Comparing Drawing Revisions: Impact on Quantities, Price and Scope
A new revision or an addendum lands days before the bid is due. The question is not what moved on the sheet but what it does to your number: which quantities change, which items appear or disappear, which requirements changed in words only, and what you still have to ask. This guide sets out the comparison step by step and gives an impact matrix you can copy, filled in for a worked example.
- Published
- Sources checked
- Reading time
- 14 min
- Written by
- Mirage Metrics team
Scope: drawing revisions and addenda received while you are still estimating, up to bid submission, on building and civil work in the US and the UK. After award the same comparison feeds a change order or a variation; the last section says what changes then.
Decision snapshot
- Best suited to
- Estimators, chief estimators, preconstruction managers and quantity surveyors who priced one issue of the documents and have just received the next.
- Inputs needed
- The previous set as priced (with its sheet index or drawing register), the new transmittal and every file it lists, the addendum narrative, the specification sections it touches, and the current estimate with its unit prices.
- What can be automated
- Reconciling received files against the transmittal and the sheet index, comparing each reissued sheet with its previous revision, listing every difference with its location, remeasuring the quantities that changed, and filling the old and new quantity columns of the matrix.
- What requires human approval
- Classifying each difference as graphic only, quantity, scope or specification; choosing the estimate items it touches; accepting a unit price for a new item; deciding what to ask, what to assume and what to carry as an allowance; signing off the revised estimate.
- When this approach is insufficient
- When the change is too large to compare line by line (a redesign, a new building footprint): re-estimate from the new set. Also once the contract is signed, when a revision becomes a contractual change with its own procedure.
Identify both sets before comparing anything
Most revision mistakes in an estimate are not comparison errors. They come from pricing a sheet that was already superseded, or from comparing against the wrong baseline. Before opening any overlay, establish exactly which issue you priced and exactly what the new issue contains.
The four places that identify a sheet
- Title block: sheet number, title, revision, date, and often the issue purpose (issued for bid, for permit, for construction). In the US, many sets follow the sheet identifier of the National CAD Standard's Uniform Drawing System: a discipline designator, a sheet type and a sequence number, so A-101 is the first architectural plan sheet. The same standard says sequence numbers need not be sequential, to leave room for inserted sheets: a gap in the numbering is not a missing sheet, the index decides.
- Revision block: one line per revision, with its number or letter, date and a short description. The description is the designer's summary, useful to start from and never enough to price from.
- Sheet index or drawing register: the list of every sheet in the set and its current revision. The index on the cover sheet is itself a sheet, and it is reissued when sheets are added or deleted.
- Transmittal: what was sent with this issue, at which revision, and for which purpose. It is the list you reconcile the received files against.
Issue purpose and revision codes
A revision issued for information or for coordination is not a revision issued for bid. On UK projects run under BS EN ISO 19650, the UK National Annex distinguishes a preliminary revision (P01, P02) from a published, contractual one (C01, C02), and gives each issue a status code, for example S1 for coordination or S3 for review and comment, as the UK BIM Framework guidance explains. When a tender pack mixes P and C revisions, note it in the matrix: you are pricing information the design team has not published as contractual.
| Object | US | UK | What it is for here |
|---|---|---|---|
| A change issued during bidding | Addendum (bulletin on some projects) | Tender addendum, revision letter | A numbered document that changes the bid documents before bids are due |
| The list of sheets and their current revision | Sheet index on the cover sheet, drawing log | Drawing register, drawing issue sheet | The reference you reconcile every received file against |
| The cover note of an issue | Transmittal | Transmittal, issue sheet | What was sent, at which revision, for which purpose, to whom |
| A marked change on a sheet | Revision cloud with a delta (triangle) tag | Revision cloud with a revision tag | The designer's notice of a change, not a guarantee that it is the only one |
| A question to the design team before bid | Pre-bid RFI, bidder's question | Tender query, clarification | Answered in a later addendum when the answer changes the documents |
Sheets superseded, added and missing
Reconcile three lists before comparing any content: the index of the set you priced, the transmittal of the new issue, and the files you actually received. Each sheet lands in one of five states:
- Reissued: a new revision of a sheet you priced. Compare it with the revision you priced, not with the one before.
- Added: a sheet number that did not exist. Everything on it is new until shown otherwise.
- Deleted or superseded: a sheet withdrawn, often with its content moved elsewhere. Confirm where the content went before closing it; a deleted sheet whose content went nowhere is a scope deletion.
- Not reissued: still current at its old revision, but possibly contradicted by a reissued sheet that references it.
- Missing: listed on the transmittal or the new index, not in the files. Ask for it the same day; do not price around it.
Illustrative example, invented figures: the sheet reconciliation for Addendum 2 (the worked example below)
| Sheet | Bid set revision | Addendum 2 transmittal | File received | Result |
|---|---|---|---|---|
| A-001 | 0 | 1 | 1 | Reissued: sheet index updated |
| A-101 | 0 | 1 | 1 | Reissued: compare |
| A-102 | 0 | 1 | 1 | Reissued: compare |
| A-121 | 0 | 1 | 1 | Reissued, no cloud, no narrative item: compare in full |
| A-401 | 0 | Deleted | None | Superseded: content moved to A-402 |
| A-402 | 0 | 1 | 1 | Reissued: compare |
| A-503 | None | 0 | 0 | Added sheet: new scope to measure |
| A-601 | 0 | Not reissued | None | Current at 0, but check it against A-102 |
| A-702 | 0 | 1 | Not received | Missing: ask for it |
| S-001 | 0 | 1 | 1 | Reissued: general notes changed |
| S-101 | 0 | Not reissued | None | Current at 0 |
Graphic change or scope change
A comparison tool finds differences. An estimate needs to know which differences cost something. Give every difference one of four types, and only one: if a change is both a quantity and a scope change, it is a scope change, and it takes several matrix rows.
| Type | Definition | Example | In the estimate |
|---|---|---|---|
| Graphic only | Nothing to build changes: a dimension string moved to another face, a tag renumbered, text reflowed, a view moved on the sheet | Dimension 30'-0" between grids 3 and 4 now dimensioned to centreline instead of face of stud; the wall has not moved | Record it as closed with no cost, so nobody re-checks it |
| Quantity | The same estimate items, in different amounts | Slab on grade thickened from 5" to 6" in one room; one more door of an existing type | Remeasure, change the quantity, keep the unit price |
| Scope | An item appears, disappears or changes in kind | Partition type W3 to ceiling replaced by W5 rated to deck; a canopy added on a new sheet | Remove the old item and add the new one at its own unit price; check dependent items |
| Spec | The requirement changes in words: material, performance, standard, allowance, warranty, in the specifications, the general notes or the addendum narrative | Abuse-resistant gypsum board required on corridor walls by an addendum item, with no sheet reissued | Price the difference on the quantity already measured; find every sheet the requirement touches |
The classic trap is the moved dimension string. On an overlay it shows exactly like a moved wall: two lines in two colours. The only way to tell them apart is to check whether the element itself moved, against the grid or a fixed reference. The reverse trap is a change of wall type tag: a few characters of text on the overlay, and possibly the largest cost change in the issue.
Notes, specifications and addenda
Drawings are only part of the documents. An addendum can change scope with no sheet reissued, and a sheet can be reissued with a change no addendum item mentions. On US federal sealed bids, an amendment may change quantities, specifications or delivery, or correct a defective or ambiguous invitation (FAR 14.208), and every term it does not modify stays unchanged (FAR 52.214-3). Private owners write the same idea into their instructions to bidders.
| Situation | Why a sheet comparison misses it | What to do |
|---|---|---|
| Addendum narrative changes a specification section, no sheet reissued | Overlay shows nothing | Read every numbered item of the addendum; list each one as a matrix row even when it has no sheet |
| Sheet reissued with a change and no cloud | Revision block and narrative say nothing about it | Overlay every reissued sheet in full, not only the clouded areas |
| Sheet reissued, but a schedule or detail it depends on is not | The plan shows a new door; the door schedule still lists the old doors | Follow each change to the sheets it references and raise a question when they now disagree |
| General note changed on a general or notes sheet | A plan that is not reissued is still affected | Treat notes sheets as scope documents: compare them line by line |
| Answer to a bidder's question published in an addendum | The answer may change scope without a drawing | Log the answer as a row, linked to the question that caused it |
Comparing plans with specifications inside one issue is a related but different check; the article on detecting plan and specification inconsistencies before a bid covers it. Here, the question is narrower: what did this issue change compared with the one you priced.
UK bills of quantities
Where the client's quantity surveyor issues a bill of quantities, check whether the addendum also reissues the bill items affected by the revised drawings. If the drawings changed and the bill did not, the two documents now disagree, and that is a tender query, not a quantity you correct on your own.
What overlay and compare tools show, and what they cannot
Overlay and compare tools are the fastest way to find differences between two revisions of a sheet, and every estimating team should use one. They are mostly of two kinds:
- Overlay: both revisions stacked in different colours. In Bluebeam Revu, Overlay Pages converts each file to a colour and stacks them as layers; where the colours fall on each other they blend darker, so the elements that changed stand out (Bluebeam). In Procore's drawing comparison, removed items appear in red and added items in blue (Procore).
- Compare with markups: Bluebeam's Compare Documents writes a new file in which each difference is circled with a cloud markup that can be listed and reviewed.
What they show well
- Every place where linework or text differs between two pages, including changes nobody clouded
- Small text changes that the eye misses: a wall type tag, a door number, a note's last word
- Where nothing changed, so a reissued sheet with no difference can be closed quickly
What they cannot tell you
- Whether a difference costs anything: a moved dimension and a moved wall look the same
- How much a quantity changed: an overlay shows a longer wall, not how many feet, at what height, of which type
- Which estimate items a change touches, and which sheets that were not reissued it contradicts
- Anything changed in the specifications, the general notes on another sheet, or the addendum narrative
- Changes on a missing sheet, or on a sheet you never received
They also need comparable inputs. Bluebeam offers page, automatic and manual three-point alignment because a sheet whose view was moved or rescaled lights up everywhere; Procore states that drawings of different sizes cannot be compared. A scanned or re-plotted sheet produces noise. When a whole sheet lights up, realign or compare region by region, and do not read the colours until the grid lines sit on each other.
In short: the tool produces the list of differences. The matrix is where each one becomes a type, a set of estimate items, a quantity, a price and a decision.
The impact matrix
One row per affected estimate item, not per change: a change that removes one partition type and adds another takes two rows, plus one for each dependent item. The cost delta is always the difference in quantity times the unit price of that line, as direct cost before markups, so the matrix adds up to the change in the direct cost of the estimate.
| Column | What to enter | Values |
|---|---|---|
| ID | Row number; one row per affected estimate item, so one change can take several rows (2a, 2b, 2c) | Text |
| Sheet or document | Sheet number, or the addendum item and specification section when no sheet changed | A-101; Add. 2 item 4, 09 21 16 |
| Revision | Old and new revision of that sheet | 0 to 1; new at 0; deleted |
| Change | What changed, in one sentence, with location (grid, room, detail) | Text |
| Type | One value only | Graphic only, Quantity, Scope, Spec, Missing |
| Estimate item | The line in your estimate, with its code if you use one | Text, or none |
| Old qty | Quantity carried in the estimate before this revision | Number |
| New qty | Quantity remeasured on the new revision | Number |
| Unit | Unit of the estimate line | LF, SF, CY, EA, m, m², m³ |
| Unit price | Unit price of that line in the current estimate (direct cost); a new item takes its own price | Currency |
| Cost delta | (New qty minus old qty) times unit price, before markups | Currency, signed |
| Confidence | How sure the row is | High, Medium, Low |
| Question | What to ask the design team, if anything | Text, or none |
| Status | Where the row stands | Open, Question sent, Priced pending answer, Allowance, Validated, Closed |
| Validated by | Who checked the measure and who accepted the price, with the date | Role and initials |
Confidence
High: the change is fully drawn and specified, and remeasured. Medium: measured, but something it depends on was not reissued or the change was not clouded or described. Low: not enough information to price without an assumption, or a sheet missing. Every Medium or Low row carries a question.
| ID | Sheet or document | Revision | Change | Type | Estimate item | Old qty | New qty | Unit | Unit price | Cost delta | Confidence | Question | Status | Validated by |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Both files are plain CSV: one row per estimate item, the columns above, nothing hidden. The worked example carries the values shown on this page.
Worked example: Addendum 2 on a medical office building
Illustrative example, invented figures: a two-storey medical office building, general contractor's estimate
Assumptions, all invented. The general contractor priced the bid set at revision 0 and carries its estimate at estimate revision E1. Addendum 2 arrives six days before bids are due: a narrative with five items, a transmittal listing eight sheets, and seven files. Unit prices are those of E1, in US dollars, direct cost before markups. A new item (the canopy, the W5 partition) takes a unit price the chief estimator accepts. The slab change on S-001 covers 1,620 SF: 25.0 CY at 5 inches, 30.0 CY at 6 inches.
| ID | Sheet or document | Revision | Change | Type | Estimate item | Old qty | New qty | Unit | Unit price | Cost delta | Confidence | Question | Status | Validated by |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | A-101 | 0 to 1 | Dimension between grids 3 and 4 now to centreline; wall not moved | Graphic only | None | None | None | None | None | Not priced | High | None | Closed | Estimator |
| 2a | A-101 | 0 to 1 | Rooms 112 to 118: partition W3 (to ceiling) replaced by W5 (1-hour, to deck) | Scope | Partition W3, 10 ft | 84 | 0 | LF | $68.00 | -$5,712 | High | None | Validated | Chief estimator |
| 2b | A-101 | 0 to 1 | Same change | Scope | Partition W5, 14 ft to deck | 0 | 84 | LF | $142.00 | $11,928 | High | None | Validated | Chief estimator |
| 2c | A-101 | 0 to 1 | Same change: rated head of wall | Scope | Head-of-wall firestop joint | 0 | 84 | LF | $18.50 | $1,554 | High | None | Validated | Chief estimator |
| 3 | A-102 | 0 to 1 | New door 214B between rooms 214 and 215 (clouded) | Quantity | Door, frame and hardware, type D2 | 0 | 1 | EA | $2,350.00 | $2,350 | Medium | Door 214B is not on schedule A-601 (not reissued): confirm type and hardware set | Priced pending answer | Estimator |
| 4 | S-001 | 0 to 1 | Note 7: slab on grade in mechanical room 120 from 5 in to 6 in, 1,620 SF | Quantity | Slab on grade concrete, placed | 25 | 30 | CY | $260.00 | $1,300 | High | None | Validated | Chief estimator |
| 5 | A-503 | new at 0 | Entrance canopy, 24 ft by 8 ft, steel frame (new sheet) | Scope | Entrance canopy, complete | 0 | 192 | SF | $95.00 | $18,240 | Low | No specification section referenced: confirm roofing, soffit finish and which package carries the steel | Allowance | Chief estimator |
| 6 | Add. 2 item 4, 09 21 16 | no sheet | Abuse-resistant gypsum board on corridor walls, one face | Spec | Gypsum board upgrade, corridors | 0 | 2,400 | SF | $1.10 | $2,640 | High | None | Validated | Chief estimator |
| 7a | A-121 | 0 to 1 | Rooms 105 to 109: ceiling ACT-1 changed to ACT-2, no cloud, not in the narrative | Scope | ACT-1 acoustic ceiling | 1,850 | 0 | SF | $4.80 | -$8,880 | Medium | Unclouded change on A-121: confirm it is intended | Priced pending answer | Estimator |
| 7b | A-121 | 0 to 1 | Same change | Scope | ACT-2 acoustic ceiling | 0 | 1,850 | SF | $6.30 | $11,655 | Medium | Same question | Priced pending answer | Estimator |
| 8 | A-702 | 0 to 1 (listed) | Listed on the transmittal, file not received | Missing | Unknown until received | None | None | None | None | Not priced | Low | Please reissue A-702 Rev 1, listed on the Addendum 2 transmittal | Question sent | Pending |
| 9 | A-401 | deleted | Enlarged toilet plans moved to A-402 Rev 1; content compared, identical | Graphic only | None | None | None | None | None | Not priced | High | None | Closed | Estimator |
| Status | Rows | Cost delta |
|---|---|---|
| Validated | 2a, 2b, 2c, 4, 6 | $11,710 |
| Priced, pending an answer | 3, 7a, 7b | $5,125 |
| Allowance, pending an answer | 5 | $18,240 |
| Closed with no cost, or not priced yet | 1, 8, 9 | $0 |
| Total | All | $35,075 |
Read row by row, the issue changes the direct cost by $35,075. The partition change on A-101 alone is a net $7,770 once the old wall is removed and the rated wall and its head joint are added; pricing only the new wall would have overstated it by $5,712. The ceiling change on A-121, a net $2,775, was not clouded and not in the narrative: only a full comparison of the reissued sheet found it. The abuse-resistant board, $2,640, came from the narrative with no sheet at all.
Of the total, $11,710 is validated. The canopy, $18,240, is the largest row and the least certain: carried as an allowance with its basis written down until the question on its roofing and steel package is answered. Sheet A-702 is not priced at all, because it never arrived.
Estimate line items to rework
A change rarely touches one line. Before marking a row validated, walk through what else the changed item drags with it:
| What | What to do |
|---|---|
| The measured item itself | Remeasure on the new revision; never adjust the old quantity by eye |
| Dependent items | Firestopping, sealants, hardware, finishes, insulation, access panels: whatever the changed item carries with it |
| Labour and productivity | A wall going to deck is slower per foot than a wall to ceiling; a unit price built from crew rates needs the new crew, not the old one |
| Subcontractor and supplier quotes | A quote based on the previous revision no longer covers the scope: ask the trade to confirm or re-quote against the new sheets, and record which revision each quote is based on |
| Allowances and contingency | A low-confidence row either becomes an allowance with a stated basis or stays a risk the chief estimator prices explicitly |
| General conditions and duration | Only when the change moves the programme: a long-lead item added, a sequence changed |
| Alternates and unit prices requested in the bid form | An addendum can add, delete or redefine them; check the bid form itself |
Subcontractor quotes deserve their own pass. A trade that priced revision 0 has not priced the rated wall. The guide to subcontractor bid leveling covers how to compare quotes on the same scope; the revision matters because a quote levelled against an old sheet is levelled against the wrong scope. If you build your estimate in a spreadsheet, the construction estimate template keeps quantity and unit price in separate columns, which is what makes a remove and add change traceable.
Questions to settle before bid day
Every Medium or Low row carries a question, and every question has a deadline: the last date for bidder questions in the instructions to bidders. Write questions the design team can answer in one line, and write down the assumption you will carry if they do not.
| Field | Content |
|---|---|
| Sheet and revision | A-102 Rev 1, door 214B |
| What the documents say | A-102 Rev 1 shows a new door 214B; door schedule A-601 Rev 0 has no entry for it |
| Why it matters to the price | Door type and hardware set set the cost of the opening |
| What we will assume if no answer is issued | Same type and hardware set as door 214A |
| Answer needed by | The question deadline in the instructions to bidders |
The RFI template has the fields of such a question and a log to follow it. If no answer is issued in time, the chief estimator decides between three courses for each open row: carry the assumption silently, price it with a margin, or state it in the bid. The third is the most honest and not always allowed: on US federal sealed bids, a bid that imposes conditions modifying the requirements of the invitation is rejected (FAR 14.404-2(d)). Private owners and UK tenders set their own rules on qualifications; read them before writing one.
Human control and the validation history
The matrix is also the record of who decided what. Keep two signatures apart: the estimator who measured a row, and the chief estimator who accepted its price and its type. A row is not validated until both have looked at it.
| Record | Content |
|---|---|
| Estimate revision | E2, built on the bid set plus Addenda 1 and 2 |
| Documents compared | Bid set Rev 0 against the Addendum 2 transmittal and files, with the sheet reconciliation attached |
| Matrix | Every row with its status and the person who validated it, and the date |
| Questions | Sent, answered, unanswered, with the assumption carried for each unanswered one |
| Superseded sheets | Kept in an archive folder and marked superseded, never deleted |
| Sign-off | Chief estimator, with the date, before the figure moves to the bid summary |
On bid day, the last check is that every addendum is acknowledged on the bid form. On US federal sealed bids, bidders acknowledge each amendment (FAR 52.214-3), and a missing acknowledgment is waived only when the bid shows the amendment was received, or when the amendment has no more than a negligible effect on price, quantity, quality or delivery (FAR 14.405(d)). The guide to estimating under pressure puts that check in the final review, done by someone who did not price the bid.
After award it is a change, not an addendum
Everything above happens before the bid goes in, while the documents are still moving and the estimate absorbs each change. Once the contract is signed, the signed documents are the baseline, and a revised drawing is a change to the contract. Three things change:
- The procedure. The contract's change clause governs. Under the US federal Changes clause, the contracting officer orders changes in writing, the contractor asserts its right to an adjustment within 30 days, and an equitable adjustment follows (FAR 52.243-4). Under NEC4, a Project Manager instruction that changes the Scope is a compensation event, and a contractor whose notification has not reached the Project Manager within eight weeks of the event is not entitled to more time or money (NEC).
- Who bears it. Before bid, you price the change into your number. After award, whether a change is paid depends on the contract: some revisions are within the scope already priced, others entitle you to time and money.
- Time limits. Notices have deadlines that do not exist during bidding. Missing one can cost the entitlement however good the pricing.
The impact matrix still does the pricing work after award: same columns, with the contract revision as the old quantity. The rest belongs to change management: the change order template for the form and the log, and, on FIDIC contracts, the FIDIC Red Book notices and claims guide.
Where Mirage fits
Mirage deploys AI agents that do the reading and comparing part of this method: reconcile the received files with the transmittal and the index, compare each reissued sheet with the one you priced, list every difference with its location on both revisions, and remeasure what changed, for your estimators to classify, price and sign off. The offer is described on the plan revision comparison software page.
At OCBM, a Moroccan general contractor, a dedicated agent checks consistency across drawing revisions and between the tender documents themselves, comparing versions of plans and tender documents to surface discrepancies before they reach a submitted bid. The case study states that OCBM's estimators no longer diff drawing revisions by hand and that 100% of quantities are traceable to a source drawing. Those facts describe that deployment only.
Questions readers ask
For the items it changes, an addendum is normally the later and governing document, but how documents rank is set by the bid documents themselves, usually in the instructions to bidders or an order of precedence clause. Read that clause on every project. When an addendum and a reissued sheet disagree with each other, do not choose: ask.
Assume yes. On US federal sealed bids, FAR 52.214-3 requires bidders to acknowledge each amendment, and FAR 14.405(d) treats a missing acknowledgment as a minor informality only when the bid shows the amendment was received or the amendment has no more than a negligible effect on price, quantity, quality or delivery. Other owners have their own rules, written in their instructions to bidders.
Use them as a starting list, not as the full list. A cloud is the designer's notice of a change; a change made without a cloud, or a cloud left around an area that did not change, both happen. Compare every reissued sheet in full and record what you found, clouded or not.
Price the reading you can defend, record the assumption in the matrix, and let the chief estimator decide whether it is carried silently, priced with a margin, or stated in the bid. Be careful with stated conditions on public bids: under FAR 14.404-2(d), a US federal bid that imposes conditions modifying the requirements of the invitation is rejected.
The comparison is the same; the consequences are not. After award, the baseline is the contract documents and a change runs through the contract's own change mechanism, with its notices and time limits. The impact matrix still helps to price it, but it is no longer an estimate update.
Sources and scope
Checked on . Scope: drawing revisions and addenda during bidding, US and UK practice. The method, the matrix and the worked example are Mirage's own, with invented figures. The FAR provisions apply to US federal sealed bidding and are quoted as examples of how an owner writes the rules; other owners write their own.
- US National CAD Standard v5, Uniform Drawing System Module 1, 1.3 Sheet identification: the sheet identifier made of a discipline designator, a sheet type designator and a sequence number; sequence numbers need not be sequential
- UK BIM Framework, Information management according to BS EN ISO 19650, Guidance Part 2, edition 4: P (preliminary) and C (published, contractual) revision codes under the UK National Annex, and status codes such as S1 (coordination) and S3 (review and comment)
- Bluebeam, Compare original PDFs with their revisions: Compare Documents (cloud markups in a new file) and Overlay Pages (coloured layers), and their page, auto and manual alignment options
- Procore, Compare Drawing Revisions: removed items in red, added items in blue; drawings of different sizes cannot be compared; at least two revisions must be uploaded
- FAR 52.214-3, Amendments to Invitations for Bids: unmodified terms remain unchanged; bidders acknowledge each amendment before the time set for receipt of bids
- FAR 14.208, Amendment of invitation for bids: amendments for changes in quantity, specifications or schedule, or to correct a defective or ambiguous invitation, sent to everyone invited before bid opening
- FAR 14.405, Minor informalities or irregularities in bids: when a missing acknowledgment of an amendment can be waived, paragraph (d)
- FAR 14.404-2, Rejection of individual bids: a bid imposing conditions that modify the requirements of the invitation is rejected, paragraph (d)
- FAR 52.243-4, Changes: written change orders within the general scope, equitable adjustment, 30 days to assert the right to an adjustment
- NEC, Compensation events: an introduction for new NEC users (April 2024): a Project Manager instruction changing the Scope as a compensation event, and the eight-week notification limit
- Mirage Metrics, OCBM case study: every OCBM fact quoted on this page
Related on this site
- Plan revision comparison software: the comparison done for you, with a delta report per revision
- OCBM case study: drawing revisions and tender documents compared before submission
- AI quantity takeoff and estimating: where the quantities in the matrix come from
- Electrical takeoff from 2D drawings: the revision and scale check per sheet, before counting
- Subcontractor bid leveling: quotes compared on the same, current scope
- Specification review: plans checked against the specifications within one issue
- RFI template: the questions to the design team, logged
- Change order template: the same change, after award