The New SLC Redevelopment Program

Location
Salt Lake City, UT, United States. Location shown at city level. See it on the map
Stage
Opened, as of October 2026 (Salt Lake City Department of Airports).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorSalt Lake City Department of Airports
CategoryAirports
AmountUS$5.1 billion (US dollars), as of July 2026Salt Lake City Department of Airports
What the amount coversProgramme value.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$5.1 bnProgramme valueProgrammeJul 2026Salt Lake City Department of Airports
Financial records, each with its kind and scope

Contracts and teams

CompanyRolePackageSource
HDJV (Holder - Big D, a construction joint venture)construction team (joint venture)Car rental facilities, central utility plant, parking garage, elevated roadway, Concourse A, Terminal, central tunnel, airfield paving, economy parking lotSalt Lake City Department of Airports
AOJV (Austin Commercial - Okland Construction Joint Venture)construction team (joint venture)Concourse B-westSalt Lake City Department of Airports
HOKarchitectThe New SLCSalt Lake City Department of Airports
HNTBcivil designerThe New SLCSalt Lake City Department of Airports
Delivery parties, each named by the owner, a government or the company itself

Milestones

DateMilestoneScopeSource
July 2014GroundbreakingWhole projectSalt Lake City Department of Airports
September 2020phase openingWhole projectSalt Lake City Department of Airports
October 2023phase openingWhole projectSalt Lake City Department of Airports
October 2024openingWhole projectSalt Lake City Department of Airports
July 2026phase openingWhole projectSalt Lake City Department of Airports
October 27, 2026openingWhole projectSalt Lake City Department of Airports
Dated milestones, at the precision of their source

About the project

Redevelopment of Salt Lake City International Airport with a new terminal and two concourses: 94 aircraft gates, 4 hardstand positions and 101 concessions. The programme broke ground in July 2014; Phase 1 opened in September 2020, Phase 2 in October 2023 and Phase 3 in October 2024; four additional gates opened in July 2026 and the remaining seven gates and six concessions opened on October 27, 2026, completing the final phase after 12 years of construction. The total cost of The New SLC is $5.1 billion.

Sources

  • SLC International Airport to Mark Completion of The New SLC, Salt Lake City Department of Airports, 23 Jul 2026. Body: 'The total cost of The New SLC is $5.1 billion'; phase opening dates. Consulted 12 Nov 2026.
  • Touch Down: SLC International Airport Celebrates the End of an Era, Salt Lake City Department of Airports, 28 Oct 2026. Body: 'After 12 years of construction the final phase of The New SLC is complete'; 'The cost of The New SLC is $5.1 billion'; 'Phase 3 opened in October 2024. Four additional gates opened in July 2026, and the remaining seven gates and six concessions open on October 27, 2026'. Consulted 12 Nov 2026.
  • The New SLC Fact Sheet, Salt Lake City Department of Airports. 'HDJV (Holder - Big D—A construction joint venture) - Scope: car rental facilities, central utility plant, parking garage, elevated roadway, Concourse A, Terminal, central tunnel, airfield paving, economy parking lot.'. Consulted 18 Nov 2026.