Schedule of Values Template (Excel)
A free Excel schedule of values and payment application for contractors: the contract sum broken into line items, work completed and materials stored each period, retainage at your contract's rates, the balance to finish and the current payment due. A second sheet pays unit-price contracts on measured quantities, with the source of each quantity.
Download the Excel templateFree, no sign-up. Opens in Excel, Google Sheets and LibreOffice.
Mirage does this work from your own documents. See pay application automation
What the template looks like
The two main sheets with their own columns, filled with the worked example further down this page. The file you download is empty: every value and rate is yours to enter.
| Item no. | Description of work | Scheduled value | From previous applications | This period | Materials presently stored | Total completed and stored to date | % complete | Balance to finish | Retainage |
|---|---|---|---|---|---|---|---|---|---|
| 03 30 00 | Cast-in-place concrete | 450,000.00 | 180,000.00 | 90,000.00 | 15,000.00 | 285,000.00 | 63.3% | 165,000.00 | 28,500.00 |
| Line | Amount |
|---|---|
| Contract sum to date | 4,288,400.00 |
| Total completed and stored to date | 1,940,000.00 |
| Retainage | 194,000.00 |
| Total earned less retainage | 1,746,000.00 |
| Less previous certificates for payment | 1,420,000.00 |
| Current payment due | 326,000.00 |
| Balance to finish, including retainage | 2,542,400.00 |
Who uses it, and when
Contractors' project managers and accountants prepare the schedule of values at the start of the job and update it every pay period; the owner's representative and the architect review it and certify the payment. Subcontractors submit their own schedule of values to the general contractor in the same form.
Lenders and their inspectors use the same sheet to release construction loan draws: they compare the percent complete on each line with what they see on site, which is why a clear, honest breakdown gets paid faster.
What is in the file
- Schedule of values
- The header with the retainage rates for work and for stored materials, then one row per line item: item number, description, scheduled value, the amount from previous applications, work this period, materials presently stored, and, computed, total completed and stored, percent complete, balance to finish and retainage. A line billed above its scheduled value turns red.
- Application
- Contract sum to date (original plus change orders), total completed and stored, retainage, total earned less retainage, previous certificates, the current payment due and the balance to finish, with a check that the schedule total equals the contract sum.
- Unit price
- For unit-price contracts (heavy civil, highway, most public works): one row per bid item with its unit, contract quantity and unit price, then each period the quantity previous, the quantity this period and its source (daily report, survey, load tickets, sheet number). Computed: contract amount, quantity to date, percent of contract quantity, amount this period and to date. An item over its contract quantity turns amber; a quantity billed with no source turns red.
- Unit price certificate
- Amount earned to date and this period, retainage at your rate, previous certificates and the current payment due, with a count of items over their contract quantity and of quantities billed without a source.
- Instructions
- How to fill it, step by step.
Column by column
- Item no. and description
- One line per meaningful part of the work, often by specification section or by trade and area. Separate labor and material lines where the owner asks for them.
- Scheduled value
- The value of the line. All lines add up to the contract sum to date; change orders are added as new lines.
- From previous applications
- The work completed on this line up to the last application: that application's 'from previous applications' plus its 'this period'. Stored materials are not carried here: those still stored are entered again under materials presently stored, and once installed they are billed as work this period.
- This period
- The value of work completed on the line since the last application.
- Materials presently stored
- Materials delivered and stored, on site or off site as the contract allows, not yet installed.
- Total completed and stored to date
- Computed: previous plus this period plus stored.
- % complete and balance to finish
- Computed: total to date over scheduled value, and what is left to bill.
- Retainage
- Computed with the rates in the header: one rate on work, another on stored materials, as many contracts distinguish them.
How to use it
- Enter the retainage rates your contract sets for work and for stored materials (the cells are empty: no rate is assumed), and the period covered.
- Break the contract sum into line items with a scheduled value each, and have the owner accept the breakdown before the first application.
- Each period, enter the work completed this period and the materials presently stored for every line; into 'from previous applications', carry last period's previous plus this-period amounts, without its stored materials.
- On the Application sheet, enter the original contract sum, the net change by change orders and the previous certificates: the current payment due computes.
- Check the line the Application sheet adds: the schedule total must equal the contract sum to date.
- On a unit-price contract, fill the Unit price sheet instead: the bid items with their units, quantities and unit prices, then each period the quantity measured and where it was measured. The Unit price certificate sheet gives the payment due.
Limits
- A generic working document: it does not reproduce any standard form, such as the AIA G702 and G703, and is not affiliated with the American Institute of Architects. The owner's contract decides which form is submitted.
- Retainage is computed at a flat rate per category. Contracts that reduce retainage at 50% completion, or hold it per subcontract, need the formulas adjusted.
- The template computes what is due; lien waivers, certified payroll and other attachments the contract requires are separate.
A worked example
Line 03 30 00, cast-in-place concrete, scheduled value 450,000. Previous applications 180,000, this period 90,000, materials stored 15,000 (rebar on site). Total completed and stored 285,000, 63.3% complete, balance to finish 165,000. With 10% retainage on work and 10% on stored materials, retainage on the line is 28,500.
With a contract sum to date of 4,288,400 and total completed and stored of 1,940,000 across all lines, retainage is 194,000, earned less retainage 1,746,000; previous certificates 1,420,000; current payment due 326,000.
Mistakes to avoid
- Front-loading: inflating early lines to bill ahead of progress. Owners and lenders see it, and it costs trust and later payments.
- Lumping a whole trade into one line. A line nobody can measure is a line the owner's representative will hold back.
- Adding change orders by changing existing scheduled values instead of adding lines. The original contract and the changes should stay readable.
- Billing stored materials without the documents the contract asks for: invoices, insurance, proof of storage location.
- Carrying last period's stored materials into 'from previous applications'. They are counted again as presently stored or, once installed, as work this period, so carrying them forward bills them twice.
- Forgetting to carry last period's work forward. The previous-applications column must match the work completed on the last certified application exactly.
Questions
The breakdown of the contract sum into line items with a value each, used on every payment application to report progress line by line. It is agreed with the owner before the first payment.
Total completed and stored to date on the line divided by its scheduled value. It is a measure of value earned, not of time elapsed.
A percentage of each payment the owner withholds until completion, as security for completing the work and correcting defects. Rates of 5% to 10% are common; some contracts and some public owners set lower caps or reduce it at a milestone.
Often yes, when the contract allows it and the contractor provides proof of ownership, insurance and storage. Off-site storage usually needs the owner's prior approval.
Each bid item is paid on the quantity actually measured, at its unit price: quantity this period times unit price, added to what earlier estimates paid. The contract's specifications say how each item is measured. The Unit price sheet keeps the source of every quantity, so the owner's inspector can check it against the field records, and marks any item that runs past its contract quantity.
No. It follows the same arithmetic as a continuation sheet and application for payment, as most pay applications do, but it is a generic working document. Use the form your contract specifies for submission.