Free tools / Construction

Bid leveling calculator

Enter three to six subcontractor bids for one scope package, mark which scope items each bidder excluded or left unclear, give those items a plug value with its basis, add bond and tax where a bidder left them out, and read the leveled comparison: the same scope, priced by everyone, with what is still open.

Three drywall bids from the guide: a lump sum, a unit price bid and a bid with alternates. Replaces what you typed.

Scope items and plug values

One line per item of the package scope. The plug value is what you would carry for the item if a bidder left it out. Say where it comes from: a reviewer will ask.

Bidders

For a unit price bid, the bidder's unit prices extended with your own quantities.

What the bidder priced that you did not ask for, if you can value it from the bid.

Scope item 1: status per bidder
Scope item 2: status per bidder
Scope item 3: status per bidder

What the bidder priced that you did not ask for, if you can value it from the bid.

Scope item 1: status per bidder
Scope item 2: status per bidder
Scope item 3: status per bidder

What the bidder priced that you did not ask for, if you can value it from the bid.

Scope item 1: status per bidder
Scope item 2: status per bidder
Scope item 3: status per bidder
Bond and tax rates, for bids that left them out

Empty means unknown, not zero: a bid that left out its bond or tax stays incomplete until you enter a rate (0 if none applies).

Enter at least two base bids to compare them.

Send a bid package you have already leveled.

Our agents read the bids as they arrived and send you back each line matched to your scope, with exclusions and gaps flagged, to set against your own leveling. A note on the trade and the number of bidders is enough to start, with no file.

See bid leveling

Prefer to talk it through? Book a call

Document

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy

How to use it

  1. List the package scope one item per line, from the drawings, the specification sections and the addenda of the package, and give every item a plug value with its basis and source.
  2. Enter each bidder's base bid exactly as submitted, and say whether its bond and sales tax are included. For a unit price bid, extend its unit prices with your own quantities.
  3. For each item and each bidder, leave Included, or choose Excluded when the bid says so, or Clarify when the bid is silent or unclear. Note the page or clause.
  4. Enter the bond and tax rates you would add to a bid that left them out, and any extra scope you want to deduct.
  5. Read the status line first: final, provisional, or no lowest yet. Then the leveled bids, the open items to settle with each subcontractor, and download the comparison for the file.

The formula

leveled bid = base bid + Σ plug values of excluded items

+ Σ plug values of items to clarify (carried until confirmed)

+ base bid × bond rate (when bond is not included)

+ taxable amount × tax rate (when tax is not included)

− value of extra scope priced but not wanted

Leveling puts every bid on the same scope before comparing them. Each exclusion is replaced by the amount you would otherwise have to pay for the item; an item the bid is silent on is carried at its plug until the bidder confirms in writing that it is included; each cost one bidder carried and another did not (bond, tax) is added to the bid that left it out. A bid with an unknown amount (an excluded or unclear item without a plug value, a missing bond or tax rate) is incomplete: it is not ranked, because ranking it would count the unknown as zero. The lowest bid is named only when no open item can change it.

A worked example

Three drywall bids: A at 400,000 with everything included; B at 385,000 excluding demolition (plug 12,000) and hoisting (plug 8,500), bond not included at 1.5%, with 5,000 of extra scope you do not want; C at 410,000 with sales tax not included at 8% on the whole bid. B levels to 385,000 + 20,500 + 5,775 − 5,000 = 406,275. C levels to 410,000 + 32,800 = 442,800. A, the second lowest on paper, is the lowest leveled bid, 6,275 under B.

The guide to leveling subcontractor bids works through a longer example: a lump sum, a unit price bid and a bid with alternates, an overlap with another package, and two open clarifications that leave the ranking provisional. The button above the form fills it in.

Plugs, exclusions and what leveling does not do

Plug value
An assumption, not a price. Use your own estimate for the item, a separate quote, or a price a bidder committed to (its own add or alternate), and write down which. A plug that is too low favours the bid that excluded the item.
Basis and source
Every plug says where it comes from (estimate line, quote, alternate), and every exclusion where the bid states it (page, clause). The CSV export keeps both, so the comparison can be checked after award.
Exclusion
An item the bid names as not included. Read the letter, not the total: most exclusions are in the last paragraph.
Clarify
The bid does not say. The plug is carried until the subcontractor confirms in writing that the item is included, and the item stays on the open list. Never award with open items.
Provisional ranking
While items are open, a bid's total is a range: carried plugs at the top, everything confirmed included at the bottom. The lowest bid is named only when its carried total is not above any other bid's best case.
Extra scope
Something the bidder priced that is not in your package, such as work another package carries. Deduct it only if you can value it from the bid.
What leveling does not do
It does not judge qualifications, schedule, bonding capacity or safety record. It gives you the price for the same scope; the award weighs the rest.

FAQ

  • Adjusting each subcontractor bid to the same scope before comparing them: adding a plug value for every item a bidder excluded, adding the costs one bidder carried and another did not, and deducting scope you did not ask for. The lowest number on paper is often the bid that left the most out.

  • The amount the general contractor carries for an item a bidder excluded or did not price. It comes from the GC's own estimate, a separate quote, or a price a bidder committed to for the same item. Adding it to that bid puts all bids on the same scope.

  • Treat silence as an open question, not as inclusion. Mark the item Clarify: the calculator carries its plug, lists it as open and keeps the ranking provisional until the bidder confirms in writing.

  • Three is the usual minimum for a competitive package, and this calculator takes up to six. With two bids you can still level, but a single exclusion can decide the outcome, so read both letters twice.

  • Only to the bids that left them out. If one bidder included the bond in its price and another did not, adding the bond to the second makes them comparable. Use the rate your contract or your surety gives you, and the taxable amount your jurisdiction applies the tax to.

  • Not automatically. The leveled total tells you what each bid costs for the same scope. Qualifications, schedule, bonding capacity, safety record and past performance still decide the award.

A leveled comparison is only as good as the reading of each bid letter.

Mirage deploys AI agents that read subcontractor quotations in the format they arrive in, map every line to your scope and flag exclusions and gaps, for your estimators to review before award.

See AI bid leveling for construction