00$805.00$805.00$1,045.80$970.78$1,222.79
137Special 23. cap 4-inch special (SPV.0060)EACH1$118.00$250.00$250.00$273.00$398.58$522.59
138Special 24. cap 8-inch special (SPV.0060)EACH5$211.00$350.00$350.00$447.72$650.87$614.87
139Special 25. connect to existing water main (SPV.0060)EACH9$2,882.00$3,000.00$3,000.00$2,846.10$4,289.68$4,484.94
140Special 26. sanitary wye 8-inch main (SPV.0060)EACH1$108.00$170.00$170.00$229.70$521.30$617.04
141Special 27. sanitary wye 10-inch main (SPV.0060)EACH56$229.00$258.00$258.00$431.30$714.98$651.70
142Special 28. sanitary lateral reconnection (SPV.0060)EACH56$155.00$140.00$140.00$189.00$526.47$1,563.24
143Special 29. corporation, curb stop & box (set) (SPV.0060)EACH56$775.00$900.00$900.00$617.01$1,453.03$1,724.30
144Special 30. water service reconnection (SPV.0060)EACH56$86.00$150.00$150.00$197.39$906.00$1,176.03
145Special 31. temporary water service project 6995-04-75 (SPV.0060)EACH1$5,000.00$5,000.00$5,000.00$62,000$0.01$120,161
146Special 32. abandon/remove sanitary sewer project 6995-04-75 (SPV.0060)EACH1$5,000.00$6,000.00$6,000.00$11,725$8,450.00$11,895
147Special 33. abandon/remove water main project 6995-04-75 (SPV.0060)EACH1$12,000$1,000.00$1,000.00$1,750.00$9,450.00$22,837
148Special 01. hpde water service 1 to 2-inch special (SPV.0090)LF813$61.00$65.00$65.00$115.54$48.41$64.76
149Special 02. sanitary lateral 6-inch (SPV.0090)LF1,900$77.00$90.00$90.00$119.69$65.76$95.45
150Special 03. sanitary sewer pipe 8- inch special (SPV.0090)LF126$121.00$163.00$163.00$137.51$139.39$131.42
151Special 04. sanitary sewer pipe 10- inch special (SPV.0090)LF2,219$106.00$115.00$115.00$121.98$134.82$147.53
152Special 05. sanitary sewer televising (SPV.0090)LF2,345$3.00$5.00$5.00$3.13$5.12$3.75
153Special 06. PVC water main 4-inch special (SPV.0090)LF80$113.00$95.00$95.00$106.00$140.81$124.62
154Special 07. PVC water main 6-inch special (SPV.0090)LF80$119.00$97.00$97.00$112.43$140.14$122.40
155Special 08. PVC water main 8-inch special (SPV.0090)LF1,330$94.00$106.00$106.00$91.07$109.79$127.67
156Special 09. copper water service 1 to 2-inch special (SPV.0090)LF1,000$74.00$74.00$74.00$126.80$60.30$66.54
157Special 10. ductile iron water main with fluorocarbon gaskets 4-inch special (SPV.0090)LF26$161.00$138.00$138.00$181.60$194.20$170.34
158Special 11. ductile iron water main with fluorocarbon gaskets 6-inch special (SPV.0090)LF85$151.00$126.00$126.00$150.69$181.43$157.84
159Special 12. ductile iron water main with fluorocarbon gaskets 8-inch special (SPV.0090)LF1,253$131.00$130.00$130.00$145.46$146.66$168.81
160Special 01. management of contaminated groundwater (SPV.0120)MGAL10$200.00$400.00$400.00$250.00$2,000.00$600.89
161Special 01. precast panels for soldier pile walls (SPV.0165)SF134$64.00$61.00$61.00$61.00$61.00$61.00
162Special 01. shredded hardwood bark mulch (SPV.0180)SY10$25.00$25.00$25.00$25.00$40.00$20.00
163Special 02. gravel mulch (SPV.0180)SY10$30.00$30.00$30.00$100.00$50.00$150.00
WisDOT contract 20251014006: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.

Every contract let that day: WisDOT letting of October 14, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy