WALK Bridge Replacement Program

Location
Norwalk, CT, United States. Location shown at city level. See it on the map
Stage
Under construction, as of November 2026 (Connecticut Department of Transportation).
Status
Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
Research as of

Owners, scope and amount

FieldValueSource
Owner or sponsorConnecticut Department of Transportation (CTDOT)
CategoryBridges
AmountUS$1.137 billion (US dollars), as of August 2018Connecticut Department of Transportation
What the amount coversProgramme value.
Threshold evidenceA cited project-scope figure meets the threshold
Sourced facts in the research record

Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.

AmountWhat it isScopeAs ofSource
US$1.14 bnProgramme valueProgrammeAug 2018Connecticut Department of Transportation
Financial records, each with its kind and scope

Contracts and teams

Contracts and teams: Not found in the sources consulted.

About the project

CTDOT's programme to replace the Walk Bridge, the circa 1896 movable rail bridge on the Northeast Corridor that carries Metro-North's New Haven Line over the Norwalk River, with a new lift bridge, together with the Fort Point Street, Osborne Avenue and East Avenue bridges and the Danbury Branch dockyard and CP243 interlocking. CTDOT's major projects table listed the programme at $1,137 million (2018). The first phase of construction on the main bridge is underway, and the 130-year-old high towers have been removed (programme website, November 2026).

Sources

  • CTDOT On The Move - Major Project Updates (table, updated 8/17/2018), Connecticut Department of Transportation, 17 Aug 2018. Row '0301-0176 / 0180 / 0181 / 0187 / 0188 / 0189 AND 0102-0297 WALK BRIDGE REPLACEMENT PROGRAM, Norwalk, Various, 2017, 2023, $1137M'. Consulted 12 Nov 2026.
  • WALK Bridge Program website, Connecticut Department of Transportation. Home page updates: first phase of construction underway; removal of the high towers; closures November 14-15 and 21-22, 2026. Consulted 12 Nov 2026.
  • Proposed Final Decision, Application No. 201909990-SDF, Department of Transportation (Norwalk, Walk Bridge), Connecticut Department of Energy and Environmental Protection, Office of Adjudications, 6 Jun 2022. 'replace the existing circa 1896 four track movable swing span railroad bridge and replace it with a new four track movable lift span bridge consisting of two side-by-side, 240-foot vertical lift spans across the Norwalk River ... The Walk Bridge, an integral component of what is known as the 'Northeast Corridor' (NEC)'. Consulted 19 Nov 2026.