FIDIC Red Book: A Practical Notice and Claims Administration Guide

Under a FIDIC Red Book contract, entitlement to extra time or money often turns on two things: whether the notice went out inside the contractual period, and whether the records exist to prove the event. In the General Conditions of the 2017 edition, a Notice of Claim is due within 28 days of becoming aware of the event and a fully detailed claim within 84 days; the 1999 edition uses 28 and 42 days. This guide shows how to run that process on a live project: a register, a matrix of who sends what by when, the records to keep, and a worked variation.

Published
Sources checked
Reading time
14 min
Written by
Mirage Metrics team

Scope: the General Conditions of the Red Book 1999 (first edition) and 2017 (second edition, reprinted in 2022 with amendments). Your Particular Conditions may change any period or clause cited here. The guide paraphrases FIDIC's conditions and does not reproduce them; buy the official text from FIDIC. It is not legal advice on a specific contract.

Decision snapshot

Best suited to
Contract managers, project managers and document controllers running an international project under a FIDIC Red Book, on either side of the contract.
Inputs needed
The signed contract (Contract Data, General and Particular Conditions), the correspondence log, instructions, drawing issues, programme revisions and site records.
What can be automated
Collecting correspondence, extracting dates and references into a register, computing the next date from the period you enter, flagging lines with no document issued, assembling record bundles, comparing drawing revisions.
What requires human approval
The date you became aware, the route an event follows, whether to send a Notice, its content and signature, the contractual basis and the quantum of any claim, and any Notice of Dissatisfaction.
When this approach is insufficient
When the contract is not a Red Book, when the Particular Conditions rewrite Clauses 3, 13 or 20 heavily, when a dispute is already before a DAAB or tribunal, or when the governing law adds requirements. At that stage you need the contract's own text and counsel.

Who this guide is for

It is written for the people who keep a FIDIC project's paper trail alive: the contractor's contract manager and document controller, the employer's project team, and the Engineer's staff who receive and answer the notices. It assumes you already know what a Red Book is (a contract for works designed by the Employer, administered by an Engineer, and paid on measured quantities) and focuses on the daily mechanics.

It is not a bidding guide. If you are pricing a French public works tender, see how to respond to a French construction tender. It is also not a transposition of NEC4, which runs on a different logic (early warnings and compensation events with their own periods); the NEC4 contract administration page covers that family separately.

Which edition governs your contract

Before any date goes into a register, establish three facts from the contract itself: which FIDIC book it is based on, which edition, and what the Particular Conditions change. The 1999 and 2017 Red Books share clause numbers but not procedures, so mixing them is the most common source of wrong deadlines. The 2017 edition was reprinted in 2022 with amendments that FIDIC made effective from 1 January 2023; a contract signed on an earlier print may or may not incorporate them.

Red Book General Conditions, 1999 and 2017: where the claim and notice rules differ (paraphrased, check your contract)
TopicRed Book 1999Red Book 2017 (reprint 2022)
Notice of a claimSub-Clause 20.1: as soon as practicable and no later than 28 days after the Contractor became aware, or should have become aware, of the eventSub-Clause 20.2.1: within 28 days after the claiming Party became aware, or should have become aware, of the event
Who the claim procedure bindsThe Contractor's claims; Employer's claims follow a lighter, separate route (Sub-Clause 2.5)Both Parties, Employer and Contractor, through the same Clause 20 procedure
Late noticeTime bar: no extension of time and no additional payment for that eventTime bar, but the Engineer has 14 days to give Notice that the claim was late; if it does not, the Notice of Claim is deemed valid. The claiming Party can argue that lateness was justified in its fully detailed claim
Fully detailed claimWithin 42 days after becoming aware of the eventSub-Clause 20.2.4: within 84 days after becoming aware, or another period agreed. It must contain the contractual or other legal basis; missing that statement is a second time bar
Engineer's responseWithin 42 days after receiving the fully detailed claim, then a determination under Sub-Clause 3.5Sub-Clause 3.7: consultation towards agreement, then a fair determination; 42 days for each step unless otherwise agreed. If no determination of a Claim arrives in time, it is deemed rejected (Sub-Clause 3.7.3)
Challenging the outcomeReferral to the Dispute Adjudication Board under Clause 20Notice of Dissatisfaction within 28 days after receiving the determination (Sub-Clause 3.7.5), otherwise the determination becomes final and binding
Warning of future problemsContractor-side obligations onlySub-Clause 8.4, Advance Warning: each Party warns the other and the Engineer of probable future events that could affect the work, the price or the programme
Form of a noticeSub-Clause 1.3: communications in writingSub-Clause 1.3: a Notice must be in writing and identified as a Notice; other communications must name the provision they are given under
Red Book General Conditions, 1999 and 2017: where the claim and notice rules differ (paraphrased, check your contract)

Source: [2018] ICLR 384, hosted by FIDIC; Gowling WLG (2024); Freshfields on the 2022 reprints. Periods are those of the General Conditions.

Three checks before you trust a period

  • Read the Particular Conditions for any change to Sub-Clauses 1.3, 3.5 or 3.7, 8, 13 and 20. Employers often shorten or lengthen claim periods there.
  • Check whether the contract is a development bank edition or a heavily amended form. It will look like a Red Book and behave differently.
  • Check how the contract defines a day and when a Notice is treated as received, including the address and method it must be sent by.

One event, from discovery to decision

The sequence below follows the 2017 General Conditions. Each step names the sub-clause so you can check it against your own contract; the 1999 differences are noted after the list.

  1. Discovery. Someone on site, in design or in the commercial team notices an event: an instruction, a late drawing, ground conditions, a suspension. The date and the evidence of that moment go into the register the same day, because the 28 days run from when you became aware or should have.
  2. Advance warning. If the problem is still in the future, Sub-Clause 8.4 asks each Party to warn the other and the Engineer of probable events that could affect the work, the price or the programme. A warning is not a Notice of Claim and does not replace one.
  3. Route decision. Is it a Variation instructed under Clause 13, a disagreement with an instruction under Sub-Clause 3.5, or an event that gives rise to a Claim under Clause 20? The route sets the documents and dates. When the answer is unclear, diarise both.
  4. Notice of Claim. For the Clause 20 route, a Notice identified as such, describing the event, goes to the Engineer within 28 days (Sub-Clause 20.2.1).
  5. Contemporary records. From that point the claiming Party keeps the records needed to substantiate the claim, and the Engineer may inspect them or instruct additional ones (Sub-Clause 20.2.3).
  6. Engineer's check on timing. If the Engineer considers the Notice late, it has 14 days to say so by Notice. Silence makes the Notice of Claim deemed valid; the other Party can still dispute that.
  7. Fully detailed claim. Within 84 days of awareness, or another agreed period: a description, the contractual or other legal basis, the contemporary records relied on, and the particulars of time and money (Sub-Clause 20.2.4). If the basis statement is missing, the claim lapses.
  8. Continuing events. If the effect continues, the first fully detailed claim is treated as interim, updated monthly, and followed by a final fully detailed claim within 28 days after the effects end (Sub-Clause 20.2.6).
  9. Agreement or determination. The Engineer consults the Parties towards agreement and, failing that, makes a fair determination, each step within 42 days unless otherwise agreed (Sub-Clause 3.7).
  10. Dissatisfaction. A Party that disagrees gives a Notice of Dissatisfaction within 28 days of receiving the determination (Sub-Clause 3.7.5). Without it, the determination becomes final and binding. The dispute then goes to the Dispute Avoidance/Adjudication Board under Clause 21.

Under the 1999 edition the shape is similar but lighter: the Contractor's notice is due within 28 days, the fully detailed claim within 42 days, and the Engineer responds within 42 days of receiving it, with determinations under Sub-Clause 3.5. There is no 14-day late-notice mechanism, and Employer's claims follow Sub-Clause 2.5 rather than the same procedure.

The notice register

A notice register is a single list of every event that could lead to a Notice, with its route, its dates and its documents. Spreadsheet or database, the format matters less than three rules: one line per event, fixed status values, and a named owner. The example values below belong to the worked example later in this guide.

Notice register: the fields to keep for every event, with example values
FieldExample valueWhy it matters
Register IDN-0042Your own sequential reference. Never reuse a number, even for a withdrawn notice.
Contract and editionRed Book 2017, reprint 2022, PC amendedCopied from the Contract Data, not from memory. Any Particular Condition touching Clauses 1.3, 3.7, 13 or 20 is noted here.
EventCulvert C3 relocated by instruction EI-017One event per line. A second consequence of the same event is a new line linked to this one.
Date aware (or should have been)2026-03-02The date the time limit runs from. Record who knew, and the document that proves it.
Route13.3.1 VariationWhich procedure the event follows: 13.3.1 Variation, 3.5 disagreement or 20.2 Claim. When unsure, record both routes and both deadlines.
Next contractual date2026-03-30Computed from the date aware and the period in your contract, then checked by a second person.
OwnerContract manager, site package BA named person, not a department.
Documents issuedCTR-L-0107 acknowledging EI-017, sent 2026-03-03Reference, date, method of delivery, recipient address as the contract defines it.
Documents receivedEngineer's acknowledgement ENG-C-0311Includes any Engineer's Notice that the claim was late.
StatusParticulars in preparationOne of a fixed list (see the matrix below), never free text.
Notice register: the fields to keep for every event, with example values

Two habits make the register trustworthy. First, a second person checks every computed date against the contract, because a period copied from a previous project is the classic error. Second, the register is reviewed at a fixed weekly slot, line by line, even when nothing seems to be happening: a line with a date inside the next ten days and no draft document is the line that goes wrong.

The event matrix: event, document, date, owner, status

The register lists events as they happen. The matrix is the reference card behind it: for each type of event, which document it calls for, how the date is computed, who owns it and what status it starts in. Build it once at contract start, from your own contract, and pin it next to the register.

Event matrix for a 2017 Red Book with General Conditions periods (template, adjust to your Particular Conditions)
EventDocument to issueDateOwnerStarting status
Engineer's instruction changes the worksInstruction, drawings, Contractor's detailed particulars (13.3.1)28 days from receiving the instruction, unless the contract says otherwiseContract manager, with planner and estimatorParticulars due
Instruction received that is not called a VariationContractor's Notice under 3.5, before starting the workPromptly, and before the work startsContract managerDecision needed
Unforeseeable ground conditions foundNotice of Claim (20.2.1), then site records, then fully detailed claim (20.2.4)28 days, then 84 days, from the date awareSite manager raises, contract manager issuesNotice due
Late drawings from the EngineerAdvance Warning (8.4) if foreseen, Notice of Claim if delay occursWarning as soon as the risk is known; claim within 28 days of awarenessPlanner raises, contract manager issuesNotice sent
Engineer gives Notice that a claim was lateReasons why lateness was justified, inside the fully detailed claimWith the fully detailed claim (84 days from awareness)Contract manager, with counsel if the value justifies itChallenge required
Engineer's determination receivedNotice of Dissatisfaction (3.7.5) if you disagree28 days from receiving the determinationCommercial directorDecision needed
Event matrix for a 2017 Red Book with General Conditions periods (template, adjust to your Particular Conditions)

Keep the status list short and closed: Logged, Notice due, Notice sent, Particulars due, Submitted, Awaiting Engineer, Determined, Dissatisfaction notified, Closed. Orange in the table marks a line waiting on a person; red marks a line where the other side has already challenged your position.

Records to keep from day one

Both editions make contemporary records the evidence base of a claim, and the 2017 edition lets the Engineer inspect them and instruct you to keep more. Records made at the time carry weight that reconstructions made months later do not. The practical rule: if a record would help prove the event, its date or its cost, it is filed against the register line the day it is created.

Record families to file against each register line
FamilyExamplesWhat it proves
CorrespondenceLetters, Notices, emails with the Engineer, transmittals, delivery receiptsProves what was said, when, and that it reached the address the contract names
Instructions and drawingsEngineer's instructions, drawing issues and revisions, RFIs and their answersProves what changed and when you were told
ProgressDaily site diaries, monthly progress reports, programme revisions, photographs with datesLinks the event to its effect on the work
ResourcesLabour and plant allocation sheets, timesheets, equipment logs, idle timeThe basis for any cost or time quantum
CostInvoices, purchase orders, subcontractor accounts, cost reports coded to the eventSeparates the event's cost from normal cost
MeetingsMinutes, action lists, comments on the minutesShows who knew what, which can matter for awareness and prejudice
Record families to file against each register line

File by register ID as well as by date. When the fully detailed claim is due, the bundle for that line should already exist, instead of being rebuilt from mailboxes.

Worked example: an instructed variation

Illustrative example, invented figures: relocating a culvert on a road project

Assumptions, all invented for this example. The contract is a Red Book 2017, reprint 2022. The Particular Conditions do not change Clauses 1.3, 3.7, 13 or 20. The instruction is stated to be a Variation under Sub-Clause 13.3.1, and the contract keeps the General Conditions' 28 days for the Contractor's detailed particulars. Days are counted as calendar days from receipt of the instruction.

Timeline of an instructed variation, register lines N-0042 and N-0043 (invented)
DayWhat happensRegister actionStatus
Day 0Engineer's instruction EI-017 relocates culvert C3 by 40 m, stated to be a VariationRegister line N-0042 opened, route 13.3.1, owner assignedLogged
Day 1Planner checks the programme: the new position crosses an access road used by two other crewsSecond line N-0043 opened for the access impact, linked to N-0042Logged
Day 3Site diary and photographs start recording the affected area dailyRecords referenced in N-0042 and N-0043Recording
Day 10Estimator prices the new culvert position; planner models 6 working days of delay to package BDraft particulars: description, programme proposal, price adjustmentDraft
Day 21Internal review: contract manager and a second reader check the particulars against the instructionTwo discrepancies corrected (wrong drawing revision cited, missing plant cost)In review
Day 26Particulars submitted under 13.3.1, identified as such, to the Engineer's contract addressDelivery receipt filed; next date: Engineer's agreement or determination under 3.7Submitted
Day 28Deadline for particulars under the assumed contract termsMet with two days of marginMet
Timeline of an instructed variation, register lines N-0042 and N-0043 (invented)

The fork to watch. Had EI-017 not been stated to be a Variation, the Contractor would have needed to give Notice under Sub-Clause 3.5 before starting the work, and any time or money consequence might then have run through Clause 20 with its own 28 and 84 days. Line N-0043, the access road impact, is the other risk: if the contract manager decides it falls outside what the 13.3.1 particulars cover, it is a separate claim with its own Notice. That is a judgment for the contract manager, and the register's job is to make sure it is taken before day 28, not after.

Mistakes that cost entitlement

  • Using the other edition's periods. Forty-two days for a fully detailed claim is right in 1999 and wrong in 2017, and the reverse. Take periods from your contract, never from a colleague's last project.
  • A letter that is not identified as a Notice. Under the 2017 edition a Notice must say it is one. A progress report that mentions a problem is not a Notice of Claim.
  • Waiting for the full cost before notifying. The notice describes the event; the quantum comes later, in the fully detailed claim.
  • Treating an Advance Warning as a Notice of Claim. They are different acts with different consequences.
  • Leaving out the legal basis. In the 2017 edition a fully detailed claim without its contractual or legal basis lapses.
  • Missing the Notice of Dissatisfaction. Twenty-eight days after a determination, silence makes it final and binding.
  • Records kept by person, not by event. The evidence exists, spread across five mailboxes, and cannot be assembled in time.
  • Sending to the wrong address. The contract names where and how Notices are delivered; an email to a site engineer may not qualify.

What software can prepare, and what it cannot decide

Most of the effort in notice administration is finding, reading and filing: which letter mentioned the culvert, when the revised drawing arrived, what the diary said that day. That work can be prepared by software that reads correspondence and drawings and keeps the register current. The decisions that create or lose rights cannot.

Split of work between software preparation and professional decision
TaskWho does itWhat stays with a professional
Find every instruction, letter and drawing issue that mentions an eventCan be prepared by softwareDecide whether the event gives an entitlement at all
Extract dates, references and senders from correspondence into the registerCan be prepared by softwareDecide the date you became aware, which is a judgment, not an extraction
Compute the next contractual date from the period and the date enteredCan be prepared by softwareConfirm the period, which depends on the edition and the Particular Conditions
Flag a register line approaching its date with no document issuedCan be prepared by softwareChoose whether to send a Notice, a protective Notice, or nothing
Draft a first version of a Notice from a template, citing the source documentsCan be prepared by software, reviewed line by lineSign and send it: the Notice is the company's act
Compare two drawing revisions and list what changedCan be prepared by softwareAssess whether the change is a Variation and value it
Assemble the record bundle for a fully detailed claimCan be prepared by softwareBuild the contractual and legal basis, and the quantum
Split of work between software preparation and professional decision

This is the boundary Mirage works to on construction documents. Its agents read correspondence, instructions and revisions, link each extracted date or reference to the page it came from, and flag what needs a person, as on the change order review and plan revision comparison workflows. Mirage has not published a FIDIC deployment; if you want to test the approach, the honest test is a closed event from one of your own projects, where you already know the right answer.

Readiness checklist

Run it at contract start, and again whenever the team or the contract changes.

  • Book, edition and print of the conditions identified from the signed contract
  • Particular Conditions read for every change to Sub-Clauses 1.3, 3.5, 3.7, 8, 13 and 20
  • Periods entered in the event matrix and checked by a second person
  • Contractual address and delivery method for Notices recorded, with a tested template that identifies a Notice as such
  • Notice register created with fixed status values and a named owner per line
  • Weekly register review booked, with the Engineer's correspondence log reconciled against it
  • Record families filed by register ID, not only by date or author
  • Rule agreed for uncertain routes: both deadlines diarised until the contract manager decides
  • Escalation path agreed for determinations: who decides on a Notice of Dissatisfaction, within how many days
  • Legal support identified for claims above a value threshold you set

Questions readers ask

Is the 28-day notice period the same in every FIDIC Red Book contract?

No. It is 28 days in the General Conditions of both the 1999 and the 2017 Red Book, but Particular Conditions frequently change it, and a contract can be based on another FIDIC book or on a development bank version with its own amendments. Read the Contract Data and the Particular Conditions before you enter any period in a register.

Does an instructed Variation need a Notice of Claim under the 2017 Red Book?

An instruction stated to be a Variation follows Sub-Clause 13.3.1: the Contractor submits detailed particulars and the Engineer agrees or determines the adjustment under Sub-Clause 3.7. The 2022 reprint lists the matters that go through Sub-Clause 3.7 and excludes them from the definition of a Claim. If the instruction is not stated to be a Variation, or if you claim something beyond what the variation procedure covers, check whether the Clause 20 route applies and diarise its dates.

What counts as the date the 28 days start?

Both editions run the period from when the claiming Party became aware, or should have become aware, of the event or circumstance. That is a factual judgment, so record the evidence for the date you choose: the document, the meeting or the site observation that first revealed the event.

Can a late Notice of Claim still be accepted under the 2017 edition?

The 2017 edition keeps the time bar but gives the Engineer 14 days to give Notice that a claim was late. If the Engineer does not, the Notice of Claim is deemed valid. If it does, the claiming Party can set out why the lateness was justified in its fully detailed claim, and the Engineer considers factors such as prejudice to the other Party. A tribunal is not bound by the Engineer's view on this. Do not plan on lateness being excused.

Is this guide legal advice?

No. It describes how to organise notices, records and deadlines. Whether an event gives a right to time or money under your contract, and under the law that governs it, is a question for your contract manager and, where the value justifies it, for a lawyer who has read the contract.

Sources and scope

Checked on . Scope: General Conditions of the FIDIC Red Book 1999 and 2017 (reprint 2022). FIDIC's contract text is copyright and not reproduced here; the sources are FIDIC-hosted and law-firm commentaries that describe it. Always read your own contract, including its Particular Conditions.

This guide explains contract administration practice for educational purposes. It is not legal advice and does not replace a reading of your contract by a qualified professional.

Related on this site

Test it on a closed event from your own project

Send us the correspondence and drawings for one event you have already settled. We will show you the register lines, dates and source links our agents produce, so you can compare them with what your team found by hand.

Prefer to talk it through? Book a call

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy