Research record, not reviewed
Washington Bridge Replacement
- Location
- Providence / East Providence, RI, United States. Location shown at city level. See it on the map
- Stage
- Stage not confirmed: Not collected yet.
- Status
- Research record, not reviewed: compiled from the sources below, and each fact checked against them on 19 Nov 2026; an editor has not yet reviewed it.
- Research as of
Owners, scope and amount
| Field | Value | Source |
|---|---|---|
| Owner or sponsor | Rhode Island Department of Transportation | |
| Category | Bridges | |
| Amount | US$427.9 million (US dollars) | Rhode Island Department of Transportation |
| What the amount covers | Construction budget. | |
| Threshold evidence | A comparable project-wide cost is still needed |
Every figure the record holds, each a different object: a project cost, a financed scope, a grant or a contract value are never added together, and an older estimate stays as history.
| Amount | What it is | Scope | As of | Source |
|---|---|---|---|---|
| US$221 M | Federal grant | Whole project | Oct 2024 | Office of U.S. Representative Seth Magaziner (joint release with the Governor of Rhode Island) |
| US$428 M | Construction budget | Whole project | Undated | Rhode Island Department of Transportation |
Contracts and teams
| Company | Role | Package | Source |
|---|---|---|---|
| Walsh Construction Company II, LLC | design-build team | New westbound Washington Bridge | Rhode Island Department of Transportation |
Milestones
| Date | Milestone | Scope | Source |
|---|---|---|---|
| November 2028 | Planned opening | Whole project | Rhode Island Department of Transportation |
About the project
Replacement of the I-195 westbound crossing over the Seekonk River. The eastbound bridge is not replaced; the project adds pier protection around its in-water piers (U.S. Coast Guard public notice, December 2025).
Sources
- Rebuilding 18 of America’s Most Economically Significant Bridges, U.S. Department of Transportation, Dec 2024. PDF page 20 · Project profile and grant. Consulted 9 Nov 2026.
- Washington Bridge documents and reports, Rhode Island Department of Transportation. New construction cost and planned opening. Consulted 9 Nov 2026.
- Quarterly Report, April-June 2025 (FFY 2025 Q3), Rhode Island Department of Transportation, 2025. 'On the Washington Bridge project, RIDOT finalized the procurement for the new westbound Washington Bridge, which will be built by the design-build team of Walsh Construction Company II, LLC. Notice to proceed was given on June 25'. Consulted 18 Nov 2026.
- $220.98 Million in Federal Funding Now Set for Washington Bridge Replacement, Office of U.S. Representative Seth Magaziner (joint release with the Governor of Rhode Island), 16 Oct 2024. '$220.98 million in federal funding to replace the Washington Bridge, fully funding the state's request ... $95,589,533 INFRA grant ... previous $125.39 million Mega grant'. Consulted 19 Nov 2026.
- Public Notice D01-217-2025, Washington (I-195 Westbound) Bridge, U.S. Coast Guard, Northeast District, 23 Dec 2025. 'This project entails the replacement of the Washington (I-195 Westbound) Bridge ... The project also calls for the installation of permanent pier protection structures (dolphin piles) to protect the existing in-water piers of the adjacent Washington (I-195 Eastbound) Bridge from vessel impact.'. Consulted 19 Nov 2026.