Change Order Template (Excel)

A free Excel change order form and log for contractors: describe the change and what originated it, price it line by line, apply overhead, profit and bond, and show its effect on the contract sum and time.

Download the Excel template

Free, no sign-up. Opens in Excel, Google Sheets and LibreOffice.

Mirage does this work from your own documents. See change order automation

What the template looks like

The Change order sheet, block by block, and the Change order log sheet, with their own fields and columns, filled with the worked example further down this page: change order 007, entered in the log as Pending, so the running contract sum still reads the sum before it. The file you download is empty: every quantity, amount and rate is yours to enter.

Change order sheet: the change
FieldEntry
Change order number007
Originated by (owner, architect, field condition...)RFI answer
Reference (RFI, directive, bulletin)RFI 014
Description of the changeDuct reroute at grid C/4
Change order sheet: cost breakdown
ItemQuantityUnitLabor $Material $Equipment $Subcontract $Line total $
Duct reroute at grid C/4, labor16hour1,120.001,120.00
Fittings and insulation610.00610.00
Change order sheet: markups and total
RateMarkupAmount $
Subtotal1,730.00
10%Overhead173.00
5%Profit86.50
1%Bond17.30
Total of this change2,006.80
Change order sheet: contract sum and time
FieldEntry
Original contract sum4,250,000.00
Net change by previous change orders38,400.00
Contract sum before this change4,288,400.00
This change2,006.80
New contract sum4,290,406.80
Contract time change (days, + or -)0
New substantial completion date
Change order log sheet
CO no.DateDescriptionReferenceStatusAmount requested $Amount approved $DaysRunning contract sum $
007Duct reroute at grid C/4RFI 014Pending2,006.8004,288,400.00

Who uses it, and when

Contractors' project managers prepare change orders; owners, their representatives and the architect review and sign them. Subcontractors use the same structure to price their own change requests to the general contractor, which then marks them up and forwards them.

Cost engineers and owner's auditors use the log at the end of the job to reconcile the final contract sum: every movement in it should trace to a signed change order, and every change order to the document that originated it.

What is in the file

Change order
Number, project, contract, date, origin and reference, description and reason; a cost breakdown in labor, material, equipment and subcontract; overhead, profit and bond rates; the contract sum before and after; the change in contract time; and the signatures.
Change order log
One row per change order with its status, the amount requested and approved, the days, and a running contract sum that moves with approved changes only.
Instructions
How to fill it, step by step.

Column by column

Number, date, project, contract
Sequential numbering per contract, the date of the document and the contract it amends.
Originated by and reference
Who asked for the change and in which document: an owner request, an architect's supplemental instruction or bulletin, an RFI answer, a field condition report.
Description and reason
What changes in the work, in the terms of the drawings and specifications, and why. A reviewer should understand the change without opening another file.
Item, quantity, unit
One line per element of the change, measured like the original estimate.
Labor, material, equipment, subcontract
The cost of each line by type. Keeping them apart is what lets the owner check rates and quantities against the contract's unit prices or rates.
Overhead, profit and bond
The rates your contract allows on changes, entered once, applied to the subtotal.
Contract sum before and after
The original sum, the net of previous change orders, this change, and the new contract sum.
Contract time change
Days added or removed, and the new substantial completion date.
Change order log
One row per change order with its status (Pending, Approved, Rejected or Void), the amount requested and approved, the days, and a running contract sum that moves with approved changes only.

How to use it

  1. Describe the change and what originated it: an owner request, an architect's bulletin, an RFI answer or a field condition.
  2. Price it line by line in labor, material, equipment and subcontract.
  3. Apply the overhead, profit and bond rates your contract allows.
  4. Show the new contract sum and the change in contract time, and have it signed before the work proceeds, as your contract requires.
  5. Record it in the log; the running contract sum moves with approved changes only.

Limits

  • A generic working document: it does not reproduce any standard form, such as the AIA G701 change order. AIA and G701 are trademarks of The American Institute of Architects; this template is not affiliated with the AIA.
  • AIA's own summary describes G701-2017 as the form for changes agreed by the owner, the contractor and the architect, whose signatures record agreement on all the terms of the change, including any change in the contract sum (or guaranteed maximum price) and the contract time. The Change order sheet records the same elements; where your contract names G701, sign the AIA form.
  • Your contract decides which form is used, who signs and which markups are allowed. Every rate is left empty.

A worked example

Change order 007, originated by RFI 014 (duct reroute at grid C/4). Labor 1,120 (16 hours at 70), material 610 (fittings and insulation), equipment 0, subcontract 0: subtotal 1,730. Overhead 10%, profit 5% and bond 1% on the subtotal add 276.80: total 2,006.80. Original contract sum 4,250,000, previous change orders +38,400, new contract sum 4,290,406.80. Contract time: no change.

In the log, change order 007 is entered as Pending with 2,006.80 requested. The running contract sum does not move until the owner approves it; if the owner approves 1,900 after negotiation, that is the figure entered in the approved column.

Mistakes to avoid

  • Proceeding with changed work on a verbal instruction. Most contracts require a written change order or directive first, and an unsigned change is hard to recover later.
  • Pricing a change without the time. A change that adds work on the critical path adds days, and the time claim is usually lost if it is not made with the price.
  • Applying markups the contract does not allow, or compounding them when the contract says otherwise.
  • One change order for several unrelated changes. Each should be reviewable and approvable on its own.
  • Counting pending change orders in the contract sum. The running total moves with approved changes only.
  • Pricing a deductive change like an addition. Enter the deleted work as negative amounts, so the total and the new contract sum fall, and credit overhead, profit and bond only where the contract gives them back.

Questions

  • A written agreement, signed after the contract, that changes the work, the contract sum, the contract time, or several of them. It records what changed, why, and what it costs.

  • Its number and date, the project and contract, a description of the change and what originated it, the price broken down by cost type with the agreed markups, the new contract sum, the change in contract time, and the signatures of the parties.

  • A change order records a change the parties have agreed on, price and time included. A construction change directive, as AIA contracts call it, orders a change before price or time is agreed, so the work can proceed while they are settled.

  • The parties the contract names, typically the owner and the contractor, and under AIA-style contracts the architect as well.

  • Usually, at the rates the contract allows. Many contracts set those rates or cap them; the template leaves them empty for that reason.

  • As long as the contract and the parties allow: some contracts set a response period for the owner, many do not. What shortens it is a complete package: a clear description, the originating document, a priced breakdown the owner can check against contract rates, and the time impact supported by the schedule. Incomplete change orders come back with questions, and each round trip adds a week.

  • One priced and agreed before the work is done, as opposed to time-and-materials, where the work is recorded as it happens and priced afterwards. Forward pricing gives the owner certainty and the contractor the risk; time-and-materials needs daily tickets signed by the owner's representative.

  • No. G701-2017 is the AIA's own form, which its summary describes as the form for changes agreed by the owner, the contractor and the architect, recording any change in the contract sum (or guaranteed maximum price) and the contract time. This template records the same elements in a sheet of its own. Where your contract names G701, sign the AIA form.

  • One row per change order: its number and date, a description, the document that originated it, its status (Pending, Approved, Rejected or Void in this template), the amount requested and the amount approved, and the days. The running contract sum moves with approved amounts only, so a pending or rejected change never reads as part of the contract sum.

  • Enter the deleted work as negative amounts in the cost columns. The line totals, the subtotal, the markups and the total of this change come out negative, and the new contract sum falls by that amount; in the log, the approved credit is a negative amount. Whether overhead, profit and bond are credited back is for your contract to say: if it gives none back, leave the three rates empty on that change order.

Changes traced to their source

This template prices a change you have already identified. Mirage deploys AI agents that tie each change back to the drawings, specification clauses, contract scope and quantities that created it, for your team to review.