CSI MasterFormat Divisions: The Complete List and How Estimators Use It

CSI MasterFormat is the master list of numbers and titles that North American project teams use to organize specifications, cost data and drawing notes by work result. It has 50 divisions, numbered 00 to 49, of which 35 are in use and 15 are reserved for future expansion, and the current edition is MasterFormat 2026. This reference lists every division with what it covers, explains how a six-digit section number reads, shows where the old Divisions 15 and 16 went, and sets out when an estimate should follow MasterFormat and when UniFormat's elements serve better.

Published
Sources checked
Reading time
13 min
Written by
Mirage Metrics team

Scope: MasterFormat as published by the Construction Specifications Institute (CSI) and Construction Specifications Canada (CSC). The division list and numbering rules were checked against CSI's own 2018 edition documents, the last edition whose full text we could read, and the current edition facts against CSI's 2026 pages. MasterFormat is CSI copyright: this page lists division titles and uses a few section numbers as examples, described in our own words. Mirage Metrics is not affiliated with CSI.

Decision snapshot

Best suited to
Estimators, preconstruction managers, project engineers and document controllers on US and Canadian commercial, institutional and industrial work.
Inputs needed
The project manual (or its table of contents), the drawing set, the edition of MasterFormat the specification follows, and your company's cost codes.
What can be automated
Listing the sections a specification contains, sorting notes and paragraphs under their division and section, building the submittal register from Part 1 of each section, coding takeoff lines to divisions, flagging gaps between specification and estimate.
What requires human approval
Which division an item belongs to when it could sit in two, the boundaries of each bid package, what each scope letter includes, quantities the drawings leave to judgment, and every price.
When this approach is insufficient
Early design, before materials are chosen (use UniFormat elements); UK work measured under NRM 2; heavy civil or process work organized by the owner's own pay items; and any contract that defines its own breakdown.

What MasterFormat is, and which edition is current

CSI defines MasterFormat as a master list of numbers and titles identifying work results and construction practices, used mainly to organize project manuals and detailed cost information and to relate drawing notations to specifications. A work result, in CSI's words, is an aspect of the project produced by applying a skill or trade to construction resources: the concrete slab, not the bag of cement. CSI describes the standard as the construction industry's standardized language for project documentation.

It is produced jointly by CSI in the United States and Construction Specifications Canada, which is why the same numbers appear on both sides of the border. The format dates back to 1963; the first edition under the MasterFormat name was produced by both organizations in 1978, and the 2004 edition was the largest change in its history, from 16 divisions to 50 and from five-digit to six-digit numbers.

The current edition is MasterFormat 2026. Construction Specifications Canada told its members on February 13, 2026 that it was coming to them. CSI reports 2,185 new and 617 reorganized listings, with Divisions 32 Exterior Improvements and 34 Transportation accounting for more than 80% of the structural changes, noticeable expansion in Divisions 28 and 31, maintenance updates in Divisions 01, 06, 09, 10 and 26, and Divisions 02, 07, 27 and 40 largely stable. It is distributed through CSI Dynamic Standards, CSI's online platform. Before it, CSI and CSC revised MasterFormat every year from late 2008 and every two years from 2012, with a 2020 edition before the 2026 one.

Source: CSI and CSC, MasterFormat 2018 Introduction and Applications Guide; CSI, MasterFormat 2026; CSC, February 13, 2026.

Which edition does your project use?

A specification written in 2024 follows an earlier edition than the one CSI sells today, and most master guide specifications lag the current list. The section numbers that matter on a project are the ones in its own project manual. Use the current edition to look things up, and the project manual to code the estimate.

How a MasterFormat number reads

Since 2004, a MasterFormat number has six digits in three pairs, written with spaces between the pairs: 07 51 13. The first pair is the division, level 1. The second pair is level 2, the third pair level 3. A pair of zeros means that level is not used, so 07 50 00 is a level 2 number. Where more detail is needed, a fourth pair follows a decimal point: 07 51 13.13 is level 4. CSI's example runs from membrane roofing down to a cold-applied built-up asphalt roof, and the table below follows it.

MasterFormat levels, from division to user-defined extension (examples from CSI's Applications Guide, titles paraphrased)
LevelPatternExampleWhat it means
Level 1XX 00 0007 00 00The division itself. CSI lists a division-level number in every division, usable as a section on a very small project.
Level 2XX XX 0007 50 00, 07 51 00A broad subject. Numbers ending in X0 00 often group related level 2 subjects: here, membrane roofing as a family, then built-up bituminous roofing inside it.
Level 3XX XX XX07 51 13A narrower work result: built-up roofing with asphalt.
Level 4XX XX XX.XX07 51 13.13A further breakdown after a decimal point: the cold-applied version. Some level 4 numbers are assigned by CSI, others by users.
Level 5XX XX XX.XX.user code08 11 13.16.ABC1User-defined, for internal filing only (a client, a project, a product grade). Never used in a project manual.
MasterFormat levels, from division to user-defined extension (examples from CSI's Applications Guide, titles paraphrased)

A few rules from CSI's Applications Guide save a lot of confusion:

  • Same places in every division. Operation and maintenance sits at XX 01 00, common work results (requirements shared by several sections of the division) at XX 05 00, schedules at XX 06 00 and commissioning at XX 08 00. In the facility services divisions, insulation sits at 2X 07 00 and instrumentation and control at 2X 09 00, which is why HVAC controls appear at 23 09 00.
  • Numbers ending in zero are usually not assigned at levels 3 and 4, so that 11 14 43 is not mistaken for a child of 11 14 40. Assigned numbers mostly step by three: 13, 16, 19, 23, 26, 29.
  • A number goes with its title, and only that title. Users may create new titles at levels 2 to 4 inside a division, at an unassigned number that fits the subject, but never inside a reserved division and never a new division.
  • Display. Spaces between the first three pairs and a decimal point before level 4 is the recommended form; 07 5113.13 and 075113.13 are accepted variants. In software, keep whichever form you choose consistent.

Source: CSI and CSC, MasterFormat 2018 Introduction and Applications Guide, sections on expansion of the numbering system, assigned numbers, designated locations and display.

The 50 divisions, 00 to 49

MasterFormat has two groups. The Procurement and Contracting Requirements Group is Division 00 alone. The Specifications Group holds Divisions 01 to 49 in five subgroups: General Requirements (01), Facility Construction (02 to 19), Facility Services (20 to 29), Site and Infrastructure (30 to 39) and Process Equipment (40 to 49). Of the 49 specification divisions, 15 are reserved for future expansion, which leaves 34 in use plus Division 00.

CSI MasterFormat divisions 00 to 49 with their subgroup and a one-line scope (titles as published by CSI; scope paraphrased from the level 2 subjects of the 2018 Master List)
DivisionTitleGroup or subgroupWhat it covers
00Procurement and Contracting RequirementsProcurement and Contracting Requirements GroupIntroductory information, bidding or procurement documents and forms, the agreement, bonds and certificates, conditions of the contract. Not specifications.
01General RequirementsGeneral RequirementsRules for the whole project: summary of work, price and payment procedures (allowances, unit prices, alternates, schedule of values), administration, submittal procedures, quality, temporary facilities, closeout.
02Existing ConditionsFacility ConstructionAssessment and surveys of what is already there, subsurface investigation, demolition and structure moving, site remediation.
03ConcreteFacility ConstructionForming and accessories, reinforcing, cast-in-place and precast concrete, finishing and curing.
04MasonryFacility ConstructionUnit masonry (clay, concrete, glass), stone assemblies, refractory and corrosion-resistant masonry.
05MetalsFacility ConstructionStructural steel and aluminum framing, metal joists, decking, cold-formed framing, metal fabrications, decorative metal.
06Wood, Plastics, and CompositesFacility ConstructionRough carpentry and framing, sheathing, heavy timber, finish carpentry, architectural woodwork and casework, structural plastics and composites.
07Thermal and Moisture ProtectionFacility ConstructionDampproofing and waterproofing, insulation, air and vapor barriers, roofing and siding panels, membrane and steep slope roofing, flashing and sheet metal, fire and smoke protection, joint sealing.
08OpeningsFacility ConstructionDoors and frames, entrances, storefronts and curtain walls, windows, skylights, hardware, glazing, louvers and vents.
09FinishesFacility ConstructionPlaster and gypsum board, tiling, ceilings, flooring, wall finishes, acoustic treatment, painting and coating.
10SpecialtiesFacility ConstructionSignage and other information specialties, toilet compartments and accessories, fireplaces and stoves, safety specialties, storage and exterior specialties.
11EquipmentFacility ConstructionVehicle and loading dock, commercial, residential, foodservice, educational, scientific and healthcare equipment.
12FurnishingsFacility ConstructionArt, window treatments, casework, furniture, multiple seating.
13Special ConstructionFacility ConstructionPools, fountains and other special facility components, special purpose rooms, fabric structures, space frames and other special structures.
14Conveying EquipmentFacility ConstructionDumbwaiters, elevators, escalators and moving walks, lifts, turntables.
15Reserved for Future ExpansionFacility ConstructionNothing is specified here; CSI asks users not to assign numbers in a reserved division.
16Reserved for Future ExpansionFacility ConstructionNothing is specified here; CSI asks users not to assign numbers in a reserved division.
17Reserved for Future ExpansionFacility ConstructionNothing is specified here; CSI asks users not to assign numbers in a reserved division.
18Reserved for Future ExpansionFacility ConstructionNothing is specified here; CSI asks users not to assign numbers in a reserved division.
19Reserved for Future ExpansionFacility ConstructionNothing is specified here; CSI asks users not to assign numbers in a reserved division.
20Reserved for Future ExpansionFacility ServicesNothing is specified here; CSI asks users not to assign numbers in a reserved division.
21Fire SuppressionFacility ServicesWater-based systems such as sprinklers and standpipes, fire-extinguishing systems, fire pumps.
22PlumbingFacility ServicesPlumbing piping and pumps, water distribution, sanitary and storm drainage inside the facility, plumbing equipment, fixtures.
23Heating, Ventilating, and Air Conditioning (HVAC)Facility ServicesFuel systems, HVAC piping and pumps, air distribution, central heating and cooling equipment, central and decentralized HVAC units, HVAC controls.
24Reserved for Future ExpansionFacility ServicesNothing is specified here; CSI asks users not to assign numbers in a reserved division.
25Integrated AutomationFacility ServicesBuilding automation networks, instrumentation and terminal devices, facility controls and control sequences.
26ElectricalFacility ServicesMedium and low voltage distribution, facility power generation, electrical protection, lighting.
27CommunicationsFacility ServicesStructured cabling, data and voice communications, audio-video, distributed communications and monitoring.
28Electronic Safety and SecurityFacility ServicesAccess control, video surveillance, security detection and alarm, life safety including fire detection and alarm.
29Reserved for Future ExpansionFacility ServicesNothing is specified here; CSI asks users not to assign numbers in a reserved division.
30Reserved for Future ExpansionSite and InfrastructureNothing is specified here; CSI asks users not to assign numbers in a reserved division.
31EarthworkSite and InfrastructureSite clearing, earth moving (grading, excavation and fill), soil treatment and stabilization, shoring and underpinning.
32Exterior ImprovementsSite and InfrastructurePaving and its bases, curbs and sidewalks, fences, retaining walls and site furnishings, wetlands, irrigation, planting.
33UtilitiesSite and InfrastructureWater, sanitary sewerage, stormwater, fuel, hydronic and steam, electrical and communications utilities on the site and beyond.
34TransportationSite and InfrastructureRailways and guideways, traction power, signaling and control, fare collection, roadway, railway, airfield and bridge construction.
35Waterway and Marine ConstructionSite and InfrastructureWaterway and marine signaling, hydraulic gates, dredging, coastal and shoreline protection, waterway structures, marine construction.
36Reserved for Future ExpansionSite and InfrastructureNothing is specified here; CSI asks users not to assign numbers in a reserved division.
37Reserved for Future ExpansionSite and InfrastructureNothing is specified here; CSI asks users not to assign numbers in a reserved division.
38Reserved for Future ExpansionSite and InfrastructureNothing is specified here; CSI asks users not to assign numbers in a reserved division.
39Reserved for Future ExpansionSite and InfrastructureNothing is specified here; CSI asks users not to assign numbers in a reserved division.
40Process InterconnectionsProcess EquipmentProcess piping and ductwork for gases, liquids and solids, and the primary control devices of process systems.
41Material Processing and Handling EquipmentProcess EquipmentBulk material processing and conveying, piece handling, cranes and hoists, manufacturing lines, packaging.
42Process Heating, Cooling, and Drying EquipmentProcess EquipmentProcess boilers and heaters, industrial furnaces and ovens, process cooling towers and chillers, dryers.
43Process Gas and Liquid Handling, Purification, and Storage EquipmentProcess EquipmentFans, blowers and compressors for process gas, process pumps and filters, purification, gas and liquid storage.
44Pollution and Waste Control EquipmentProcess EquipmentAir pollution, noise, odor and water pollution control, solid waste handling.
45Industry-Specific Manufacturing EquipmentProcess EquipmentEquipment for oil and gas extraction, mining, food and beverage, textiles, paper, chemicals, plastics and other industries.
46Water and Wastewater EquipmentProcess EquipmentPreliminary treatment, chemical feed, clarification, secondary and further treatment equipment.
47Reserved for Future ExpansionProcess EquipmentNothing is specified here; CSI asks users not to assign numbers in a reserved division.
48Electrical Power GenerationProcess EquipmentPower generation equipment by source (fossil, nuclear, hydro, solar, wind, geothermal, fuel cell) and power control equipment.
49Reserved for Future ExpansionProcess EquipmentNothing is specified here; CSI asks users not to assign numbers in a reserved division.
CSI MasterFormat divisions 00 to 49 with their subgroup and a one-line scope (titles as published by CSI; scope paraphrased from the level 2 subjects of the 2018 Master List)

Source: CSI and CSC, MasterFormat 2018, Groups, Subgroups and Divisions and Master List; Applications Guide for the group structure. CSI's 2026 summary describes changes to listings inside divisions; check scope lines for Divisions 32 and 34 against the edition your project uses.

The subgroups follow a simple logic that is worth knowing by heart. Facility Construction (02 to 14) is the fabric of the building, from what is demolished to what is finished and furnished. Facility Services (21 to 28) is what used to be mechanical and electrical: fire suppression, plumbing, HVAC, automation, power, communications, security. Site and Infrastructure (31 to 35) is everything outside the building line and civil work in general. Process Equipment (40 to 48) serves industrial plants, water treatment and power generation, and rarely appears on a commercial building.

The other distinction people trip on is between Division 00 and Division 01. Division 00 holds the documents of the deal: the invitation, the bid form, the agreement, the bonds, the general and supplementary conditions. Division 01 holds the procedural rules every section of the specification relies on: how to submit, how to request payment, how substitutions, allowances, unit prices and alternates work, what temporary facilities are required, how the project closes out. Part 1 of each technical section extends Division 01 for its own subject rather than repeating it.

In a project manual's table of contents, CSI recommends listing every group and subgroup, and, inside any subgroup that is used, every division from its first to its last, with the unused ones, reserved divisions included, marked "Not Used". Sections are listed only if they are used. That is why a table of contents shows Division 24 even though nothing will ever be specified there.

The divisions a commercial building estimate uses

A commercial building, an office, a school, a medical building or a retail shell, draws on the divisions in the table below and rarely on the others. Process equipment (40 to 48), transportation (34) and marine work (35) belong to industrial and civil projects. CSI's guide notes that cost databases organized on MasterFormat put bonds, insurance, permits and fees under Division 00, temporary facilities, mobilization and site administration under Division 01, and the cost of work results under the other divisions. The table lists what usually lands in each division on a building estimate, and the point where estimates most often go wrong.

Divisions most used on a commercial building estimate, with the common trap in each
DivisionWhat usually lands thereWatch for
00Bonds, insurance, permits and fees, which CSI's guide places here for cost purposesMany estimates carry bonds and insurance as rates on the summary rather than as lines. Decide once, so they are not counted twice.
01Temporary facilities and controls, mobilization, site administration, cleaning, the allowances the owner asked forGeneral conditions are often kept outside the division list in a company's cost codes. Map them, or the division totals will not match the bid.
02Selective demolition, surveys, hazardous material abatement on renovation workCheck whether abatement is in your contract, in a separate contract or carried as an allowance: Divisions 00 and 01 say which.
03Footings, foundation walls, slabs, reinforcingReinforcing (03 20 00 range) can be bought or subcontracted separately from placing concrete. Make sure it is in one package, not none or two.
04CMU and brick walls, masonry veneerMasonry mortar and grout are specified in Division 04, under its common work results (04 05 00 range), not with concrete in 03.
05Structural steel, joists, deck, stairs, railings and miscellaneous metalsMiscellaneous metals can be a different package from structural steel. List both.
06Blocking, rough carpentry, millwork and caseworkArchitectural casework can sit in 06 or 12 depending on how it is specified.
07Roofing, insulation, waterproofing, air barriers, flashing, sealants, firestoppingFirestopping (07 84 00 range) is specified here but MEP trades often seal their own penetrations. Say who carries it.
08Doors, frames and hardware, storefront, windows, glazingHardware is commonly supplied by one party and installed by another.
09Framing and gypsum board, ceilings, flooring, tile, paintThe largest division on many interior jobs. Check whether non-structural framing is priced with drywall or with metals in your company.
10Toilet partitions and accessories, signage, fire extinguishers and cabinets, lockersOwner-furnished items show up here; carry installation only when the spec says so.
11, 12Kitchen and loading dock equipment, window treatments, furnitureOften owner-furnished or bought under a separate contract.
14ElevatorsGypsum shaft walls around the hoistway are specified in 09 (09 21 16.23 in CSI's list), not in 14.
21Sprinklers and standpipesCheck whether the section asks the installer to design the system or the drawings already show it.
22Plumbing piping, fixtures, water heatersWhere building plumbing stops and site utilities in 33 start is set by the specification, not by MasterFormat.
23Equipment, ductwork, piping, HVAC controlsControls may be specified in 23 09 00 (HVAC instrumentation and control) or in Division 25. Read which.
26, 27, 28Power, lighting, data cabling, fire alarm, access control, camerasFire alarm sits in 28, not in 26; low voltage packages are often split from electrical.
31, 32, 33Grading and excavation, paving and curbs, landscaping, water, sewer and storm utilitiesSitework can be a single package or several; keep the division split even if one contractor prices it.
Divisions most used on a commercial building estimate, with the common trap in each

Most contractors do not estimate in raw MasterFormat numbers. They keep a cost code list built on it, usually the division plus a level 2 or level 3 subject, with their own additions for general conditions, self-performed work and fees. That is fine, and CSI explicitly allows user-defined numbers inside a division as long as they do not reuse an assigned number for a different subject. The test of a good code list is whether every code can be traced back to one MasterFormat location, so that a line in the estimate can be checked against the section that governs it.

The free construction estimate template groups its lines by these divisions, with labels such as "03 Concrete" in its drop-down, and keeps a column for the drawing sheet and specification section each quantity comes from.

The old 16 divisions and where they went

Many people still say "Division 15" for mechanical and "Division 16" for electrical. That vocabulary comes from the 16-division format, last published in the 1995 edition. CSI's Applications Guide explains why it was replaced: with one digit per level after the division, each division had room for only nine level 2 subjects, so topics went where there was space rather than where they belonged. Fire suppression, detection and alarm, lightning protection, and solar and wind equipment were all filed in Division 13 for that reason. The 2004 edition added a sixth digit, arranged the digits in pairs and moved building services into their own subgroup.

1995 MasterFormat to 2004 and later: the moves estimators still trip on
1995 format2004 and laterSource
Division 15, MechanicalDivision 21 Fire Suppression, Division 22 Plumbing, Division 23 HVACCSI's own account of the 2004 edition
Division 16, ElectricalDivision 25 Integrated Automation, Division 26 Electrical, Division 27 Communications, Division 28 Electronic Safety and SecurityCSI's own account of the 2004 edition
Fire suppression, detection and alarm, lightning protection, solar and wind equipment filed in Division 13Moved out of Division 13 to divisions that fit, now that numbering had room: fire suppression to 21, fire detection and alarm to 28CSI's Applications Guide on why the numbering was expanded
Division 2, Site ConstructionSpread over Division 02 Existing Conditions (site remediation, for example) and the new Site and Infrastructure subgroup, Divisions 31 to 35, which also covers heavy civil, transportation, utility and marine work1995 and 2018 division lists; CSI's account of the 2004 edition
Division 6, Wood and Plastics; Division 8, Doors and Windows; Division 14, Conveying SystemsDivision 06 Wood, Plastics, and Composites; Division 08 Openings; Division 14 Conveying Equipment1995 and 2018 division lists
Five-digit numbers, e.g. 09650 resilient flooring, 14240 hydraulic elevators, 16540 classified location lightingSix digits in pairs where the subject fitted: 09 65 00, 14 24 00, and 26 54 00 for the lighting, now in Division 26CSI's Applications Guide, assigned numbers
1995 MasterFormat to 2004 and later: the moves estimators still trip on

Source: Greg Ceton (CSI), Insulation Outlook, 2005; Consulting-Specifying Engineer, 2005; 1995 division list; CSI Applications Guide.

Two consequences for an estimator. First, an old cost database or a historical bid coded in five digits needs a crosswalk before it can be compared with a current estimate: 15xxx lines split three ways, 16xxx lines four ways. Second, a scope letter that says "Division 16 work" on a current project is ambiguous. Does it include data cabling (27) and fire alarm (28)? Name the divisions or the sections.

MasterFormat, UniFormat and OmniClass

The three are often confused because CSI publishes all of them, but they answer different questions. MasterFormat asks what is being built, trade by trade. UniFormat asks what the building is made of, function by function: its foundations, its exterior walls, its heating, whatever they turn out to be made of. OmniClass is a wider set of tables for classifying construction information in databases and models.

There are two UniFormats. UNIFORMAT II is ASTM E1557, a standard classification of building elements and related sitework, first approved in 1993 and current as E1557-09, reapproved in 2020. It has three levels, major group elements, group elements and individual elements, plus a suggested fourth level in an appendix, and it states that it does not apply to major civil works and is unsuitable for process work or trade estimates. CSI UniFormat, published by CSI and CSC, uses the same lettered backbone with an Introduction category in front and a Z General category at the end. Its 2010 edition is still the stable edition in 2026: CSI's 2026 release added UniFormat material to its online platform but did not replace the 2010 edition.

MasterFormat, CSI UniFormat, UNIFORMAT II and OmniClass compared
MasterFormatCSI UniFormatUNIFORMAT II (ASTM E1557)OmniClass
What it classifiesWork results: what a trade produces by applying skill to productsPhysical elements by the function they perform, whatever the work results usedBuilding elements and related sitework, by functionConstruction information in general, in many tables, for databases and software
Top level50 divisions, 00 to 49Introduction, then A Substructure, B Shell, C Interiors, D Services, E Equipment and Furnishings, F Special Construction and Demolition, G Building Sitework, Z GeneralSeven major group elements, A Substructure to G Building SiteworkTables, e.g. Table 21 Elements, Table 22 Work Results, Table 23 Products
Numbering example09 21 16, then .23 for a level 4A, A10, A1010, A1010.10, then a user level 5Level 1 letter, level 2 three characters, level 3 five characters; a suggested level 4 in an appendixTable 22 follows MasterFormat; Table 21 follows UniFormat
Built forProject manuals, detailed cost estimates, drawing notes, product dataPreliminary project descriptions, early cost estimates, performance requirements, BIM and facility dataEconomic evaluation and elemental cost plans early in design, value engineering, early schedulesOrganizing electronic data and BIM libraries
Current versionMasterFormat 2026UniFormat 2010, still the stable edition in 2026E1557-09, reapproved 2020Not covered here
Published byCSI and CSCCSI and CSCASTM International, Subcommittee E06.81CSI
MasterFormat, CSI UniFormat, UNIFORMAT II and OmniClass compared

Source: CSI and CSC, UniFormat 2010; The Construction Standard, OIR 26.1; ASTM E1557-09 (2020); RSMeans on UNIFORMAT II; CSI Applications Guide on OmniClass Tables 21, 22 and 23.

An exterior wall shows the difference. In UniFormat it is one element, B20 Exterior Vertical Enclosures, priced early as a cost per unit of wall area. In MasterFormat the same wall is spread over several divisions once it is designed: masonry or panels in 04 or 07, framing in 05 or 06, insulation and air barrier in 07, windows in 08, interior gypsum board and paint in 09. Neither view is wrong. The first tells an owner what the wall costs; the second tells a contractor who builds which part of it.

The two systems meet in the middle of a project. CSI's UniFormat guide shows MasterFormat numbers appended under a UniFormat element once a material is chosen, for example a subgrade wall element carrying 03 30 00 if it will be cast-in-place concrete or 04 20 00 if it will be unit masonry. And MasterFormat keeps a place for element-based performance requirements at 01 80 00, organized after UniFormat.

For UK work, neither applies: quantities are measured into a bill under RICS's NRM 2, the rules for detailed measurement of building works. See the NRM2 bill of quantities guide for that structure.

Estimate by division or by element

CSI's guidance is direct: UniFormat is most commonly used early, before work results have been selected, for preliminary project descriptions and preliminary cost estimates; MasterFormat organizes outline and full specifications, detailed cost data and drawing notations; and the right moment to switch is when work results are being chosen. ASTM E1557 says the same from the other side, positioning UNIFORMAT II for budgets and elemental cost plans before design begins, value engineering and early schedules.

Which structure to estimate in, by project stage
StageOrganize the estimate byWhy
Concept and schematic designUniFormat elementsMaterials are not chosen yet; an exterior wall has a cost per area before anyone knows if it is brick or panels.
Design developmentUniFormat, with MasterFormat numbers added where materials are decidedCSI's UniFormat guide describes appending MasterFormat numbers element by element as choices are made.
Value engineeringUniFormat, with MasterFormat as a suffixCSI notes that MasterFormat is not well suited to value analysis, which attaches cost to functions.
Construction documents and bidMasterFormat divisions and sectionsLines tie to specification sections, subcontract bids and the submittal register.
Buyout, schedule of values, cost controlMasterFormat or company cost codes built on itThe estimate becomes the budget; the same numbers carry through billing.
Which structure to estimate in, by project stage

The practical rule for a contractor: if the estimate will be checked against an owner's budget built on elements, keep an element view alongside the division view until the design settles. If the estimate will become a bid and then a budget, the division view wins, because subcontract bids, the submittal register and the schedule of values all speak in sections. The AI takeoff and estimating page covers how quantities feed that division view.

One number across specs, submittals, packages and the estimate

The real value of MasterFormat on a project is that one number can follow a piece of work through every document. The specification section is the anchor; everything else should point to it.

How the same section number links the project documents
DocumentOrganized asWhat the section number does there
SpecificationOne section per work result, numbered and titled from MasterFormatEach section has three parts: general, products, execution. Submittal requirements sit in Part 1.
Division 01Project-wide proceduresSubmittal procedures, schedule of values, allowances, unit prices and alternates each have their own Division 01 location.
DrawingsKeynotesReference keynoting systems use MasterFormat numbers so a note on a sheet points to its section.
Submittal registerOne line per required submittal, keyed by sectionBuilt by reading Part 1 of every section.
Bid packagesGroups of sections priced togetherMasterFormat does not say which trade does which work: the package is the contractor's decision.
EstimateLines coded to division and sectionLets each line be checked against its section and each package total against a bid.
Schedule of valuesLines often by section or by trade and areaIf the estimate and the schedule of values share codes, billing reconciles to the budget.
How the same section number links the project documents

Source: CSI Applications Guide on drawing notations, cost data and trade jurisdictions; State of Missouri, Format for Construction Specifications on the three-part section.

The weak link is almost always the bid package. CSI is explicit that MasterFormat's structure does not imply how work is assigned to disciplines, trades or subcontractors, and that a trade is likely to work across several divisions. A drywall package can include sections from 05, 07 and 09; an electrical package may or may not include 27 and 28. Write each package as a list of section numbers, then check that every section in the project manual appears in exactly one package, or is deliberately excluded.

The same discipline applies downstream. The submittal log template keys every submittal to its specification section, and the schedule of values template works best when its lines carry the same codes as the estimate, so that billing reconciles to the budget line by line.

Worked example: a scope mapped to sections

Illustrative example, invented figures: a single-storey retail building, shell and one tenant fit-out

Assumptions, all invented for this example. A general contractor receives a narrative scope and a 40-sheet drawing set for a one-storey retail building with one tenant fit-out. The project manual follows a recent MasterFormat edition. The estimator maps each scope item to a division and section before measuring anything. The numbers shown are from CSI's 2018 Master List, the edition we could check line by line; on a real job, take them from the project manual.

Scope items mapped to MasterFormat divisions and sections (invented project)
Scope itemDivisionSection or familyStatus
Spread footings and slab on grade0303 30 00 range, cast-in-place concrete; 03 20 00 range for the reinforcingMapped
Load-bearing CMU walls at the rear0404 20 00 range, unit masonry, with its grout and reinforcingMapped
Steel joists and roof deck0505 20 00 range for joists, 05 30 00 range for deckingMapped
Single-ply roof on tapered insulation0707 50 00 family, membrane roofing; the spec will carry the level 3 number below itMapped
Storefront at the tenant entrance0808 40 00 family, entrances and storefrontsDecision
Hollow metal doors with hardware0808 10 00 family for doors and frames, 08 71 00 for door hardwareMapped
Gypsum board partitions, acoustical ceiling0909 21 16, gypsum board assemblies; 09 50 00 family for ceilingsMapped
Restroom fixtures and toilet accessories22, 1022 40 00 range for fixtures; accessories in the 10 20 00 family, interior specialtiesMapped
Rooftop units, ductwork, thermostats23 (or 25)23 70 00 family for the units, 23 30 00 family for air distribution, controls in 23 09 00 or Division 25Decision
Wet sprinkler system2121 10 00 family, water-based fire suppressionMapped
Fire alarm2828 46 00, fire detection and alarmMapped
Panelboards, power and lighting2626 20 00 family for low voltage distribution, 26 50 00 family for lightingMapped
Firestopping at all rated penetrations0707 84 00 range, firestoppingDecision
Grading, parking lot paving and curbs31, 3231 20 00 family, earth moving; 32 10 00 family for bases and pavingMapped
Water service and sewer connection33 (and 22)33 10 00 and 33 30 00 families on the site sideDecision
Construction fence, site trailer, owner signage allowance0101 50 00 family for temporary facilities; 01 21 00 for the allowanceMapped
Performance and payment bonds00Division 00, where the bond forms live; priced as a rate on the summaryMapped
Scope items mapped to MasterFormat divisions and sections (invented project)

The four decisions. The storefront is specified in the shell project manual, but the tenant's lease makes it a fit-out cost: the section is the same, the estimate line is split by contract. The rooftop unit controls appear at 23 09 00 in the specification and nowhere in Division 25, so they stay with the HVAC package. Firestopping is specified in 07 84 00, but the mechanical and electrical subcontractors will seal their own penetrations, so the estimator writes that into their scope letters and carries 07 84 00 only for the drywall contractor's rated walls. And the water and sewer services cross the building line: the estimator reads where Section 22 stops and Division 33 starts in this specification, and finds a five-foot line written into Part 1 of the plumbing section.

The result. Seventeen scope items, fifteen divisions touched, four decisions recorded with the reason for each. None of those four decisions could be read off the numbers alone: they came from the specification text, the lease and the trades' habits.

Common mistakes

  • Using 1995 numbers on a current job. "Division 15" and five-digit codes in a scope letter or a cost database make lines disappear between mechanical, plumbing and fire protection.
  • Coding the estimate to the current edition when the project manual uses an older one. Section numbers moved between editions; the project manual is what the subcontractors price.
  • Treating a division as a bid package. MasterFormat does not assign trades. Packages built division by division leave orphan sections, typically firestopping, joint sealants, access doors and miscellaneous metals.
  • Putting fire alarm in electrical without saying so. Fire detection and alarm is in Division 28. If the electrical subcontractor carries it, the scope letter has to name it.
  • Leaving general conditions out of the division structure. Then the division totals do not add up to the bid, and nobody can reconcile the two after award.
  • Inventing numbers inside a reserved division. CSI asks users not to assign anything in Divisions 15 to 20, 24, 29, 30, 36 to 39, 47 or 49. Company codes placed there will collide with a future edition.
  • Pricing early design by division. Before materials are chosen, a division estimate forces guesses about products. An element estimate prices the function and survives design changes.
  • Dropping lines without a division. An item that does not fit cleanly still needs a home. Give it the closest section and a note, rather than leaving it uncoded.

What software can prepare, and what an estimator decides

Most of the effort around MasterFormat on a bid is reading and sorting: which sections the project manual contains, which drawing notes belong to which section, which submittals each section asks for, which estimate lines have no section and which sections have no estimate line. That work can be prepared by software. The decisions that carry money and risk cannot.

Split of work between software preparation and the estimator's decision
TaskWho does itWhat stays with the estimator
Read a specification and list its sections with their numbers and titles as the project wrote themCan be prepared by softwareConfirm which MasterFormat edition and which company additions the project follows
Sort drawing notes, schedules and specification paragraphs under the division and section they belong toCan be prepared by software, with the source page attachedSettle items that could sit in two places, such as controls or casework
List every submittal each section asks for into a registerCan be prepared by softwareSet review periods and dates required on site
Code takeoff quantities to the division and section of the estimateCan be prepared by software, each quantity traced to its sheetMeasure what the drawings leave to judgment, and price it
Flag lines with no division, or sections with no estimate lineCan be prepared by softwareDecide whether the gap is an omission, an exclusion or work in another package
Group sections into proposed bid packages from past projectsCan be suggested by softwareDraw the package boundaries and write the scope letters
Convert an element estimate into division totalsCan be prepared once materials are chosenChoose the materials, which is a design decision
Split of work between software preparation and the estimator's decision

This is the line Mirage works to on construction documents. Its agents read specifications and submittals and organize them into MasterFormat divisions and sections, each item traced to the clause it came from; cross-check specifications against the drawings on specification review; and keep the submittal register current on RFI and submittal tracking. Mirage has not published a deployment centred on MasterFormat classification. Its published construction results are on takeoff: at OCBM, 100% of quantities are tied to a source drawing, and at John Cockerill, piping takeoff takes 80 to 90% less time. If you are reorganizing a whole estimating process, the guide to automating an estimating department starts with the cost codes you already use.

Checklist

Run it at the start of every bid, before the first quantity is measured.

  • MasterFormat edition of the project manual identified, and company additions to it written down
  • Project manual table of contents read division by division, reserved and unused divisions confirmed empty
  • Every section in the project manual assigned to exactly one bid package, or listed as excluded
  • Scope letters written as lists of section numbers, with the boundary items (firestopping, controls, fire alarm, utilities) named
  • Division 00 and Division 01 items priced once, either as lines or as summary rates, not both
  • Estimate lines coded to division and section, each with the sheet or section its quantity comes from
  • Lines without a division resolved before the bid goes out
  • Old cost data in five-digit codes crosswalked before comparison
  • Element view kept alongside the division view if the owner's budget is elemental
  • Submittal register and schedule of values set up on the same section numbers as the estimate

Questions readers ask

Sources and scope

Checked on . Scope: MasterFormat as published by CSI and CSC, with the division structure and numbering rules from CSI's 2018 edition documents and the current edition facts from CSI's 2026 pages; CSI UniFormat 2010; ASTM E1557-09 (2020). These standards are copyright; this page paraphrases them and reproduces only division titles and example numbers. Buy access to the full lists from CSI and ASTM.

This guide explains how MasterFormat and UniFormat are used in estimating and project documentation. It is not affiliated with or endorsed by CSI, CSC or ASTM. Always code a project to the edition and numbering its own project manual uses.

Related on this site

Test it on one of your own project manuals

Send us a specification and the drawing set from a bid you have already priced. We will show you the sections, the division-by-division sort and the submittal list our agents produce, each item linked to its page, so you can compare them with what your team built by hand.

Prefer to talk it through? Book a call

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy