Schedule of Values Template (Excel)
A free Excel schedule of values and payment application for contractors: the contract sum broken into line items, work completed and materials stored each period, retainage at your contract's rates, the balance to finish and the current payment due.
Download the Excel templateFree, no sign-up. Opens in Excel, Google Sheets and LibreOffice.
Mirage does this work from your own documents. See pay application automation
Who uses it, and when
Contractors' project managers and accountants prepare the schedule of values at the start of the job and update it every pay period; the owner's representative and the architect review it and certify the payment. Subcontractors submit their own schedule of values to the general contractor in the same form.
Lenders and their inspectors use the same sheet to release construction loan draws: they compare the percent complete on each line with what they see on site, which is why a clear, honest breakdown gets paid faster.
What is in the file
- Schedule of values
- The header with the retainage rates for work and for stored materials, then one row per line item: item number, description, scheduled value, the amount from previous applications, work this period, materials presently stored, and, computed, total completed and stored, percent complete, balance to finish and retainage. A line billed above its scheduled value turns red.
- Application
- Contract sum to date (original plus change orders), total completed and stored, retainage, total earned less retainage, previous certificates, the current payment due and the balance to finish, with a check that the schedule total equals the contract sum.
- Instructions
- How to fill it, step by step.
Column by column
- Item no. and description
- One line per meaningful part of the work, often by specification section or by trade and area. Separate labor and material lines where the owner asks for them.
- Scheduled value
- The value of the line. All lines add up to the contract sum to date; change orders are added as new lines.
- From previous applications
- The total completed and stored on the previous application, for this line.
- This period
- The value of work completed on the line since the last application.
- Materials presently stored
- Materials delivered and stored, on site or off site as the contract allows, not yet installed.
- Total completed and stored to date
- Computed: previous plus this period plus stored.
- % complete and balance to finish
- Computed: total to date over scheduled value, and what is left to bill.
- Retainage
- Computed with the rates in the header: one rate on work, another on stored materials, as many contracts distinguish them.
How to use it
- Enter the retainage rates your contract sets for work and for stored materials, and the period covered.
- Break the contract sum into line items with a scheduled value each, and have the owner accept the breakdown before the first application.
- Each period, enter the work completed this period and the materials stored for every line; copy last period's totals into 'from previous applications'.
- On the Application sheet, enter the original contract sum, the net change by change orders and the previous certificates: the current payment due computes.
- Check the line the Application sheet adds: the schedule total must equal the contract sum to date.
Limits
- A generic working document: it does not reproduce any standard form, such as the AIA G702 and G703, and is not affiliated with the American Institute of Architects. The owner's contract decides which form is submitted.
- Retainage is computed at a flat rate per category. Contracts that reduce retainage at 50% completion, or hold it per subcontract, need the formulas adjusted.
- The template computes what is due; lien waivers, certified payroll and other attachments the contract requires are separate.
A worked example
Line 03 30 00, cast-in-place concrete, scheduled value 450,000. Previous applications 180,000, this period 90,000, materials stored 15,000 (rebar on site). Total completed and stored 285,000, 63.3% complete, balance to finish 165,000. With 10% retainage on work and 10% on stored materials, retainage on the line is 28,500.
With a contract sum to date of 4,288,400 and total completed and stored of 1,940,000 across all lines, retainage is 194,000, earned less retainage 1,746,000; previous certificates 1,420,000; current payment due 326,000.
Mistakes to avoid
- Front-loading: inflating early lines to bill ahead of progress. Owners and lenders see it, and it costs trust and later payments.
- Lumping a whole trade into one line. A line nobody can measure is a line the owner's representative will hold back.
- Adding change orders by changing existing scheduled values instead of adding lines. The original contract and the changes should stay readable.
- Billing stored materials without the documents the contract asks for: invoices, insurance, proof of storage location.
- Forgetting to carry last period's totals forward. The previous-applications column must match the last certified application exactly.
Questions
What is a schedule of values in construction?
The breakdown of the contract sum into line items with a value each, used on every payment application to report progress line by line. It is agreed with the owner before the first payment.
How is percent complete calculated?
Total completed and stored to date on the line divided by its scheduled value. It is a measure of value earned, not of time elapsed.
What is retainage?
A percentage of each payment the owner withholds until completion, as security for completing the work and correcting defects. Rates of 5% to 10% are common; some contracts and some public owners set lower caps or reduce it at a milestone.
Can stored materials be billed?
Often yes, when the contract allows it and the contractor provides proof of ownership, insurance and storage. Off-site storage usually needs the owner's prior approval.
Is this the AIA G702 and G703?
No. It follows the same arithmetic as a continuation sheet and application for payment, as most pay applications do, but it is a generic working document. Use the form your contract specifies for submission.