Comparing Drawing Revisions: Impact on Quantities, Price and Scope

A new revision or an addendum lands days before the bid is due. The question is not what moved on the sheet but what it does to your number: which quantities change, which items appear or disappear, which requirements changed in words only, and what you still have to ask. This guide sets out the comparison step by step and gives an impact matrix you can copy, filled in for a worked example.

Published
Sources checked
Reading time
14 min
Written by
Mirage Metrics team

Scope: drawing revisions and addenda received while you are still estimating, up to bid submission, on building and civil work in the US and the UK. After award the same comparison feeds a change order or a variation; the last section says what changes then.

Decision snapshot

Best suited to
Estimators, chief estimators, preconstruction managers and quantity surveyors who priced one issue of the documents and have just received the next.
Inputs needed
The previous set as priced (with its sheet index or drawing register), the new transmittal and every file it lists, the addendum narrative, the specification sections it touches, and the current estimate with its unit prices.
What can be automated
Reconciling received files against the transmittal and the sheet index, comparing each reissued sheet with its previous revision, listing every difference with its location, remeasuring the quantities that changed, and filling the old and new quantity columns of the matrix.
What requires human approval
Classifying each difference as graphic only, quantity, scope or specification; choosing the estimate items it touches; accepting a unit price for a new item; deciding what to ask, what to assume and what to carry as an allowance; signing off the revised estimate.
When this approach is insufficient
When the change is too large to compare line by line (a redesign, a new building footprint): re-estimate from the new set. Also once the contract is signed, when a revision becomes a contractual change with its own procedure.

Identify both sets before comparing anything

Most revision mistakes in an estimate are not comparison errors. They come from pricing a sheet that was already superseded, or from comparing against the wrong baseline. Before opening any overlay, establish exactly which issue you priced and exactly what the new issue contains.

The four places that identify a sheet

  • Title block: sheet number, title, revision, date, and often the issue purpose (issued for bid, for permit, for construction). In the US, many sets follow the sheet identifier of the National CAD Standard's Uniform Drawing System: a discipline designator, a sheet type and a sequence number, so A-101 is the first architectural plan sheet. The same standard says sequence numbers need not be sequential, to leave room for inserted sheets: a gap in the numbering is not a missing sheet, the index decides.
  • Revision block: one line per revision, with its number or letter, date and a short description. The description is the designer's summary, useful to start from and never enough to price from.
  • Sheet index or drawing register: the list of every sheet in the set and its current revision. The index on the cover sheet is itself a sheet, and it is reissued when sheets are added or deleted.
  • Transmittal: what was sent with this issue, at which revision, and for which purpose. It is the list you reconcile the received files against.

Issue purpose and revision codes

A revision issued for information or for coordination is not a revision issued for bid. On UK projects run under BS EN ISO 19650, the UK National Annex distinguishes a preliminary revision (P01, P02) from a published, contractual one (C01, C02), and gives each issue a status code, for example S1 for coordination or S3 for review and comment, as the UK BIM Framework guidance explains. When a tender pack mixes P and C revisions, note it in the matrix: you are pricing information the design team has not published as contractual.

The same objects in US and UK vocabulary
ObjectUSUKWhat it is for here
A change issued during biddingAddendum (bulletin on some projects)Tender addendum, revision letterA numbered document that changes the bid documents before bids are due
The list of sheets and their current revisionSheet index on the cover sheet, drawing logDrawing register, drawing issue sheetThe reference you reconcile every received file against
The cover note of an issueTransmittalTransmittal, issue sheetWhat was sent, at which revision, for which purpose, to whom
A marked change on a sheetRevision cloud with a delta (triangle) tagRevision cloud with a revision tagThe designer's notice of a change, not a guarantee that it is the only one
A question to the design team before bidPre-bid RFI, bidder's questionTender query, clarificationAnswered in a later addendum when the answer changes the documents
The same objects in US and UK vocabulary

Sheets superseded, added and missing

Reconcile three lists before comparing any content: the index of the set you priced, the transmittal of the new issue, and the files you actually received. Each sheet lands in one of five states:

  • Reissued: a new revision of a sheet you priced. Compare it with the revision you priced, not with the one before.
  • Added: a sheet number that did not exist. Everything on it is new until shown otherwise.
  • Deleted or superseded: a sheet withdrawn, often with its content moved elsewhere. Confirm where the content went before closing it; a deleted sheet whose content went nowhere is a scope deletion.
  • Not reissued: still current at its old revision, but possibly contradicted by a reissued sheet that references it.
  • Missing: listed on the transmittal or the new index, not in the files. Ask for it the same day; do not price around it.

Illustrative example, invented figures: the sheet reconciliation for Addendum 2 (the worked example below)

Sheet reconciliation: bid set, Addendum 2 transmittal, files received (invented)
SheetBid set revisionAddendum 2 transmittalFile receivedResult
A-001011Reissued: sheet index updated
A-101011Reissued: compare
A-102011Reissued: compare
A-121011Reissued, no cloud, no narrative item: compare in full
A-4010DeletedNoneSuperseded: content moved to A-402
A-402011Reissued: compare
A-503None00Added sheet: new scope to measure
A-6010Not reissuedNoneCurrent at 0, but check it against A-102
A-70201Not receivedMissing: ask for it
S-001011Reissued: general notes changed
S-1010Not reissuedNoneCurrent at 0
Sheet reconciliation: bid set, Addendum 2 transmittal, files received (invented)

Graphic change or scope change

A comparison tool finds differences. An estimate needs to know which differences cost something. Give every difference one of four types, and only one: if a change is both a quantity and a scope change, it is a scope change, and it takes several matrix rows.

Four types of change, with an example of each and what to do in the estimate
TypeDefinitionExampleIn the estimate
Graphic onlyNothing to build changes: a dimension string moved to another face, a tag renumbered, text reflowed, a view moved on the sheetDimension 30'-0" between grids 3 and 4 now dimensioned to centreline instead of face of stud; the wall has not movedRecord it as closed with no cost, so nobody re-checks it
QuantityThe same estimate items, in different amountsSlab on grade thickened from 5" to 6" in one room; one more door of an existing typeRemeasure, change the quantity, keep the unit price
ScopeAn item appears, disappears or changes in kindPartition type W3 to ceiling replaced by W5 rated to deck; a canopy added on a new sheetRemove the old item and add the new one at its own unit price; check dependent items
SpecThe requirement changes in words: material, performance, standard, allowance, warranty, in the specifications, the general notes or the addendum narrativeAbuse-resistant gypsum board required on corridor walls by an addendum item, with no sheet reissuedPrice the difference on the quantity already measured; find every sheet the requirement touches
Four types of change, with an example of each and what to do in the estimate

The classic trap is the moved dimension string. On an overlay it shows exactly like a moved wall: two lines in two colours. The only way to tell them apart is to check whether the element itself moved, against the grid or a fixed reference. The reverse trap is a change of wall type tag: a few characters of text on the overlay, and possibly the largest cost change in the issue.

Notes, specifications and addenda

Drawings are only part of the documents. An addendum can change scope with no sheet reissued, and a sheet can be reissued with a change no addendum item mentions. On US federal sealed bids, an amendment may change quantities, specifications or delivery, or correct a defective or ambiguous invitation (FAR 14.208), and every term it does not modify stays unchanged (FAR 52.214-3). Private owners write the same idea into their instructions to bidders.

Where a change hides, what the comparison misses, and what to do
SituationWhy a sheet comparison misses itWhat to do
Addendum narrative changes a specification section, no sheet reissuedOverlay shows nothingRead every numbered item of the addendum; list each one as a matrix row even when it has no sheet
Sheet reissued with a change and no cloudRevision block and narrative say nothing about itOverlay every reissued sheet in full, not only the clouded areas
Sheet reissued, but a schedule or detail it depends on is notThe plan shows a new door; the door schedule still lists the old doorsFollow each change to the sheets it references and raise a question when they now disagree
General note changed on a general or notes sheetA plan that is not reissued is still affectedTreat notes sheets as scope documents: compare them line by line
Answer to a bidder's question published in an addendumThe answer may change scope without a drawingLog the answer as a row, linked to the question that caused it
Where a change hides, what the comparison misses, and what to do

Comparing plans with specifications inside one issue is a related but different check; the article on detecting plan and specification inconsistencies before a bid covers it. Here, the question is narrower: what did this issue change compared with the one you priced.

UK bills of quantities

Where the client's quantity surveyor issues a bill of quantities, check whether the addendum also reissues the bill items affected by the revised drawings. If the drawings changed and the bill did not, the two documents now disagree, and that is a tender query, not a quantity you correct on your own.

What overlay and compare tools show, and what they cannot

Overlay and compare tools are the fastest way to find differences between two revisions of a sheet, and every estimating team should use one. They are mostly of two kinds:

  • Overlay: both revisions stacked in different colours. In Bluebeam Revu, Overlay Pages converts each file to a colour and stacks them as layers; where the colours fall on each other they blend darker, so the elements that changed stand out (Bluebeam). In Procore's drawing comparison, removed items appear in red and added items in blue (Procore).
  • Compare with markups: Bluebeam's Compare Documents writes a new file in which each difference is circled with a cloud markup that can be listed and reviewed.

What they show well

  • Every place where linework or text differs between two pages, including changes nobody clouded
  • Small text changes that the eye misses: a wall type tag, a door number, a note's last word
  • Where nothing changed, so a reissued sheet with no difference can be closed quickly

What they cannot tell you

  • Whether a difference costs anything: a moved dimension and a moved wall look the same
  • How much a quantity changed: an overlay shows a longer wall, not how many feet, at what height, of which type
  • Which estimate items a change touches, and which sheets that were not reissued it contradicts
  • Anything changed in the specifications, the general notes on another sheet, or the addendum narrative
  • Changes on a missing sheet, or on a sheet you never received

They also need comparable inputs. Bluebeam offers page, automatic and manual three-point alignment because a sheet whose view was moved or rescaled lights up everywhere; Procore states that drawings of different sizes cannot be compared. A scanned or re-plotted sheet produces noise. When a whole sheet lights up, realign or compare region by region, and do not read the colours until the grid lines sit on each other.

In short: the tool produces the list of differences. The matrix is where each one becomes a type, a set of estimate items, a quantity, a price and a decision.

The impact matrix

One row per affected estimate item, not per change: a change that removes one partition type and adds another takes two rows, plus one for each dependent item. The cost delta is always the difference in quantity times the unit price of that line, as direct cost before markups, so the matrix adds up to the change in the direct cost of the estimate.

Impact matrix columns: what to enter and the allowed values
ColumnWhat to enterValues
IDRow number; one row per affected estimate item, so one change can take several rows (2a, 2b, 2c)Text
Sheet or documentSheet number, or the addendum item and specification section when no sheet changedA-101; Add. 2 item 4, 09 21 16
RevisionOld and new revision of that sheet0 to 1; new at 0; deleted
ChangeWhat changed, in one sentence, with location (grid, room, detail)Text
TypeOne value onlyGraphic only, Quantity, Scope, Spec, Missing
Estimate itemThe line in your estimate, with its code if you use oneText, or none
Old qtyQuantity carried in the estimate before this revisionNumber
New qtyQuantity remeasured on the new revisionNumber
UnitUnit of the estimate lineLF, SF, CY, EA, m, m², m³
Unit priceUnit price of that line in the current estimate (direct cost); a new item takes its own priceCurrency
Cost delta(New qty minus old qty) times unit price, before markupsCurrency, signed
ConfidenceHow sure the row isHigh, Medium, Low
QuestionWhat to ask the design team, if anythingText, or none
StatusWhere the row standsOpen, Question sent, Priced pending answer, Allowance, Validated, Closed
Validated byWho checked the measure and who accepted the price, with the dateRole and initials
Impact matrix columns: what to enter and the allowed values

Confidence

High: the change is fully drawn and specified, and remeasured. Medium: measured, but something it depends on was not reissued or the change was not clouded or described. Low: not enough information to price without an assumption, or a sheet missing. Every Medium or Low row carries a question.

Blank impact matrix, ready to copy
IDSheet or documentRevisionChangeTypeEstimate itemOld qtyNew qtyUnitUnit priceCost deltaConfidenceQuestionStatusValidated by
Blank impact matrix, ready to copy

Both files are plain CSV: one row per estimate item, the columns above, nothing hidden. The worked example carries the values shown on this page.

Worked example: Addendum 2 on a medical office building

Illustrative example, invented figures: a two-storey medical office building, general contractor's estimate

Assumptions, all invented. The general contractor priced the bid set at revision 0 and carries its estimate at estimate revision E1. Addendum 2 arrives six days before bids are due: a narrative with five items, a transmittal listing eight sheets, and seven files. Unit prices are those of E1, in US dollars, direct cost before markups. A new item (the canopy, the W5 partition) takes a unit price the chief estimator accepts. The slab change on S-001 covers 1,620 SF: 25.0 CY at 5 inches, 30.0 CY at 6 inches.

Impact matrix for Addendum 2, filled in (invented figures)
IDSheet or documentRevisionChangeTypeEstimate itemOld qtyNew qtyUnitUnit priceCost deltaConfidenceQuestionStatusValidated by
1A-1010 to 1Dimension between grids 3 and 4 now to centreline; wall not movedGraphic onlyNoneNoneNoneNoneNoneNot pricedHighNoneClosedEstimator
2aA-1010 to 1Rooms 112 to 118: partition W3 (to ceiling) replaced by W5 (1-hour, to deck)ScopePartition W3, 10 ft840LF$68.00-$5,712HighNoneValidatedChief estimator
2bA-1010 to 1Same changeScopePartition W5, 14 ft to deck084LF$142.00$11,928HighNoneValidatedChief estimator
2cA-1010 to 1Same change: rated head of wallScopeHead-of-wall firestop joint084LF$18.50$1,554HighNoneValidatedChief estimator
3A-1020 to 1New door 214B between rooms 214 and 215 (clouded)QuantityDoor, frame and hardware, type D201EA$2,350.00$2,350MediumDoor 214B is not on schedule A-601 (not reissued): confirm type and hardware setPriced pending answerEstimator
4S-0010 to 1Note 7: slab on grade in mechanical room 120 from 5 in to 6 in, 1,620 SFQuantitySlab on grade concrete, placed2530CY$260.00$1,300HighNoneValidatedChief estimator
5A-503new at 0Entrance canopy, 24 ft by 8 ft, steel frame (new sheet)ScopeEntrance canopy, complete0192SF$95.00$18,240LowNo specification section referenced: confirm roofing, soffit finish and which package carries the steelAllowanceChief estimator
6Add. 2 item 4, 09 21 16no sheetAbuse-resistant gypsum board on corridor walls, one faceSpecGypsum board upgrade, corridors02,400SF$1.10$2,640HighNoneValidatedChief estimator
7aA-1210 to 1Rooms 105 to 109: ceiling ACT-1 changed to ACT-2, no cloud, not in the narrativeScopeACT-1 acoustic ceiling1,8500SF$4.80-$8,880MediumUnclouded change on A-121: confirm it is intendedPriced pending answerEstimator
7bA-1210 to 1Same changeScopeACT-2 acoustic ceiling01,850SF$6.30$11,655MediumSame questionPriced pending answerEstimator
8A-7020 to 1 (listed)Listed on the transmittal, file not receivedMissingUnknown until receivedNoneNoneNoneNoneNot pricedLowPlease reissue A-702 Rev 1, listed on the Addendum 2 transmittalQuestion sentPending
9A-401deletedEnlarged toilet plans moved to A-402 Rev 1; content compared, identicalGraphic onlyNoneNoneNoneNoneNoneNot pricedHighNoneClosedEstimator
Impact matrix for Addendum 2, filled in (invented figures)
Cost delta by status (invented figures, direct cost before markups)
StatusRowsCost delta
Validated2a, 2b, 2c, 4, 6$11,710
Priced, pending an answer3, 7a, 7b$5,125
Allowance, pending an answer5$18,240
Closed with no cost, or not priced yet1, 8, 9$0
TotalAll$35,075
Cost delta by status (invented figures, direct cost before markups)

Read row by row, the issue changes the direct cost by $35,075. The partition change on A-101 alone is a net $7,770 once the old wall is removed and the rated wall and its head joint are added; pricing only the new wall would have overstated it by $5,712. The ceiling change on A-121, a net $2,775, was not clouded and not in the narrative: only a full comparison of the reissued sheet found it. The abuse-resistant board, $2,640, came from the narrative with no sheet at all.

Of the total, $11,710 is validated. The canopy, $18,240, is the largest row and the least certain: carried as an allowance with its basis written down until the question on its roofing and steel package is answered. Sheet A-702 is not priced at all, because it never arrived.

Estimate line items to rework

A change rarely touches one line. Before marking a row validated, walk through what else the changed item drags with it:

What to check in the estimate for each change
WhatWhat to do
The measured item itselfRemeasure on the new revision; never adjust the old quantity by eye
Dependent itemsFirestopping, sealants, hardware, finishes, insulation, access panels: whatever the changed item carries with it
Labour and productivityA wall going to deck is slower per foot than a wall to ceiling; a unit price built from crew rates needs the new crew, not the old one
Subcontractor and supplier quotesA quote based on the previous revision no longer covers the scope: ask the trade to confirm or re-quote against the new sheets, and record which revision each quote is based on
Allowances and contingencyA low-confidence row either becomes an allowance with a stated basis or stays a risk the chief estimator prices explicitly
General conditions and durationOnly when the change moves the programme: a long-lead item added, a sequence changed
Alternates and unit prices requested in the bid formAn addendum can add, delete or redefine them; check the bid form itself
What to check in the estimate for each change

Subcontractor quotes deserve their own pass. A trade that priced revision 0 has not priced the rated wall. The guide to subcontractor bid leveling covers how to compare quotes on the same scope; the revision matters because a quote levelled against an old sheet is levelled against the wrong scope. If you build your estimate in a spreadsheet, the construction estimate template keeps quantity and unit price in separate columns, which is what makes a remove and add change traceable.

Questions to settle before bid day

Every Medium or Low row carries a question, and every question has a deadline: the last date for bidder questions in the instructions to bidders. Write questions the design team can answer in one line, and write down the assumption you will carry if they do not.

A question to the design team, row 3 of the worked example (invented)
FieldContent
Sheet and revisionA-102 Rev 1, door 214B
What the documents sayA-102 Rev 1 shows a new door 214B; door schedule A-601 Rev 0 has no entry for it
Why it matters to the priceDoor type and hardware set set the cost of the opening
What we will assume if no answer is issuedSame type and hardware set as door 214A
Answer needed byThe question deadline in the instructions to bidders
A question to the design team, row 3 of the worked example (invented)

The RFI template has the fields of such a question and a log to follow it. If no answer is issued in time, the chief estimator decides between three courses for each open row: carry the assumption silently, price it with a margin, or state it in the bid. The third is the most honest and not always allowed: on US federal sealed bids, a bid that imposes conditions modifying the requirements of the invitation is rejected (FAR 14.404-2(d)). Private owners and UK tenders set their own rules on qualifications; read them before writing one.

Human control and the validation history

The matrix is also the record of who decided what. Keep two signatures apart: the estimator who measured a row, and the chief estimator who accepted its price and its type. A row is not validated until both have looked at it.

What the validation history of a revised estimate keeps
RecordContent
Estimate revisionE2, built on the bid set plus Addenda 1 and 2
Documents comparedBid set Rev 0 against the Addendum 2 transmittal and files, with the sheet reconciliation attached
MatrixEvery row with its status and the person who validated it, and the date
QuestionsSent, answered, unanswered, with the assumption carried for each unanswered one
Superseded sheetsKept in an archive folder and marked superseded, never deleted
Sign-offChief estimator, with the date, before the figure moves to the bid summary
What the validation history of a revised estimate keeps

On bid day, the last check is that every addendum is acknowledged on the bid form. On US federal sealed bids, bidders acknowledge each amendment (FAR 52.214-3), and a missing acknowledgment is waived only when the bid shows the amendment was received, or when the amendment has no more than a negligible effect on price, quantity, quality or delivery (FAR 14.405(d)). The guide to estimating under pressure puts that check in the final review, done by someone who did not price the bid.

After award it is a change, not an addendum

Everything above happens before the bid goes in, while the documents are still moving and the estimate absorbs each change. Once the contract is signed, the signed documents are the baseline, and a revised drawing is a change to the contract. Three things change:

  • The procedure. The contract's change clause governs. Under the US federal Changes clause, the contracting officer orders changes in writing, the contractor asserts its right to an adjustment within 30 days, and an equitable adjustment follows (FAR 52.243-4). Under NEC4, a Project Manager instruction that changes the Scope is a compensation event, and a contractor whose notification has not reached the Project Manager within eight weeks of the event is not entitled to more time or money (NEC).
  • Who bears it. Before bid, you price the change into your number. After award, whether a change is paid depends on the contract: some revisions are within the scope already priced, others entitle you to time and money.
  • Time limits. Notices have deadlines that do not exist during bidding. Missing one can cost the entitlement however good the pricing.

The impact matrix still does the pricing work after award: same columns, with the contract revision as the old quantity. The rest belongs to change management: the change order template for the form and the log, and, on FIDIC contracts, the FIDIC Red Book notices and claims guide.

Where Mirage fits

Mirage deploys AI agents that do the reading and comparing part of this method: reconcile the received files with the transmittal and the index, compare each reissued sheet with the one you priced, list every difference with its location on both revisions, and remeasure what changed, for your estimators to classify, price and sign off. The offer is described on the plan revision comparison software page.

At OCBM, a Moroccan general contractor, a dedicated agent checks consistency across drawing revisions and between the tender documents themselves, comparing versions of plans and tender documents to surface discrepancies before they reach a submitted bid. The case study states that OCBM's estimators no longer diff drawing revisions by hand and that 100% of quantities are traceable to a source drawing. Those facts describe that deployment only.

Questions readers ask

Sources and scope

Checked on . Scope: drawing revisions and addenda during bidding, US and UK practice. The method, the matrix and the worked example are Mirage's own, with invented figures. The FAR provisions apply to US federal sealed bidding and are quoted as examples of how an owner writes the rules; other owners write their own.

Related on this site

Send us two revisions of a set you priced

Send the issue you priced and the revision or addendum that replaced it. We will return the sheet reconciliation and the list of every difference, located on both revisions, with the quantities that changed, for your estimators to classify and price.