How to Level Subcontractor Bids: Scope Gaps, Exclusions and a Worked Comparison

The lowest subcontractor bid on paper is often the one that left the most out. Leveling puts every bid on the same scope before you compare them: your scope sheet first, then each exclusion and each silence priced with a plug you can trace, bond and tax added where a bid left them out, overlaps with other packages removed, and a ranking that says whether it is final or still waiting on answers. This guide gives the method and a worked comparison of three drywall bids in which the lowest base bid is not the lowest leveled one.

Published
Sources checked
Reading time
16 min
Written by
Mirage Metrics team

Scope: subcontractor bids for one bid package at a general contractor in the United States or Canada, from bid day to the subcontract scope letter. It covers the method, done by hand, in a spreadsheet or in the free calculator; it does not cover prequalification or the choice of software.

Decision snapshot

Best suited to
Chief estimators, preconstruction managers and subcontract buyers at general contractors who receive three or more bids per package and have to carry one number in their own bid, then award.
Inputs needed
The package's drawings, specification sections and addenda; your takeoff and estimate; every bid as submitted, with its letter, breakdown, alternates and the addenda it acknowledges; the subcontract's bond, tax and insurance requirements.
What can be automated
Reading each bid against the scope sheet, marking exclusions and silence with the page they come from, extending unit prices with your quantities, adding plugs, bond and tax, and re-running the comparison each time an answer comes in.
What requires human approval
The scope sheet itself, every plug value and its basis, the package boundaries, the questions on the scope review call, and the award.
When this approach is insufficient
When the scope is not defined well enough to write a scope sheet (early design), when bids are for different means and methods that cannot be put on one scope, or when only one bid came in: then you are pricing a scope, not leveling bids.

Build the leveling scope before the bids arrive

Leveling measures every bid against one scope, and that scope has to be yours. Write a scope sheet for each bid package before bids come in, from the package's drawings, its specification sections and every addendum issued, not from the first bid letter that lands. A scope sheet copied from the lowest bidder's letter has, by construction, the same holes as that letter.

Columns of a scope sheet for one bid package
ColumnWhat goes in itWhy
Scope itemOne line per element of the package, written from the drawings, the specification sections and every addendumThe scope is yours; each bid is measured against it, never the other way round
Spec section and drawingThe section that specifies the item and the sheet that shows itWhat you quote on the scope review call, and what settles a dispute after award
Quantity and unitFrom your takeoffLets you extend a unit price bid and check a lump sum line against what it should cover
Package ownerThis package, another package (named), or the GC's own workThe line that exposes gaps and overlaps between packages
Plug valueWhat you would carry for the item if a bidder leaves it outTurns an exclusion into a number
Plug basis and sourceOwn estimate, a bidder's firm add or alternate, another bid, a separate quote, an allowance; and the line or page it came fromA plug nobody can trace is an opinion
Columns of a scope sheet for one bid package

Two habits make the sheet useful on bid day. Put on it the items that sit on a package boundary (firestopping, blocking, hoisting, cleanup), because those are where bids differ. And write the plug values before you open the bids, so the price of an item is not influenced by which bidder left it out. The bid leveling template has these columns, with the plug basis and source next to every value.

The scope sheet is also the bid form you wish you had sent. Issuing it with the invitation to bid, as a list subcontractors confirm line by line, does not remove the need to level, but it turns most of the reading into checking boxes.

Read bids written three different ways

Bids for the same package rarely arrive in the same shape. Before anything can be compared, each one has to be brought to a single number for the scope it actually covers, and the way to get there depends on the format.

Bid formats, what to watch for, and the number to start from
FormatWhat it looks likeHow to read itNumber to start from
Lump sum with an inclusions and exclusions letterOne price, then paragraphs of inclusions, exclusions and qualificationsRead every paragraph against the scope sheet; the price says nothing about what is in itBase bid as submitted
Unit pricesA rate per unit for each line, sometimes extended on the bidder's own quantitiesExtend every rate with your quantities, not the bidder's; a line with no rate is silence, not zeroThe extension on your quantities
Base bid with alternatesA base price, plus adds and deducts for options the bid documents asked for or the bidder volunteeredTake the alternates your scope includes, ignore the ones it does not, keep voluntary alternates out of the comparisonBase bid, with a scope alternate entered as a plug at the bidder's own price
Bid with allowancesA fixed sum inside the price for work not yet definedMake every bid carry the same allowance, or noneBase bid, adjusted so allowances match
Bid formats, what to watch for, and the number to start from

Unit prices: extend them with your quantities

A unit price bid usually comes with the bidder's own extension. Do not use it. Multiply each rate by your takeoff quantity, so every bid is priced on the same quantities, and note the difference: a bidder whose quantities are well below yours has either found something in the drawings or missed something, and both are questions for the call. A line on your scope sheet with no rate on the form is silence, not a zero.

Alternates: only the ones your scope includes

When your scope includes an item that a bid prices as an alternate (the bid's base is level 4 finish, your scope says level 5), the alternate is a gap in the base bid, and the bidder's own alternate price is the plug for it. Alternates your scope does not call for stay out of the comparison, and voluntary alternates (a cheaper product, a different method) are judged on their own, after leveling, because they change the scope rather than price it.

Exclusions, silence and qualifications

Read each bid letter paragraph by paragraph against the scope sheet, and give every line of the sheet a status for every bidder. Most exclusions sit in the last paragraphs, and the most expensive ones are often not exclusions at all but things the bid never mentions.

What a bid can say about a scope item, how to treat it, and what to record
What you findExampleTreatmentWhat to record
Stated exclusion"Firestopping by others", "hoisting by GC"Excluded: add the plugWhere the bid says it: page and clause
SilenceThe bid neither includes nor excludes an item on your scope sheetClarify: carry the plug until the bidder confirms in writingAsk it on the scope review call
Not pricedA unit price form with an empty line, or "TBD"Excluded, at the plug, until a price comes inAsk for the price in writing
Addendum not acknowledgedThe bid lists addenda 1 and 2; there were threeClarify, carrying the value of what addendum 3 changed for that packageAsk whether the price includes it
Extra scopeThe bidder priced work another package carries, or that nobody asked forDeduct it, if the bid lets you value itNote what it is and where the bid prices it
QualificationPrice valid 30 days, work in two mobilizations, escalation clause on studsNo plug; it goes to the award decisionRecord it next to the bidder
What a bid can say about a scope item, how to treat it, and what to record

The rule that matters most: silence is not inclusion. A bid that does not mention shaft wall has not promised to build it. Carry the plug until the bidder confirms in writing, and keep the item on the open list. Treating silence as included is how a low bid wins the comparison and comes back as a change order.

Exclusion or qualification

An exclusion removes an item from the price, so it gets a plug. A qualification sets a condition on the price (validity, mobilizations, escalation, working hours), so it is recorded and weighed at award, and priced only if the bid prices it.

Overlaps and gaps between packages

A package is one slice of a project, and its edges are where money goes missing or is paid twice. A gap is an item no package carries: every bidder excluded it, so the comparison between them is unaffected, but your own estimate is short by its value. An overlap is an item two packages carry: the bidder who priced it looks expensive, and you would buy it twice.

Items that commonly sit on a package boundary
ItemWhere it may sitHow the gap or overlap appears
Firestopping at penetrations and head-of-wall jointsDrywall, each MEP trade for its own penetrations, or a firestopping specialistTwo packages price it, or each assumes the other does
In-wall blocking for wall-mounted itemsRough carpentry or drywallSpecified in a carpentry section, installed inside drywall partitions
Access panelsSupplied by the trade that needs access, installed by drywallSupply and install split between two packages
Acoustical ceilings at corridorsCeilings package or drywallA drywall bidder prices them along with the soffits
Hoisting, cleanup, layout, temporary protectionEach sub, or the GC's general conditionsBid instructions silent; every bidder assumes differently
Items that commonly sit on a package boundary

The scope sheet's package owner column settles each one: every item on a boundary belongs to exactly one package. Then an exclusion of an item your scope gives to this package gets a plug, an item priced here that belongs to another package is deducted from the bid that priced it (when the bid lets you value it), and an item every bidder excluded is a line in your own estimate, not an adjustment between bidders.

Plug pricing: who sets the plug, from what

A plug is the amount the general contractor carries for an item a bid leaves out. It is the GC's number, so the GC sets it: in most estimating departments the estimator who owns the package proposes it and the chief estimator approves it, before award and ideally before the bids are opened. It is an assumption, which is why each one needs a basis and a source someone else can check.

Where a plug value can come from, when to use it, and its risk
BasisWhen to use itStrengthWatch out for
A firm add or alternate from the bidder itselfThe bid prices the item separately, as an add or an alternateThe best plug for that bidder's own gap: it is a price it will signOnly for that bidder; it says nothing about the others
A separate quoteA specialist quoted the item on its own (firestopping, shaft wall)A market price for exactly that scopeCheck it covers the same scope and conditions
Your own estimateYou measured the item and priced it in your estimateIndependent of the bidders, consistent across themOnly as good as the estimate line; note which line
Another bidder's priceAnother bid prices the item as a separate lineReal, current, same projectNot usable when the item is buried in a lump sum; the lowest such price favors the bid that left it out
AllowanceThe item cannot be priced yetKeeps the item visibleA placeholder; carry the same allowance on every bid
Where a plug value can come from, when to use it, and its risk

A plug that is too low favors the bid that excluded the item, and a plug that is too high punishes it. Two checks keep plugs honest. First, a plug only matters where bids differ: if every bidder excluded hoisting, the hoisting plug moves none of them against the others. Second, before award, compare the leveled difference between the first two bids with the plugs that only one of them carries: if a plausible error in one of those plugs could close the gap, get a firm price for that item before deciding. The worked example below shows both.

Sales tax, bonds, insurance and conditions

Some differences between bids are not scope but cost carried by one bidder and not by another. Each one is answered for every bid (included or not), and added to the bids that left it out.

Costs and conditions to put on the same basis across bids
ItemWhat to establish for each bidLeveling treatmentGoverned by
Sales taxWhether it is included, and on what: materials only or the whole priceAdd tax to the bids that left it out, on the same base the others carry, at the rate your jurisdiction applies to that contractPer your contract and jurisdiction
Performance and payment bondsWhether the bid includes them, and the bidder's quoted rate if notAdd the bond cost to the bids that left it outPer your subcontract and bid instructions; federal work below
InsuranceWhether the bidder can meet the subcontract's limits and endorsements, or prices on a wrap-up basisUsually not a dollar adjustment: a bidder that cannot comply is a qualification for the awardPer your subcontract
Schedule and conditionsDuration, crew size, start date, number of mobilizations, price validity, escalation clausesRecorded as qualifications, priced only when the bid prices themPer your bid documents
Costs and conditions to put on the same basis across bids

Sales tax

Whether sales tax applies to a subcontract, and whether to the materials or to the whole price, depends on the state or province and on the type of contract. Do not settle it in the leveling sheet: establish it for your project, then ask each bidder whether its price includes tax and on what base, and add the missing amount on that base. In the bid leveling calculator, a taxable amount field takes the materials total of a bidder's breakdown when tax applies to materials only.

Bonds

On federal work, the Miller Act requires the prime contractor to furnish a performance bond and a payment bond before award of a construction contract of more than $100,000 (40 U.S.C. 3131), and the Federal Acquisition Regulation applies the requirement to construction contracts exceeding $150,000 (FAR 28.102-1). Those rules bind the prime contractor. Whether you require bonds from subcontractors, and in what amount, is set by your subcontract and bid instructions, and on state and local public work by the owner's contract and the bonding law that governs it. For leveling, what counts is consistency: if one bid includes its bond and another quotes it as an add, add that bidder's quoted rate, or your surety's, to the second.

Insurance, schedule and conditions

Insurance is rarely a dollar adjustment. Check that every bidder can meet the subcontract's limits and endorsements, and if the project has a wrap-up insurance program, that every bid is priced on the same basis. Duration, crew size, mobilizations, price validity and escalation clauses are recorded next to each bid and weighed at award; they become a number only when the bid prices them.

Worked comparison: three drywall bids

Illustrative example, invented figures: a drywall and framing package on a commercial building

Assumptions, all invented. The package covers gypsum board assemblies and non-structural metal framing. The subcontract requires a performance and payment bond. Sales tax in this invented jurisdiction applies to the materials in a subcontract, at 7 percent; use your own jurisdiction's rule and rate. Section numbers follow MasterFormat numbering, as a project manual would.

1. The scope sheet, written before bid day

Scope sheet for the drywall package, with plug values and their sources (invented)
Scope itemSpec section and drawingPlug $Plug basis and source
Partitions, soffits and ceilings per partition types09 21 16, 09 22 16; A-401, A-501All three bids include it
Firestopping at rated partitions07 84 00; A-50118,400Own estimate, from the takeoff count
Level 5 finish, lobby and corridors09 21 16; finish schedule A-6019,600Bidder C's Alternate 1, a firm add
Shaft wall at two elevator shafts09 21 16.23; A-40121,500Own estimate: 1,720 SF at 12.50
In-wall wood blocking06 10 53, assigned to this package by the scope sheet7,200Own estimate, from the takeoff
Hoisting and material distributionBid instructions14,000Own estimate, general conditions sheet
Daily cleanup to GC dumpstersBid instructions6,500Own estimate, general conditions sheet
Scope sheet for the drywall package, with plug values and their sources (invented)

Blocking is specified in a carpentry section, but the scope sheet assigns it to this package, and the bid instructions say so. Acoustical ceilings belong to the ceilings package.

2. Bidder B's unit prices, extended with your quantities

Bidder B's unit prices extended on your takeoff quantities (invented)
Line on B's unit price formYour quantityB's rate $Extension $B's own quantity
Partition type P138,400 SF11.25432,00038,100 SF
Rated partition type P39,800 SF16.40160,7209,800 SF
Ceilings and soffits4,100 SF8.7035,6704,100 SF
Total628,390B's own total: 625,015
Bidder B's unit prices extended on your takeoff quantities (invented)

B's own total, 625,015, used 300 SF less of partition type P1 (300 x 11.25 = 3,375). The comparison uses 628,390, and the quantity difference goes on the call list.

3. What each bid says

The three bids as submitted, with their exclusions and conditions (invented)
BidderStructureBase as submitted $What the bid says
ALump sum and a two-page letter612,000Excludes firestopping (p. 2, exclusion 4) and hoisting (exclusion 7). Bond not included: "performance and payment bond available, add 1.1%". Sales tax included. Price valid 30 days.
BUnit prices628,390 (extended on your quantities)Excludes blocking (clarification 3: "by carpentry"). No line for shaft wall: silent. Bond included. Sales tax excluded; its breakdown shows 236,000 of materials.
CBase bid with alternates589,000Base at level 4 finish; Alternate 1 adds level 5 for 9,600; Alternate 2 deducts 4,200 for level 3 in back-of-house areas, which the scope does not call for. Excludes firestopping, shaft wall and hoisting (exclusions 2, 5, 6). Silent on cleanup. Prices acoustical ceiling tile at corridors, 12,400 (breakdown line 7), which is in the ceilings package. Bond included. Sales tax excluded; 220,000 of materials.
The three bids as submitted, with their exclusions and conditions (invented)

4. The leveled comparison on bid day

Bond for A is added at its own quoted rate, 1.1 percent of 612,000 = 6,732. Tax is 7 percent of the materials each bid shows: 16,520 for B, 15,400 for C. C's Alternate 1 (level 5) is a plug at C's own price. C's corridor ceilings, 12,400, are deducted because the ceilings package carries them. The two silent items are carried at their plugs.

Leveled comparison on bid day, in dollars, provisional (invented)
BidderBase bidPlugs for exclusionsCarried for open itemsBond addedTax addedExtra scope deductedLeveled totalIf open items are includedOpen clarifications
A612,00032,40006,73200651,132651,132None priced; price valid 30 days
B628,3907,20021,500016,5200673,610652,110Shaft wall: silent
C589,00063,5006,500015,400−12,400662,000655,500Cleanup: silent
Leveled comparison on bid day, in dollars, provisional (invented)
  • A: 612,000 + 18,400 firestopping + 14,000 hoisting + 6,732 bond = 651,132.
  • B: 628,390 + 7,200 blocking + 21,500 shaft wall carried + 16,520 tax = 673,610; 652,110 if shaft wall turns out included.
  • C: 589,000 + 18,400 + 9,600 + 21,500 + 14,000 (firestopping, level 5, shaft wall, hoisting) + 6,500 cleanup carried + 15,400 tax − 12,400 ceilings = 662,000; 655,500 if cleanup turns out included.

C, the lowest bid as submitted by 23,000, is second once leveled. A is lowest at 651,132, and the ranking is provisional: two items are still open. Yet A stays lowest whatever the answers are, because its total is below the best case of both other bids (652,110 and 655,500). The order of B and C, on the other hand, depends on the answers.

5. Which plugs decide it

Firestopping and hoisting are excluded by both A and C, so their plugs move neither against the other. What separates them is what only one carries: C's shaft wall plug (21,500), its level 5 alternate (9,600, a firm price), C's tax against A's bond, and C's ceiling deduct. After the clarifications below, A leads C by 4,368. If the shaft wall plug were too high by more than that, that is if shaft wall really cost less than 17,132, C would be lowest. Before award, a shaft wall quote you can rely on is worth more than any other check.

To run this example yourself, open the bid leveling calculator and use "Fill in the worked example": it loads these inputs, with the bid references, and gives the same totals, the same provisional status and a CSV of the table and its assumptions.

Clarifications: the scope review call and the written answer

Every open item becomes a question to one bidder, and the answer has to reach the file in writing: an email, a revised bid letter, or signed minutes of the call. A verbal "yes, it is in there" changes nothing in the comparison.

  • Walk the scope sheet line by line with each bidder, in the same order for all of them
  • Ask about every exclusion, every silent item and every quantity that differs from yours, quoting the page and clause
  • Confirm the addenda the price includes, by number and date
  • Confirm bond, sales tax and insurance: included or not, and on what base
  • Ask for a price on any excluded item you might want the bidder to carry, as a firm add
  • Keep every bidder's price confidential: the call is about scope
  • Get the answers in writing and attach them to the bid in the file
  • Change each item's status from Clarify to Included or Excluded, and re-run the comparison

Provisional and final leveling

On bid day the comparison is provisional, and it should look provisional. Each bid with an open item is really a range: the leveled total with the open items carried at their plugs, and a best case if they all turn out included. Three situations follow.

  • The lowest holds whatever the answers are when its total is not above any other bid's best case. You can carry it in your own bid, and say the leveling is provisional.
  • The answers can change the lowest when another bid's best case is below it. Do not name a lowest bid yet; settle the open items that decide it first.
  • A bid with an unknown amount (an excluded item with no plug, a bond left out with no rate) cannot be ranked at all: ranking it would count the unknown as zero. Its known total is only a floor.

The calculator and the template apply these three rules and say which one the comparison is in. In the example, the written answers come back: B confirms that its unit prices do not include shaft wall, C confirms that cleanup is included, and A extends its price validity to the award date.

Final leveled comparison after the written answers, in dollars (invented)
BidderAnswer in writingFinal leveled totalRankOver lowest
AConfirms bid validity extended to award date651,13210
CDaily cleanup is included655,50024,368
BShaft wall is not included673,610322,478
Final leveled comparison after the written answers, in dollars (invented)

B's shaft wall moves from carried to excluded at the same plug, so its total does not change; C loses the 6,500 it was carrying. Nothing is open: the ranking is final, and A leads by 4,368.

Handing the decision to the estimate and the award

The leveled comparison feeds two documents, and each takes something different from it.

The estimate

Your own bid carries the bidder you expect to buy, at its subcontract price, plus every plug for what that bidder does not carry, as separate lines you will buy elsewhere or do yourself. In the example, with A: the subcontract at 612,000 plus its bond at 6,732, and firestopping (18,400) and hoisting (14,000) as their own lines, together the 651,132 of the comparison. Items every bidder excluded are estimate lines too, or they are missing from your price.

The subcontract scope letter

The award turns the comparison into the subcontract's scope. The scope letter, or scope exhibit, lists what was confirmed included, what was accepted as excluded, the alternates taken, the addenda and bid documents the price is based on, and attaches the written clarifications. Every Clarify item has to be settled in it: an open question left out of the scope letter is the first change order of the job.

Keep the comparison itself in the file with its plug sources and bid references. The calculator's CSV export and the template both keep them, so the award can be explained months later by someone who was not in the room.

Where Mirage fits

Mirage deploys AI agents that do the reading part of this method: they read each subcontractor bid in the format it arrives in, map its lines to your scope sheet, mark exclusions and silent items with the page they come from, and prepare the comparison for your estimators, who set the plugs, run the calls and decide. Connections to your estimating or document systems are possible, to be configured and validated on your tools. See AI bid leveling for construction for that workflow; the method on this page works the same by hand.

Questions readers ask

Sources and scope

Checked on . Scope: subcontractor bid leveling at a general contractor in North America. The method and the worked example are Mirage's own, with invented figures; the only rules cited are the federal bond requirements. Sales tax, state bonding and insurance requirements are left to your contract and jurisdiction.

Related on this site

Send us the bids for one package

Send the bids you received for one package, with the drawings and specification sections that define it. We will return a comparison with every bid mapped to the scope, each exclusion and silent item marked with the page it comes from, and the questions to settle before award, for your estimators to check against their own leveling.

Prefer to talk it through? Book a call

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy