WisDOT contract 20260113016 bid tabulation
C La Crosse, Losey Boulevard; Main Street Intersection (LOC STR, La Crosse County City of La Crosse, Losey Boulevard). Let by Wisconsin DOT on January 13, 2026, La Crosse. 3 bids received; low bid $679,524 by Pember Companies, Inc..
- Owner
- Wisconsin DOT
- Letting
- 13 JAN 2026
- Pay items
- 105
- Data through
- 10 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Pember Companies, Inc. | $679,524 | Low |
| 2 | Chippewa Concrete Services, Inc. | $682,103 | 0.0% |
| 3 | Fowler & Hammer, Inc. | $790,602 | +16% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Pember Companies, Inc. | 2. Chippewa Concrete Services, Inc. | 3. Fowler & Hammer, Inc. |
|---|---|---|---|---|---|---|
| 1 | Removing concrete pavement (204.0100) | SY | 57 | $60.80 | $56.52 | $66.69 |
| 2 | Removing asphaltic surface (204.0110) | SY | 8 | $27.05 | $194.52 | $229.55 |
| 3 | Removing curb & gutter (204.0150) | LF | 154 | $14.05 | $10.11 | $11.93 |
| 4 | Removing concrete sidewalk (204.0155) | SY | 171 | $45.60 | $9.09 | $10.73 |
| 5 | Removing concrete bases (204.0195) | EACH | 10 | $725.00 | $521.36 | $615.25 |
| 6 | Finishing roadway (project) 01. 5991-07-81 (213.0100) | EACH | 1 | $500.00 | $5,275.00 | $10,000 |
| 7 | Base aggregate dense 3/4-inch (305.0110) | TON | 37 | $97.05 | $103.59 | $122.25 |
| 8 | Base aggregate dense 1 1/4-inch (305.0120) | TON | 88 | $89.55 | $60.30 | $71.16 |
| 9 | Concrete base 7-inch (320.0135) | SY | 56 | $82.60 | $159.38 | $170.90 |
| 10 | Drilled tie bars (416.0610) | EACH | 98 | $7.25 | $16.91 | $10.50 |
| 11 | Drilled dowel bars (416.0620) | EACH | 28 | $14.30 | $20.67 | $27.10 |
| 12 | Tack coat (455.0605) | GAL | 18.40 | $26.40 | $26.22 | $30.94 |
| 13 | Asphaltic surface (465.0105) | TON | 37 | $411.20 | $398.04 | $469.73 |
| 14 | Concrete curb & gutter 30-inch type K (601.0417) | LF | 122 | $50.40 | $105.36 | $67.15 |
| 15 | Concrete curb & gutter 30-inch type L (601.0419) | LF | 53 | $50.40 | $105.36 | $76.20 |
| 16 | Concrete curb pedestrian (601.0600) | LF | 139 | $47.25 | $63.10 | $70.00 |
| 17 | Concrete sidewalk 5-inch (602.0410) | SF | 821 | $8.50 | $23.03 | $15.80 |
| 18 | Curb ramp detectable warning field natural patina (602.0515) | SF | 96 | $74.25 | $65.41 | $77.40 |
| 19 | Maintenance and repair of haul roads (project) 01. 5991-07-81 (618.0100) | EACH | 1 | $500.00 | $1,582.50 | $5,000.00 |
| 20 | Mobilization (619.1000) | EACH | 1 | $80,885 | $66,363 | $73,056 |
| 21 | Concrete median sloped nose (620.0300) | SF | 14 | $29.20 | $23.03 | $56.00 |
| 22 | Water (624.0100) | MGAL | 2.60 | $100.00 | $58.87 | $69.47 |
| 23 | Topsoil (625.0100) | SY | 104 | $26.20 | $35.51 | $41.91 |
| 24 | Mulching (627.0200) | SY | 104 | $5.70 | $1.32 | $1.56 |
| 25 | Mobilizations erosion control (628.1905) | EACH | 4 | $300.00 | $263.75 | $311.25 |
| 26 | Mobilizations emergency erosion control (628.1910) | EACH | 4 | $250.00 | $1.58 | $1.87 |
| 27 | Erosion mat urban class I type B (628.2008) | SY | 10 | $6.20 | $9.50 | $11.21 |
| 28 | Inlet protection type C (628.7015) | EACH | 6 | $116.45 | $68.58 | $80.93 |
| 29 | Fertilizer type B (629.0210) | CWT | 1 | $360.00 | $237.38 | $280.13 |
| 30 | Seeding mixture no. 40 (630.0140) | LB | 4.90 | $37.00 | $36.93 | $43.58 |
| 31 | Seeding temporary (630.0200) | LB | 3 | $15.00 | $15.83 | $18.68 |
| 32 | Seed water (630.0500) | MGAL | 2.60 | $150.00 | $263.75 | $311.25 |
| 33 | Posts tubular steel 2X2-inch X 8-FT (634.0808) | EACH | 2 | $295.00 | $263.75 | $311.25 |
| 34 | Signs type II reflective H (637.2210) | SF | 12.33 | $35.30 | $30.07 | $35.48 |
| 35 | Signs type II reflective H folding (637.2215) | SF | 20.72 | $35.40 | $31.28 | $36.91 |
| 36 | Moving signs type II (638.2102) | EACH | 4 | $280.00 | $258.48 | $305.03 |
| 37 | Field office type B (642.5001) | EACH | 1 | $9,500.00 | $7,912.50 | $12,000 |
| 38 | Traffic control drums (643.0300) | DAY | 1,011 | $1.05 | $1.06 | $1.25 |
| 39 | Traffic control barricades type III (643.0420) | DAY | 140 | $3.20 | $3.17 | $3.74 |
| 40 | Traffic control warning lights type A (643.0705) | DAY | 140 | $0.55 | $0.53 | $0.62 |
| 41 | Traffic control warning lights type C (643.0715) | DAY | 303 | $0.55 | $0.53 | $0.62 |
| 42 | Traffic control signs (643.0900) | DAY | 1,471 | $1.05 | $1.06 | $1.25 |
| 43 | Traffic control signs PCMS (643.1050) | DAY | 28 | $79.55 | $79.13 | $93.38 |
| 44 | Temporary marking line removable tape 6-inch (643.3180) | LF | 332 | $1.60 | $1.58 | $1.87 |
| 45 | Traffic control interim lane closure (643.4100) | EACH | 4 | $530.00 | $527.50 | $622.50 |
| 46 | Traffic control (643.5000) | EACH | 1 | $12,000 | $5,275.00 | $11,725 |
| 47 | Temporary pedestrian surface matting (644.1440) | SF | 100 | $15.90 | $15.83 | $18.68 |
| 48 | Temporary pedestrian curb ramp (644.1601) | DAY | 26 | $53.00 | $52.75 | $62.25 |
| 49 | Temporary pedestrian detectable warning field (644.1605) | SF | 20 | $15.90 | $15.83 | $18.68 |
| 50 | Marking curb epoxy (646.8120) | LF | 327 | $13.80 | $13.72 | $16.19 |
| 51 | Marking island nose epoxy (646.8220) | EACH | 4 | $350.00 | $348.15 | $410.85 |
| 52 | Marking removal line 6-inch (646.9002) | LF | 150 | $5.30 | $5.28 | $6.23 |
| 53 | Construction staking curb gutter and curb & gutter (650.5500) | LF | 175 | $2.10 | $4.22 | $2.49 |
| 54 | Construction staking electrical installations (project) 01. 5991-07- 81 (650.8501) | EACH | 1 | $1,325.00 | $580.25 | $1,556.25 |
| 55 | Construction staking curb ramps (650.9000) | EACH | 4 | $132.55 | $189.90 | $155.63 |
| 56 | Construction staking sidewalk (project) 01. 5991-07-81 (650.9500) | EACH | 1 | $900.00 | $527.50 | $1,058.25 |
| 57 | Construction staking supplemental control (project) 01. 5991-07-81 (650.9911) | EACH | 1 | $1,060.00 | $844.00 | $1,245.00 |
| 58 | Conduit rigid nonmetallic schedule 40 2-inch (652.0225) | LF | 81 | $13.90 | $13.83 | $16.32 |
| 59 | Conduit rigid nonmetallic schedule 40 3-inch (652.0235) | LF | 237 | $14.50 | $14.44 | $17.04 |
| 60 | Conduit special 3-inch (652.0615) | LF | 500 | $23.75 | $23.61 | $27.86 |
| 61 | Install conduit into existing item (652.0700.S) | EACH | 2 | $400.00 | $396.24 | $375.58 |
| 62 | Pull boxes steel 24X42-inch (653.0140) | EACH | 8 | $1,385.00 | $1,376.48 | $1,624.38 |
| 63 | Removing pull boxes (653.0905) | EACH | 12 | $330.00 | $328.22 | $387.33 |
| 64 | Concrete bases type 1 (654.0101) | EACH | 2 | $935.00 | $931.32 | $1,099.05 |
| 65 | Concrete bases type 2 (654.0102) | EACH | 4 | $1,017.00 | $1,011.69 | $1,193.89 |
| 66 | Concrete bases type 10 (654.0110) | EACH | 2 | $10,875 | $10,818 | $12,766 |
| 67 | Concrete bases type 10-special (654.0120) | EACH | 2 | $15,100 | $15,022 | $17,727 |
| 68 | Cable traffic signal 5-14 AWG (655.0230) | LF | 439 | $2.30 | $2.30 | $2.71 |
| 69 | Cable traffic signal 7-14 AWG (655.0240) | LF | 495 | $2.85 | $2.81 | $3.31 |
| 70 | Cable traffic signal 12-14 AWG (655.0260) | LF | 949 | $5.10 | $5.05 | $5.96 |
| 71 | Cable type UF 2-12 AWG grounded (655.0305) | LF | 498 | $2.85 | $2.83 | $3.34 |
| 72 | Electrical wire traffic signals 10 AWG (655.0515) | LF | 961 | $1.65 | $1.62 | $1.92 |
| 73 | Electrical wire lighting 12 AWG (655.0610) | LF | 580 | $1.70 | $1.66 | $1.95 |
| 74 | Loop detector wire (655.0800) | LF | 1,216 | $1.75 | $1.75 | $2.07 |
| 75 | Traffic signal evp detector cable (655.0900) | LF | 143 | $1.65 | $1.62 | $1.92 |
| 76 | Pedestal bases (657.0100) | EACH | 2 | $410.00 | $405.25 | $478.23 |
| 77 | Transformer bases breakaway 11 1/2-inch bolt circle (657.0255) | EACH | 6 | $830.00 | $826.91 | $975.83 |
| 78 | Poles type 3 (657.0310) | EACH | 4 | $3,900.00 | $3,866.82 | $4,563.21 |
| 79 | Poles type 9 (657.0345) | EACH | 2 | $9,350.00 | $9,294.96 | $10,969 |
| 80 | Poles type 9-special (657.0347) | EACH | 2 | $12,975 | $12,905 | $15,229 |
| 81 | Traffic signal standards aluminum 3.5-FT (657.0405) | EACH | 2 | $625.00 | $618.82 | $730.27 |
| 82 | Monotube arms 25-FT (657.0525) | EACH | 2 | $5,025.00 | $4,997.87 | $5,897.96 |
| 83 | Monotube arms 35-FT-special (657.0536) | EACH | 2 | $5,900.00 | $5,872.13 | $6,929.67 |
| 84 | Luminaire arms truss type 4 1/2- inch clamp 15-FT (657.0715) | EACH | 4 | $1,145.00 | $1,140.66 | $1,346.08 |
| 85 | Traffic signal face 3S 12-inch (658.0173) | EACH | 10 | $985.00 | $978.54 | $1,154.77 |
| 86 | Traffic signal face 5S 12-inch (658.0175) | EACH | 4 | $1,490.00 | $1,480.47 | $1,747.10 |
| 87 | Pedestrian signal face 16-inch (658.0416) | EACH | 8 | $645.00 | $641.31 | $756.81 |
| 88 | Signal mounting hardware (location) 01. losey & main intersection (658.5070) | EACH | 1 | $6,410.00 | $6,373.88 | $7,521.78 |
| 89 | Luminaires utility LED C (659.1125) | EACH | 4 | $400.00 | $395.35 | $466.55 |
| 90 | Lamp, ballast, LED, switch disposal by contractor (659.5000.S) | EACH | 25 | $26.50 | $26.42 | $31.17 |
| 91 | Temporary traffic signals for intersections (location) 01. losey boulevard & main street (661.0201) | EACH | 1 | $121,000 | $120,279 | $141,941 |
| 92 | Sawing asphalt (690.0150) | LF | 47 | $4.30 | $2.07 | $10.00 |
| 93 | Sawing concrete (690.0250) | LF | 641 | $7.20 | $3.11 | $10.00 |
| 94 | On-the-job training apprentice at $5.00/HR (ASP.1T0A) | HRS | 1,200 | $5.00 | $5.00 | $5.00 |
| 95 | On-the-job training graduate at $5.00/HR (ASP.1T0G) | HRS | 600 | $5.00 | $5.00 | $5.00 |
| 96 | Special 01. marking arrow symbol grooved (epoxy) (SPV.0060) | EACH | 4 | $285.00 | $284.85 | $336.15 |
| 97 | Special 02. furnish and install evp detector (SPV.0060) | EACH | 1 | $1,855.00 | $1,843.38 | $2,175.36 |
| 98 | Special 03. APS push button system (SPV.0060) | EACH | 1 | $14,570 | $14,491 | $17,101 |
| 99 | Special 04. remove traffic signals (SPV.0060) | EACH | 1 | $8,440.00 | $8,396.72 | $9,908.93 |
| 100 | Special 05. video detection system (SPV.0060) | EACH | 1 | $52,000 | $51,691 | $61,000 |
| 101 | Special 01. marking line epoxy grooved 4-inch (SPV.0090) | LF | 272 | $7.40 | $7.39 | $8.72 |
| 102 | Special 02. marking line epoxy grooved 8-inch (SPV.0090) | LF | 255 | $9.55 | $9.50 | $11.21 |
| 103 | Special 03. marking crosswalk epoxy grooved transverse line 12- inch (SPV.0090) | LF | 425 | $22.30 | $22.16 | $26.15 |
| 104 | Special 04. marking stop bar epoxy grooved transverse line 12-inch (SPV.0090) | LF | 115 | $22.30 | $22.16 | $26.15 |
| 105 | Special 01. concrete raised median (SPV.0165) | SF | 261 | $12.35 | $47.53 | $30.30 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from WisDOT's tabulation for this contract. WisDOT All Bids Received PDFs, one per letting (awarded contracts only), January 2022 to November 2026. WisDOT prints unit prices to two decimals but computes line amounts from the full price, so about one bid in fifteen misses its total and is left out.
Every contract let that day: WisDOT letting of January 13, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.