NRM2 Bill of Quantities: Structure, Measurement Rules, and How NRM1, NRM2 and NRM3 Differ

NRM2 is the RICS rulebook for measuring building work into a bill of quantities: 41 work sections, general rules for units and rounding, and a fixed composition for the bill, from preliminaries to provisional sums, risks and dayworks. It sits after NRM1, which governs the cost plan, and its codes are meant to trace every bill item back to that plan. This guide explains which volume applies when, how a bill is built and coded, the rules that most often change a quantity, and the provisional sum distinction that moves programme risk between client and contractor.

Published
Sources checked
Reading time
12 min
Written by
Mirage Metrics team

Scope: the current UK editions, NRM 1 3rd edition and NRM 2 and NRM 3 2nd editions, all effective from 1 December 2021. NRM is RICS copyright; this guide paraphrases it and does not reproduce it. Download the volumes from rics.org before relying on a rule. Contract terms, such as how a provisional sum is instructed, come from your contract, not from NRM.

Decision snapshot

Best suited to
Quantity surveyors and cost managers preparing bills of quantities, contractors' estimators pricing them, and anyone moving from SMM7 habits to NRM2.
Inputs needed
The cost plan and its codes, the drawings and specifications at their current revision, the client's procurement route, and the decisions on which risks the client keeps.
What can be automated
Measuring quantities from drawings, applying rounding and unit rules, coding items to the cost plan, checking provisional sums for missing information, comparing revisions.
What requires human approval
The breakdown structure, the meaning of incomplete design, which risks to transfer, whether a sum is defined, any departure from the rules, and signing the bill.
When this approach is insufficient
Work other than building works, which NRM2 does not set out to measure, a design too immature for a firm bill, or a contract that handles change in a way the bill does not anticipate.

Who this guide is for

It is written for the people who produce and price bills in the UK: the client's quantity surveyor or cost manager, the contractor's estimator, and the trade package buyers who receive a section of the bill. It assumes you know what a bill of quantities is for and concentrates on the parts of NRM that change a number or move a risk.

It is not a substitute for the volumes, which RICS publishes free on its NRM page. RICS states that the previous editions are out of date and should not be used on new projects, so check which edition a project's documents cite before you measure anything.

NRM1, NRM2 and NRM3: which volume does what

The New Rules of Measurement are three volumes. All three current editions are dated October 2021, took effect on 1 December 2021, and were reissued by RICS in October 2022 as practice information with no material change to their content. RICS gives the publication of ICMS, the Cost prediction professional standard and the RIBA Plan of Work 2020 as the main reasons for the new editions.

The three NRM volumes, current editions
VolumeTitleEditionUsed for
NRM 1Order of cost estimating and cost planning for capital building works3rd edition, October 2021, effective 1 December 2021Order of cost estimates and elemental cost plans, before and during design
NRM 2Detailed measurement for building works2nd edition, October 2021, effective 1 December 2021Bills of quantities and quantified schedules of works, and a framework for schedules of rates
NRM 3Order of cost estimating and cost planning for building maintenance works2nd edition, October 2021, effective 1 December 2021Cost estimates and cost plans for building maintenance works
The three NRM volumes, current editions

Source: NRM 1, NRM 2 and NRM 3, title pages and section 1.5; RICS NRM page.

ICMS, the International Cost Management Standard (3rd edition, November 2021, published by the ICMS Coalition), is a classification for reporting construction and life cycle costs. It has no detailed measurement rules. NRM maps to it: NRM2 notes that ICMS can be mapped at its Level 4, the cost sub-group, to the NRM1 elemental breakdown.

Status: what is mandatory and what is not

The current volumes are RICS practice information, which RICS defines as information that is not mandatory and sets no requirements for members. The first edition of NRM2, in 2012, had the status of a guidance note: recommended practice that members were not required to follow (NRM 2 first edition).

One link is mandatory. NRM1 incorporates the principles of the Cost prediction professional standard, and RICS members and regulated firms must follow those principles when they produce cost prediction reports. Among them is recommending ICMS where that is in the client's interest. In practice, NRM becomes binding on a project when the documents say so: NRM2 asks that a bill prepared under it states that it is, and the preliminaries must confirm the method of measurement and any departure from it.

NRM2 replaced the Standard Method of Measurement, first published in 1922, whose last edition, SMM7, dates from 1988. NRM2's first edition became operative on 1 January 2013; Designing Buildings gives 1 July 2013 as the date it replaced SMM7. The visible change for anyone used to SMM7 is the numbering: lettered work sections A to Y became numbered sections 1 to 41 (Jones Melling).

From the NRM1 cost plan to the NRM2 bill

NRM1 runs alongside the RIBA Plan of Work. Each stage has its own estimate or cost plan, and formal cost plans 2 and 3 are progressions of the previous plan, not new plans. NRM1 adds that whether each is prepared depends on the procurement route: an updated plan might not be needed at Stage 4 under design and build. The bill comes in at contractor engagement, as the pricing document.

RIBA stages and the RICS estimate or cost plan at each one (after NRM 1, Table 1.1)
RIBA stageRICS estimate or cost planVolume
0Rough order of cost estimateNRM 1
1Order of cost estimate (option costs)NRM 1
2Elemental cost estimate and formal cost plan 1NRM 1
3Formal cost plan 2NRM 1
4Formal cost plan 3NRM 1
Contractor engagementPre-tender estimate, pricing documents (the bill), post-tender estimateNRM 1 and NRM 2
RIBA stages and the RICS estimate or cost plan at each one (after NRM 1, Table 1.1)

The cost plan is organised by group elements, numbered 0 to 14. VAT is not one of them: NRM1 treats it as a separate assessment and recommends excluding it from estimates and cost plans. Risk allowances and inflation are also kept out of the base cost: NRM1 asks for a base cost estimate with no allowance for either, then risk allowances (design development, construction, employer change and other employer risks), then tender inflation to the tender return date and construction inflation to the mid-point of construction.

NRM 1 group elements, current edition
Group elementName
0Facilitating works
1Substructure
2Superstructure
3Internal finishes
4Fittings, furnishings and equipment
5Services
6Prefabricated buildings and building units
7Work to existing buildings
8External works
9Main contractor's preliminaries
10Main contractor's overheads and profit
11Project and design team fees
12Other project costs
13Risks
14Inflation
NRM 1 group elements, current edition

Source: NRM 1, Table 1.1, Table 2.1, sections 2.15 to 2.17, 3.4 and Part 4.

Risk is an assessment, not a percentage

NRM1 recommends that risk allowances are not a standard percentage but a considered assessment of the risks identified. A flat 10% carried from one cost plan to the next is exactly what it advises against.

What an NRM2 bill contains

NRM2 covers bills of quantities and quantified schedules of works. A bill is either firm, to obtain a lump sum for a fully designed project, or approximate, to be remeasured as built. Either way it has the same parts.

Composition of a bill of quantities under NRM 2 (section 2.5)
PartWhat it holds
Form of tender and summaryThe offer and the carried totals of every part of the bill
PreliminariesSection 1: the information and requirements (Part A) and a pricing schedule (Part B) split into the employer's requirements and the main contractor's cost items. The QS cannot quantify the contractor's preliminaries; the bill asks for the breakdown
Measured worksWork sections 2 to 41, measured under the rules
Non-measurable worksWork that cannot be measured under the rules
Provisional sumsDefined or undefined, each excluding overheads and profit (see below)
Contractor-designed worksWork the contractor is to design
RisksA schedule of construction risks the client transfers, each priced as a lump sum
CreditsMaterials arising from strip-out or demolition, normally on refurbishment or demolition work
Dayworks (provisional)Labour hours and lump sums for materials and plant, against which the contractor tenders rates and percentages
AnnexesSupporting information annexed to the bill
Composition of a bill of quantities under NRM 2 (section 2.5)

Three further rules apply to the bill as a whole. Overheads and profit are added as a percentage on the preliminaries, the measured work (contractor-designed work included), the risk allowances and work from provisional sums. Where the contract has no fluctuations clause, the bill provides a fixed price adjustment. And VAT is excluded from the bill (NRM 2, 2.5.7 and 2.6).

Provisional sums, risks and dayworks

A provisional sum is money in the bill for work that cannot yet be measured. NRM2 divides it in two, and the label decides who carries the programme and preliminaries consequences of that work.

Defined and undefined provisional sums under NRM 2 (section 2.5.5)
TypeInformation requiredProgramme and preliminariesEffect
DefinedThe nature and construction of the work; how and where it is fixed and what is fixed to it; quantities showing its scope and extent; any specific limitationsThe contractor is taken to have allowed for it in programming, planning and pricing the preliminariesRisk with the contractor
UndefinedAny sum without that information, including one labelled defined that lacks any of the four itemsThe contractor is taken to have made no such allowance; the time and preliminaries effect of the work comes back when it is instructedRisk with the client
Defined and undefined provisional sums under NRM 2 (section 2.5.5)

Provisional sums exclude overheads and profit, which the bill provides for separately. A law firm's training material on the subject (Fenwick Elliott) adds two practical points: under the JCT Standard Building Contract, extension of time and loss and expense run for undefined sums, not defined ones; and NEC contracts do not refer to NRM2 or to provisional sums at all, since they manage change through compensation events. If your contract is an NEC, read the NEC4 compensation events guide before you rely on provisional sum mechanics.

Risks. Residual risks the client chooses to transfer go in a schedule of construction risks, each priced by the contractor as a lump sum for taking and managing it, excluding overheads and profit. Risks to be shared are handled with provisional quantities. Risks the client keeps stay in the client's cost plan and do not appear in the bill.

Dayworks. A provisional schedule of labour hours and lump sums for materials and plant, against which the contractor tenders rates and percentages. It may be included in the contract sum, in which case it is treated as a provisional sum, or left out.

Elemental, work section or works package, and the codes

NRM2 allows three breakdown structures for a bill. The rules of measurement are the same in each; what changes is the order of the items.

The three breakdown structures allowed by NRM 2 (section 2.8)
StructureOrganised bySuits
ElementalBy the NRM 1 group elements, whatever the order of the work sectionsTender analysis against the cost plan, cost data for future projects
Work sectionBy the 41 NRM 2 work sectionsPricing: like items grouped together, as contractors and their supply chains price them
Works packageBy packages the client or contractor defines; NRM 2 deliberately does not standardise themProcurement by trade package, management contracting, construction management
The three breakdown structures allowed by NRM 2 (section 2.8)

NRM2 notes the tension: contractors often prefer work section bills for pricing, while elemental bills make tender analysis and cost data easier. Its answer is coding. The codes used for the cost plan are the basis for the bill's codes: a project reference, then the bill number, group element, element and sub-element (predefined by NRM1), then a user-defined component and subcomponent. NRM2's own example is DPB27-3.1.1.2.1.1. A work section or works package bill keeps that code and adds a suffix, such as /04 for work section 4, so the same item can be sorted either way and every item still traces back to the cost plan.

Source: NRM 2, sections 2.8.1 to 2.8.4, Tables 2.3 and 2.4, Appendix A1.

The general measurement rules

Section 1 of NRM2 is the preliminaries; sections 2 to 41 hold the rules of measurement, from excavating and filling and in situ concrete to builder's work in connection with mechanical, electrical and transportation installations. Each work section has its own tables, but a set of general rules applies everywhere, and they are where most small quantity errors come from.

General rules of measurement and description (NRM 2, section 3.2 and Appendix A, paraphrased)
RuleWhat it meansNRM 2 ref.
Measure net as fixed in positionThe quantity is what is built, unless a work section says otherwise; laps, joints and waste are in the rate, not the quantity3.2.1
Curved work on the centre lineLengths of curved work are taken along their centre line3.2.1
Dimensions to the nearest 10 mm5 mm and over rounds up, under 5 mm rounds down3.2.1
Quantities to the nearest whole unitA quantity under one unit is given as one3.2.1
Tonnes to two decimal placesSteel reinforcement and structural steel are billed in tonnes3.2.1, A9
Deemed includedUnless stated otherwise each item includes labour, materials, fixing, plant, waste, cutting, establishment charges and compliance; each work section lists more3.2.2, 3.1.2
DescriptionsType and quality, critical dimensions, method of fixing where it is not left to the contractor, and the background3.2.2
Work the tables do not coverMeasured by analogy, and any rule derived that way is stated in full in the preliminaries or the bill3.2.4
Unspecified productsThe description carries a PC (prime cost) price, excluding overheads and profit3.2.6
Provisional quantitiesRemeasured; a variance under 20% leaves the tendered rate fixed, 20% or more opens it to review3.2.7
General rules of measurement and description (NRM 2, section 3.2 and Appendix A, paraphrased)

Apart from enumerated and itemised items, the unit is metric (metres, square metres, cubic metres), and every item carries its unit. NRM2 also reminds the reader that the bill is a legal document: its descriptions are what the contractor priced.

Worked example: checking a draft bill

Illustrative example, invented figures: a draft bill for an office refurbishment

Assumptions, all invented for this example. A firm bill of quantities for the refurbishment of two office floors, elemental breakdown, measured under NRM2 2nd edition, with no departures stated in the preliminaries. A second reader checks the draft against the general rules before it is issued.

Second-reader check of a draft bill (invented)
ItemDraftRuleIssued billStatus
Ceiling height dimension3,247 mmNearest 10 mm, 5 mm and over rounds up3,250 mmCorrected
Floor finish, meeting room46.7 m²Nearest whole unit47 m²Corrected
Screed patch repair0.4 m²Under one unit is given as one1 m²Corrected
Steel reinforcement, new lift pit2.346 tTonnes to two decimal places2.35 tCorrected
Entrance canopy, provisional sum labelled definedNature and fixing described, no quantitiesA defined sum needs all four pieces of informationQuantities added from the design team's sketch, or relabelled undefinedDecision needed
Recovered radiators from strip-outPriced inside demolitionArisings belong in the credits sectionMoved to creditsCorrected
SummaryTotals carried with VATVAT is excluded from billsVAT removed and stated as excludedCorrected
Second-reader check of a draft bill (invented)

The line that matters. The six rounding and placement corrections are mechanical. The canopy is not. Left as it was, a sum labelled defined but without quantities is construed as undefined, so the contractor is taken to have made no allowance for it in the programme or the preliminaries, and the client carries that effect when the canopy is instructed. The QS either gets the quantities from the design team before issue, or labels the sum undefined and keeps the time and cost exposure in the client's risk assessment. Both are legitimate; leaving it ambiguous is not.

Mistakes that move cost or risk

  • Measuring to a superseded edition. RICS says the earlier editions should not be used on new projects. A bill that cites NRM2 without an edition invites argument.
  • A defined sum missing one of its four items. It is construed as undefined, whatever the bill calls it, and the programme risk moves back to the client.
  • Overheads and profit inside provisional sums. NRM2 keeps them out; the percentage is added once, separately.
  • Unstated departures. A rule derived by analogy, or any deviation from NRM2, must be stated in full in the preliminaries or the bill. An unstated one is a dispute waiting.
  • VAT in the bill or the cost plan. Both NRM1 and NRM2 exclude it; report it separately.
  • A flat risk percentage. NRM1 asks for an assessment of identified risks, and NRM2 for a schedule of the risks the client transfers.
  • Bill items that cannot be traced to the cost plan. Without the codes, tender analysis against the cost plan becomes a manual reconciliation.
  • Assuming JCT provisional sum mechanics under an NEC contract. NEC does not use them; change runs through compensation events.

What software can prepare, and what stays with the QS

Most of the hours in a bill go into measuring, rounding, coding and checking: work that follows rules and can be prepared by software that reads the drawings and keeps each quantity linked to its source. The decisions that set the price and allocate risk cannot.

Split of work between software preparation and the quantity surveyor's decision
TaskWho does itWhat stays with the QS
Measure lengths, areas, volumes and counts from the drawings, sheet by sheetCan be prepared by software, checked by the QSDecide what the drawings mean where they are incomplete or contradict each other
Apply the rounding and unit rules to every quantityCan be prepared by softwareDecide where a work section's own rule overrides the general one
Code every item to the cost plan and add the work section suffixCan be prepared by softwareChoose the breakdown structure and the bill numbering for the project
Flag a provisional sum labelled defined that lacks quantities or fixing informationCan be prepared by softwareDecide whether to complete the information or accept an undefined sum
Compare a new drawing revision with the measured one and list changed quantitiesCan be prepared by softwareDecide whether a change is design development or a client change
Link every quantity to the sheet and revision it came fromCan be prepared by softwareSign the bill: it is a legal document
Split of work between software preparation and the quantity surveyor's decision

This is the boundary Mirage works to. Its agents measure from drawings and link every quantity to the sheet it came from: at OCBM, 100% of extracted quantities are traceable to a source drawing (OCBM case study). Mirage has not published a UK NRM deployment; the NRM quantity surveying page describes what a first one would involve, and the honest test is a bill your team has already priced, where you know the right answer.

Checklist before the bill goes out

  • Edition of NRM2 stated in the bill, and the preliminaries confirm the method of measurement
  • Every departure from the rules, including rules derived by analogy, stated in full
  • Breakdown structure chosen and every item coded back to the cost plan
  • Dimensions to the nearest 10 mm, quantities to whole units, tonnes to two decimals
  • Every defined provisional sum checked for all four pieces of information
  • Provisional sums and the risk schedule priced excluding overheads and profit
  • Risks sorted into transferred (schedule), shared (provisional quantities) and retained (cost plan)
  • Credits for arisings in their own section
  • Dayworks included as a provisional sum or deliberately left out
  • VAT excluded and stated as excluded
  • Every quantity traceable to the drawing and revision it was measured from

Questions readers ask

Sources and scope

Checked on . Scope: the current UK editions of NRM 1, NRM 2 and NRM 3, read in full on rics.org. NRM is RICS copyright and is paraphrased here, not reproduced. Secondary sources are used only where named in the text.

This guide explains measurement practice for educational purposes. It does not replace the RICS volumes, the contract documents of a project or the judgment of a qualified quantity surveyor.

Related on this site

Test it on a bill you have already priced

Send us the drawings behind one bill your team has measured. We will return the quantities our agents produce, each linked to its sheet, so you can compare them line by line with yours.

Prefer to talk it through? Book a call

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy