Bid Leveling Template (Excel)
A free Excel spreadsheet to level up to four subcontractor bids on one scope package: list the scope, mark what each bidder included, give excluded or unclear items a plug value with its source, add bond and tax where they were left out, and read a ranking that says whether it is final or still provisional.
Download the Excel templateFree, no sign-up. Opens in Excel, Google Sheets and LibreOffice.
Mirage does this work from your own documents. See AI bid leveling
Who uses it, and when
Project managers and estimators at general contractors use it on bid day, when three or four subcontractor quotes for the same package arrive in different formats, with different exclusions, and the team has to decide which one to carry in its own bid.
Construction managers and owner's representatives use the same sheet after award, to document why a bidder was selected: the plug sources and the bid references in the sheet are what let someone check the comparison months later.
What is in the file
- Leveling
- The package block and the bond and tax rates; the scope items with their specification section, quantity, plug value, plug basis and plug source; three columns per bidder: a status for each item (included, excluded, not priced, clarify or extra scope), the adjustment it causes and where the bid says it. Under them, the leveled comparison, one row per bidder: base bid, bond and tax answered Y or N, taxable amount, extra scope deducted, plugs, bond and tax added, leveled bid, best case if the items to clarify are included, missing values, open items, rank and difference to the lowest. Then the ranking status and the lowest leveled bid.
- Instructions
- How to fill it, step by step.
Column by column
- Scope item
- One line per element of the package scope, written from the drawings, the specification sections and the addenda of the package, not from any bidder's letter. The scope is yours; the bids are measured against it.
- Spec section, quantity, unit
- Where the item is specified and how much of it there is. They let you check a bidder's unit price against the quantity it should cover.
- Plug value, basis, source
- What you would carry for the item if a bidder left it out, where that number comes from (your estimate, the bidder's own add or alternate, another bidder's price, a separate quote, an allowance) and the line, quote or page it was taken from. A cell turns red when a bidder needs a plug that is still empty.
- Bidder status
- For each bidder and each item: Included, Excluded, Not priced, Clarify (the bid is silent or unclear) or Extra scope. Read the bid letter's inclusions and exclusions paragraph by paragraph to set it.
- Bidder adjustment
- Computed: the plug value when the item is excluded, not priced or to clarify, zero otherwise.
- Where the bid says it
- The page, clause or line of the bid that states the exclusion, or a note that the bid is silent. It is what you quote back on the scope review call.
- Base bid, bond and tax
- In the comparison table: the number on the bid as submitted (a unit price bid extended with your quantities), Y or N for bond and for sales tax, and the taxable amount when tax applies to part of the bid only.
- Extra scope deducted
- Entered by hand when a bidder priced something you did not ask for and you can value it from the bid, with what it is and where it is priced.
- Leveled bid and best case
- Base bid plus plugs, bond and tax added, minus deducts; then the same total if every item to clarify turns out included.
- Missing values, open items
- Missing values counts what the sheet cannot price (a plug left empty, bond or tax not answered, a rate left empty); open items adds the items to clarify. A bid with a missing value is not ranked.
- Rank, over lowest, status
- The rank among complete bids, the gap to the lowest, and one status line: final, provisional (items open, but the lowest holds whatever they resolve to) or not decided.
How to use it
- Write the package's scope in column A, one item per line, from the drawings, specifications and addenda, not from a bidder's letter.
- Give each item a plug value, its basis (your estimate, the bidder's own add or alternate, another bid, a separate quote, an allowance) and its source.
- Enter each bidder's name, then mark every scope item for that bidder (included, excluded, not priced, clarify or extra scope) and note where the bid says it.
- In the comparison table, enter each base bid as submitted, Y or N for bond and sales tax, the taxable amount if tax applies to part of the bid, and any extra scope to deduct.
- Read the ranking status first: final, provisional or not decided. Settle every item marked clarify in writing before award.
Limits
- A plug value is an assumption: the leveled total is only as good as your plug values, which is why the sheet asks where each one comes from.
- Deducts for extra scope are entered by hand: the sheet cannot know what an item the bidder added is worth to you.
- Bond and tax are added at one rate each, on the base bid and on the taxable amount you enter. Whether tax applies, and to what, depends on your contract and jurisdiction.
- Leveling makes bids comparable. The award still weighs qualifications, schedule, bonding and the bidder's record, which the sheet only records.
A worked example
A drywall package with six scope items and three bidders, the example the bid leveling guide works through. Bidder A, a lump sum of 612,000, excludes firestopping (plug 18,400 from your takeoff) and hoisting (plug 14,000) and leaves out its bond (1.1%, 6,732): leveled 651,132. Bidder C, lowest as submitted at 589,000, excludes four items worth 63,500 in plugs, leaves sales tax out (7% on 220,000 of materials, 15,400), prices 12,400 of ceilings that belong to another package, and says nothing about daily cleanup, carried at 6,500: 662,000, or 655,500 if cleanup turns out included.
Bidder B, unit prices extended with your quantities to 628,390, excludes blocking (7,200), leaves tax out (7% on 236,000, 16,520) and has no line for shaft wall, carried at 21,500: 673,610, or 652,110 at best. Two items are open, yet the status reads provisional with A lowest, because A's 651,132 is below both other best cases. Leave the bond rate empty and A is no longer ranked; the status changes to not decided.
Mistakes to avoid
- Building the scope list from the lowest bidder's letter: whatever it left out disappears from the comparison.
- Using a plug value that is too low because it came from the bidder who excluded the item without committing to it. Take it from your estimate, a separate quote, or a price a bidder actually offered as an add or alternate.
- Treating 'not mentioned' as included. Silence is a Clarify, carried at its plug and asked before award, in writing.
- Comparing a bid with bond and tax to one without them. Answer Y or N for both on every bid and add what is missing.
- Awarding with open Clarify items. The scope letter in the subcontract should settle every one of them.
Questions
Comparing subcontractor bids for the same scope line by line, so that missing scope, exclusions and extras are accounted for before the bids are compared. Without it, the lowest number on paper is often the bid that left the most out.
An amount the general contractor carries for an item a bidder excluded or did not price, from its own estimate, a separate quote or a price a bidder committed to for the same item. Adding it to that bid puts all bids on the same scope.
A bid with a missing value (an excluded or unclear item without a plug, bond or tax not answered, or left out with no rate) has a total that counts the unknown as zero. Ranking it would compare it as if it were complete. The sheet shows its known total as a floor and marks it not ranked until the value is entered.
A bid tabulation lists the bids as submitted, often published by a public owner after a bid opening. Leveling adjusts each bid to the same scope before comparing them, which is what a general contractor does before awarding a subcontract.
Yes, with some formula work: copy a bidder's three columns and a row of the comparison table, point the new row's formulas at the new columns, and extend the ranges of the rank, difference and status formulas. The online calculator takes up to six bidders.
Not automatically. The leveled total tells you the price for the same scope; qualifications, schedule, bonding, safety record and past performance still decide the award.
The scope list for the package, from the drawings, specification sections and addenda, with a plug value and its source for each item. With that in place, leveling a bid is marking statuses and noting where the bid says it; without it, each bid has to be read to discover the scope, and the lowest letter tends to define it.
An exclusion removes an item from the price; a qualification sets a condition on it, such as a working-hours restriction, an escalation clause or a validity period. Both change what the bid is worth, but only exclusions get a plug value; qualifications go in the notes and are weighed at award.