The New SLC Redevelopment Program
- Location
- Salt Lake City, UT, United States. Location shown at city level. See it on the map
- Stage
- Opened, as of October 2026 (Salt Lake City Department of Airports).
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Salt Lake City Department of Airports | |
| Category | Airports | |
| Amount | US$5.1 billion (US dollars), as of July 2026 | Salt Lake City Department of Airports |
| What the amount covers | Programme value. | |
| Threshold evidence | A cited project-scope figure meets the threshold |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$5.1 bn | Programme value | Programme | Jul 2026 | Salt Lake City Department of Airports |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| HDJV (Holder - Big D, a construction joint venture) | construction team (joint venture) | Car rental facilities, central utility plant, parking garage, elevated roadway, Concourse A, Terminal, central tunnel, airfield paving, economy parking lot | Salt Lake City Department of Airports |
| AOJV (Austin Commercial - Okland Construction Joint Venture) | construction team (joint venture) | Concourse B-west | Salt Lake City Department of Airports |
| HOK | architect | The New SLC | Salt Lake City Department of Airports |
| HNTB | civil designer | The New SLC | Salt Lake City Department of Airports |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| July 2014 | Groundbreaking | Whole project | Salt Lake City Department of Airports |
| September 2020 | phase opening | Whole project | Salt Lake City Department of Airports |
| October 2023 | phase opening | Whole project | Salt Lake City Department of Airports |
| October 2024 | opening | Whole project | Salt Lake City Department of Airports |
| July 2026 | phase opening | Whole project | Salt Lake City Department of Airports |
| October 27, 2026 | opening | Whole project | Salt Lake City Department of Airports |
About the project
Redevelopment of Salt Lake City International Airport with a new terminal and two concourses: 94 aircraft gates, 4 hardstand positions and 101 concessions. The programme broke ground in July 2014; Phase 1 opened in September 2020, Phase 2 in October 2023 and Phase 3 in October 2024; four additional gates opened in July 2026 and the remaining seven gates and six concessions opened on October 27, 2026, completing the final phase after 12 years of construction. The total cost of The New SLC is $5.1 billion.
Sources
- SLC International Airport to Mark Completion of The New SLC, Salt Lake City Department of Airports, 23 Jul 2026. Body: 'The total cost of The New SLC is $5.1 billion'; phase opening dates. Consulted 12 Nov 2026.
- Touch Down: SLC International Airport Celebrates the End of an Era, Salt Lake City Department of Airports, 28 Oct 2026. Body: 'After 12 years of construction the final phase of The New SLC is complete'; 'The cost of The New SLC is $5.1 billion'; 'Phase 3 opened in October 2024. Four additional gates opened in July 2026, and the remaining seven gates and six concessions open on October 27, 2026'. Consulted 12 Nov 2026.
- The New SLC Fact Sheet, Salt Lake City Department of Airports. 'HDJV (Holder - Big D—A construction joint venture) - Scope: car rental facilities, central utility plant, parking garage, elevated roadway, Concourse A, Terminal, central tunnel, airfield paving, economy parking lot.'. Consulted 18 Nov 2026.