DBE Participation Template (Excel)

A free Excel template for DBE participation on a DOT-assisted contract: each DBE commitment with its certification and NAICS code, the counting rule of 49 CFR 26.55 and its credit rate, the countable commitment and the countable amount paid, attainment against the contract goal as formulas, and a good faith efforts log.

Download the Excel template

Free, no sign-up. Opens in Excel, Google Sheets and LibreOffice.

No Mirage deployment on DBE compliance is published. See subcontractor bid leveling

What the template looks like

The Commitments sheet and the goal attainment, filled with the worked example further down this page. The file you download is empty.

Commitments
DBE firmCertified in the work's NAICS codeCertified at executionCounting ruleCommittedSubcontracted to non-DBECreditCountableStatus
Earthwork subcontractorYesYesOwn forces120,000.0020,000.00100%100,000.00Counted
Ready-mix regular dealerYesYesRegular dealer of materials150,000.0060%90,000.00Counted
Rebar distributorYesYesDistributor of materials50,000.0040%20,000.00Counted
Firm certified after executionYesNoOwn forces90,000.00100%Not counted
Summary: goal attainment
LineValue
Contract amount the goal applies to2,000,000.00
DBE contract goal10.0%
Goal amount200,000.00
Countable commitments210,000.00
Countable commitments as a share of the contract10.5%
ResultCountable commitments meet the goal

Who uses it, and when

The Disadvantaged Business Enterprise program of 49 CFR part 26 applies to contracts assisted by the US Department of Transportation. A recipient sets contract goals to meet the part of its overall goal it does not expect to meet by DBE-neutral means, only on contracts with subcontracting possibilities, and a contract goal may be higher or lower than the overall goal (§ 26.51(d) and (e)). When a contract has a goal, the recipient awards it only to a bidder that documents enough DBE participation to meet it, or documents adequate good faith efforts (§ 26.53(a)).

With the bid, or no later than 5 days after bid opening if the solicitation treats it as a matter of responsibility, the bidder lists each DBE, the work it will perform, its certification in a NAICS code applicable to that work, the dollar amount, a written commitment and each DBE's written confirmation (§ 26.53(b)(2) and (3)). A design-build solicitation can ask for an open-ended DBE performance plan instead (§ 26.53(e)). After award, a listed DBE cannot be terminated, or its work reduced, without the recipient's written consent (§ 26.53(f)), and participation counts toward the contractor's final compliance only once the DBE has been paid (§ 26.55(h)). Estimators and contract administrators at prime contractors keep the list from the bid to closeout.

Since 3 October 2025, a recipient may not set contract goals or count DBE participation until the Unified Certification Program (UCP) that covers it has completed the reevaluation of every certified DBE described in § 26.111 (§§ 26.51(h) and 26.55(i)). Each UCP must complete it by 24 December 2026, with one extension of up to 90 days possible (§ 26.111(c)). The template records where your UCP stands and computes the figures either way.

What is in the file

Commitments
The project block (contract amount the goal applies to, the goal, the UCP reevaluation), then one line per DBE commitment: certification, NAICS code, status after the reevaluation, counting rule, committed amount, non-DBE subcontracting, own work force share, paid to date, with the credit rate, the countable amounts, a check and a status computed.
Summary
Goal amount, countable commitments and their share of the contract, the shortfall, countable payments to date and their share, and the lines counted, to check and not counted.
Good faith efforts
One line per DBE solicited: work offered, dates, how, quote received and amount, selected or not, the firm selected instead and why, and whether the quote copies are on file, with counts. When a non-DBE is selected over a DBE, the documentation must include copies of each DBE and non-DBE quote (§ 26.53(b)(2)(vi)); the recipient judges the efforts using appendix A of part 26, and a bidder found short can ask for administrative reconsideration before award (§ 26.53(d)).
Rules
The seven counting rules of § 26.55 with their credit rates and what to enter for each; the drop-down list reads from here.
Instructions
How to fill it, step by step, and the limits.

Column by column

Certified in that NAICS code
To count toward a goal, each DBE must be certified in a NAICS code applicable to the work it will perform on the contract (§ 26.53(b)(2)(ii)). No means the line is not counted.
Certified at contract execution
A firm not certified when the contract is executed does not count (§ 26.55(f)), and work performed after a firm ceases to be certified does not count either (§ 26.55(g)).
Status after the § 26.111 reevaluation
Retained, Pending or Disqualified, as the UCP's written decision states (§ 26.111(a)(4)). Disqualified lines are not counted; Pending lines are flagged.
Counting rule and credit rate
100% for work performed with the DBE's own forces (with the supplies it obtains), a manufacturer, a fee for a bona fide service, or a joint venture's distinct portion; 60% for a regular dealer and 40% for a distributor, of the cost of materials including transportation; fees or commissions only for any other supplier (§ 26.55(a), (b) and (e)).
Committed amount
The amount the rule applies to: the subcontract or purchase amount, or the fee for a fee rule.
Of which subcontracted to non-DBE firms
Work a DBE subcontracts to a non-DBE firm does not count (§ 26.55(a)(3)); it is taken out of the countable amount.
Own work force share
The share of the cost of its contract the DBE performs with its own work force. Below 30%, the recipient must presume it is not performing a commercially useful function, a presumption the DBE may rebut (§ 26.55(c)(3) and (4)). The line is flagged, not removed.
Countable commitment and countable paid
Computed: the committed amount less non-DBE subcontracting, times the credit rate; and the amount paid for the countable work, times the credit rate. Zero when the line is not counted.
Check and status
Computed: Counted, Check (with the reason) or Not counted (with the section).

How to use it

  1. Fill the project block: the recipient, the contract, the contract amount the goal applies to and the goal stated in the solicitation, and whether your UCP has completed the § 26.111 reevaluation.
  2. Enter one line per DBE commitment as listed with the bid: the firm, its certification, the NAICS code of its work and whether it is certified in that code, whether it was certified when the contract was executed, and its status after the reevaluation.
  3. Choose the counting rule for each line and enter the committed amount; for a fee rule, enter the fee. Enter what the DBE subcontracts to non-DBE firms and the share of its contract it performs with its own work force.
  4. Read the Summary: countable commitments against the goal amount. If they fall short, log the good faith efforts, one line per DBE solicited, with the quotes.
  5. As payments are made, enter the amount paid for the countable work on each line. The countable paid to date is what final compliance rests on (§ 26.55(h)).

Limits

  • The recipient, not this sheet, decides certification, commercially useful function and the credit for materials, contract by contract (§ 26.55(c) and (e)(5)). The sheet applies the counting rules to what you enter.
  • Trucking has its own counting rules (§ 26.55(d)): the DBE must own and operate at least one fully licensed, insured and operational truck on the contract, and credit for trucks leased with drivers from non-DBE firms is limited. Enter trucking under the rule the recipient applies.
  • Good faith efforts are judged by the recipient against appendix A of part 26; the log keeps the record, it does not judge it.
  • 100 commitment lines and 200 good faith effort lines.
  • A working document, not legal advice; the contract's DBE provisions govern.

A worked example

An invented example: a DOT-assisted contract of $2,000,000 with a 10% DBE contract goal, so a goal amount of $200,000, and a UCP that has completed its reevaluation.

A DBE earthwork subcontractor commits $120,000 with its own forces, of which $20,000 is subcontracted to a non-DBE firm: $100,000 counts. A DBE regular dealer supplies $150,000 of ready-mix concrete: 60%, $90,000. A DBE distributor supplies $50,000 of rebar: 40%, $20,000. A firm that was not certified when the contract was executed, committed at $90,000, does not count.

Countable commitments are $210,000, 10.5% of the contract amount: the commitments meet the goal. When the earthwork subcontractor has been paid $50,000 and the dealer $100,000, the countable paid to date is $50,000 plus 60% of $100,000, $110,000, or 5.5% of the contract.

Mistakes to avoid

  • Counting the full price of materials bought through a DBE that acts as a distributor or a broker. A regular dealer counts 60%, a distributor 40%, any other supplier its fee only (§ 26.55(e)).
  • Counting what the DBE subcontracts to non-DBE firms (§ 26.55(a)(3)).
  • Listing a DBE for work outside the NAICS codes it is certified in (§ 26.53(b)(2)(ii)).
  • Reporting commitments as attainment at closeout. Final compliance counts what the DBE has been paid (§ 26.55(h)).
  • Replacing a listed DBE, or self-performing its work, without the recipient's written consent (§ 26.53(f)).
  • Keeping no copy of the quotes when a non-DBE was selected over a DBE (§ 26.53(b)(2)(vi)).

Questions

  • A DBE contract goal is the share of a DOT-assisted contract the recipient sets for participation by certified DBEs, to meet the part of its overall goal it does not expect to meet by DBE-neutral means (§ 26.51(d)). Goals are set only on contracts with subcontracting possibilities and may be higher or lower than the overall goal (§ 26.51(e)). Since 3 October 2025, none may be set until the recipient's UCP has completed the § 26.111 reevaluation (§ 26.51(h)).

  • Only the value of the work the DBE performs counts: 100% for its own forces, a manufacturer, a bona fide service fee or a joint venture's distinct portion; 60% of the cost of materials from a regular dealer and 40% from a distributor; fees or commissions only for any other supplier. Work subcontracted to non-DBE firms is taken out, and participation counts toward final compliance only once paid (§ 26.55).

  • When the goal is not met, the bidder documents the efforts it made to meet it, and the recipient judges their adequacy using appendix A of part 26; if they are adequate, award cannot be denied for missing the goal (§ 26.53(a)(2)). The documentation must include copies of each DBE and non-DBE quote when a non-DBE subcontractor was selected over a DBE (§ 26.53(b)(2)(vi)), and the bidder can ask for administrative reconsideration before award (§ 26.53(d)).

  • At the recipient's choice: with the bid as a matter of responsiveness (or with initial proposals in a negotiated procurement), or no later than 5 days after bid opening as a matter of responsibility (§ 26.53(b)(3)). A design-build solicitation can ask for an open-ended DBE performance plan instead (§ 26.53(e)).

  • If a DBE does not perform or exercise responsibility for at least 30 percent of the total cost of its contract with its own work force, or subcontracts more than normal industry practice for the work, the recipient must presume it is not performing a commercially useful function (§ 26.55(c)(3)). The DBE may rebut the presumption (§ 26.55(c)(4)).

  • Yes. It uses standard functions (VLOOKUP, IFERROR, COUNTIF, SUMPRODUCT) and drop-down lists, which Google Sheets and LibreOffice support.

Sources

Read on eCFR on 12 November 2026; title 49 was up to date as of 9 November 2026.

Subcontractor quotes read as they arrive

This template counts the commitments you enter. No Mirage deployment on DBE compliance is published. Mirage deploys AI agents that read subcontractor bids in the layout they arrive and match every line to your scope, flagging exclusions and price gaps before award; at OCBM, three agents are in production and 100% of quantities are tied to a source drawing.