BABA Compliance Template (Excel)

A free Excel log for Build America, Buy America compliance on federally funded infrastructure work: one line per item permanently incorporated, its single category under 2 CFR part 184, the test that applies, the certification received and a status computed per line, with counts by status, the cost of components test for a manufactured product, and FHWA's minimal use check for foreign iron or steel.

Download the Excel template

Free, no sign-up. Opens in Excel, Google Sheets and LibreOffice.

No Mirage deployment on Buy America compliance is published. See RFI and submittal tracking

What the log looks like

The Items sheet and the Summary's minimal use check, filled with the worked example further down this page. The file you download is empty.

Items
ItemDescriptionCategoryTest that appliesOrigin, per the certificationCertificationStatus
1Structural steel girdersIron or steel productAll manufacturing processes, melting through coating, in the USProduced in the United StatesYesDocumented compliant
2Precast box culvertManufactured productManufactured in the US, US components over 55% of component costProduced in the United StatesYesDocumented compliant
3Anchor boltsIron or steel productAll manufacturing processes, melting through coating, in the USNot produced in the United StatesYesNot produced in the US
4PVC conduitConstruction material: plastic and polymer-based productsAll manufacturing processes, first combination of inputs to final form, in the USNot yet knownNoDocumentation missing
5Aggregate baseSection 70917(c) material (excluded)ExcludedExcluded material
Summary: FHWA minimal use of foreign iron or steel
LineValue
Total contract cost2,000,000.00
Foreign iron or steel, delivered cost3,000.00
Allowance: 0.1% of the contract or $2,500, whichever is greater2,500.00
ResultAbove the minimal use allowance

Who uses it, and when

The Build America, Buy America Act, sections 70901 to 70927 of the Infrastructure Investment and Jobs Act, sets a Buy America Preference on federal financial assistance for infrastructure: none of the funds of a federal award for an infrastructure project may be obligated unless all the iron, steel, manufactured products and construction materials incorporated into the project are produced in the United States (2 CFR 184.1(b) and 184.3). The preference must be in the terms of the award and in every subaward, contract and purchase order for the work (2 CFR 184.4(b)), so it reaches the prime contractor, its subcontractors and its suppliers.

Infrastructure is read broadly: roads, highways and bridges, public transportation, ports, railroads, airports, water systems, electrical transmission, utilities, broadband, buildings and real property, and energy facilities including EV charging, among others (2 CFR 184.4(c) and (d)). Project engineers, procurement and quality staff on those jobs keep a log like this one from the bid to closeout: listing each item from the specification, chasing the supplier's documentation before delivery and handing the owner a record of every item.

There is no certificate form in 2 CFR part 184. The agency's rules and the contract set it: FTA requires each bidder to submit a Buy America certificate of compliance or non-compliance with its bid (49 CFR 661.6 and 661.13(b)); FHWA leaves the means to standard recipient and federal-aid contract procedures (23 CFR 635.410(d)), so the state DOT's specifications say which documents it requires. A waiver is issued by the federal agency, not the owner or the contractor, on one of three grounds: the public interest, items not produced in the United States in sufficient and reasonably available quantities or of a satisfactory quality, or domestic items raising the cost of the overall project by more than 25 percent (2 CFR 184.7(a)). A recipient requests it in writing, and the agency publishes a proposed waiver for at least 15 days of public comment before issuing it (2 CFR 184.7(b) and (d)).

What is in the file

Items
The project block, then one line per item: description, spec section or bid item, supplier, category, construction material type, the test that applies (looked up), the origin the certification states, the domestic content answer for a manufactured product, certification received and its reference, any waiver relied on, the delivered cost, a status computed per line, and notes.
Summary
Lines by status and by category, and FHWA's minimal use check: foreign iron or steel at its delivered cost against 0.1% of the total contract cost or $2,500, whichever is greater (23 CFR 635.410(b)(4)), with a warning when a foreign line has no cost.
Cost of components
The 2 CFR 184.5 test for one manufactured product: each component's cost, whether it was mined, produced or manufactured in the United States, the domestic share and whether it is greater than the threshold, prefilled at the 55% of 2 CFR 184.3.
Tests
The five categories and the eight construction material types, each with the test the regulation sets and its section. The drop-down lists and the Test column read from here.
Instructions
How to fill it, the certification rules by agency, and the limits.

Column by column

Category
One only, chosen by what the item is when it is brought to the work site: iron or steel product, manufactured product, construction material, section 70917(c) material or none of the categories. An item meets the test of its own category only (2 CFR 184.4(e) and (f)). Section 70917(c) materials, cement and cementitious materials, aggregates such as stone, sand or gravel, and aggregate binding agents or additives, are excluded (2 CFR 184.3).
Construction material type
For a construction material only: non-ferrous metals, plastic and polymer-based products, glass, fiber optic cable, optical fiber, lumber, drywall or engineered wood (2 CFR 184.3). Each has its own manufacturing standard (2 CFR 184.6). Minor additions to a construction material do not change its category.
Test that applies
Computed from the category and the material type: where the manufacturing processes must take place, or the cost of components test for a manufactured product.
Origin, per the certification
What the supplier's certification or documentation states: produced in the United States, not produced in the United States, or not yet known.
Domestic content test met
For a manufactured product. Under 2 CFR 184.3, it is produced in the United States when it is manufactured there and the cost of its US components is greater than 55 percent of the cost of all its components, computed as 2 CFR 184.5 sets out. FHWA applies manufacture in the United States to projects obligated on or after 1 October 2025 and adds the 55 percent test from 1 October 2026 (23 CFR 635.410(c)(1)(vii)); FTA requires all components of US origin (49 CFR 661.5(d)).
Certification received, reference and date
Whether the document is in hand, and which one: the reference you will cite when the owner or the inspector asks.
Waiver relied on
The name and reference of the federal agency's waiver that covers the item, if one does (2 CFR 184.7).
Delivered cost to the project
The value of the item as delivered to the project. FHWA's minimal use check uses it for foreign iron or steel.
Status
Computed, in this order: Category missing, Excluded material, Not covered, Material type missing, Waiver relied on, Not produced in the US, Domestic content test not met, Documentation missing, Origin not confirmed, Documented compliant.

How to use it

  1. Fill the project block: owner or recipient, the federal agency and program, the contract number and the date the federal award was obligated. 2 CFR part 184 applies to awards obligated on or after 23 October 2023; awards obligated from 14 May 2022 until then fall under OMB memorandum M-22-11 (2 CFR 184.2(b)).
  2. List every item that will be permanently incorporated in the project, from the specification and the bid items, one line each.
  3. Give each item its one category as it will be when it arrives on site, and a material type for a construction material. Read the test in the Test column.
  4. Ask each supplier for its certification or documentation before the item ships. When it arrives, record its reference and date, the origin it states and, for a manufactured product, whether it states the domestic content test is met. To check a manufacturer's figure, use the Cost of components sheet.
  5. Record any waiver an item relies on, with its reference, after reading the waiver's scope.
  6. Review the Summary every week: lines with documentation missing first, then lines not produced in the United States. On an FHWA federal-aid highway project, enter the total contract cost and the delivered cost of every foreign iron or steel item to see the minimal use check.

Limits

  • The log records what the documents state. It does not verify a supplier's statement or audit a manufacturer's cost of components.
  • Agency rules can be stricter than 2 CFR part 184, and your contract decides which apply. FTA requires every component of a manufactured product to be of US origin (49 CFR 661.5(d)); FHWA phases its manufactured products rule by obligation date (23 CFR 635.410(c)).
  • The minimal use check is FHWA's and applies to federal-aid highway projects (23 CFR 635.410(b)(4)).
  • 300 item lines; 50 components on the Cost of components sheet, one product per sheet (copy it for the next).
  • A working document, not legal advice.

A worked example

An invented example: an FHWA federal-aid highway contract of $2,000,000, with the award obligated after 1 October 2026.

Structural steel girders are an iron or steel product; the mill certification states that every manufacturing process, coating included, took place in the United States. Status: Documented compliant. A precast concrete box culvert is a manufactured product; the manufacturer's statement says it was manufactured in the United States and that US components exceed 55% of component cost. Status: Documented compliant. Its steel reinforcement must also meet the iron and steel requirement, and its cost counts in the culvert's calculation (23 CFR 635.410(c)(2)(i)).

Anchor bolts from a foreign mill are delivered at $3,000: Not produced in the US. The allowance is the greater of 0.1% of $2,000,000, which is $2,000, and $2,500, so $2,500. The Summary reads Above the minimal use allowance.

PVC conduit is a construction material, plastic and polymer-based products, and no certification has arrived: Documentation missing. The aggregate base is a section 70917(c) material: Excluded material.

Mistakes to avoid

  • Putting an item in two categories, or categorizing it by what it is made of rather than what it is when it arrives on site (2 CFR 184.4(e)).
  • Treating cement, sand, gravel or stone as construction materials. They are section 70917(c) materials and are excluded (2 CFR 184.3).
  • Reading the 55% as a share of the product's price. It is the cost of the components, computed as 2 CFR 184.5 sets out, without any cost of manufacturing the product itself.
  • Relying on a waiver without reading its scope and dates. Only the federal agency issues one, after public comment (2 CFR 184.7).
  • Asking for the certification after delivery, when another supplier is no longer an option.

Questions

  • Meeting the Buy America Preference of the Build America, Buy America Act on a federally funded infrastructure project: all iron, steel, manufactured products and construction materials incorporated into the project are produced in the United States, unless a federal agency waiver applies (2 CFR 184.1(b) and 184.7). The preference flows down to every contract and purchase order for the work (2 CFR 184.4(b)).

  • Iron or steel products, manufactured products and construction materials, plus section 70917(c) materials (cement and cementitious materials, aggregates such as stone, sand or gravel, aggregate binding agents or additives), which are excluded. Each item goes in one category only, based on its status when it is brought to the work site (2 CFR 184.3 and 184.4(e)).

  • Under 2 CFR 184.3, a manufactured product is produced in the United States when it is manufactured there and the cost of its components mined, produced or manufactured in the United States is greater than 55 percent of the cost of all its components, computed as 2 CFR 184.5 sets out. FHWA applies the test to projects obligated on or after 1 October 2026 (23 CFR 635.410(c)); FTA requires all components of US origin (49 CFR 661.5(d)).

  • The document a bidder or supplier provides to show an item meets the preference. 2 CFR part 184 sets no form. FTA requires a Buy America certificate of compliance or non-compliance with each bid (49 CFR 661.6 and 661.13(b)); FHWA leaves the means to standard recipient and federal-aid contract procedures (23 CFR 635.410(d)), so the state DOT's specifications set the documents.

  • A federal agency may waive the preference when applying it would be inconsistent with the public interest, when the items are not produced in the United States in sufficient and reasonably available quantities or of a satisfactory quality, or when domestic items would increase the cost of the overall project by more than 25 percent (2 CFR 184.7(a)). The recipient requests it in writing and the agency publishes the proposed waiver for at least 15 days of comment (2 CFR 184.7(b) and (d)).

  • Yes. FHWA's minimal use rule allows foreign iron or steel products whose cost, as delivered to the project, does not exceed 0.1 percent of the total contract cost or $2,500, whichever is greater (23 CFR 635.410(b)(4)). The template's Summary sheet applies it.

  • Yes. It uses standard functions (VLOOKUP, COUNTIF, SUMIFS, SUMPRODUCT, IFERROR) and drop-down lists, which Google Sheets and LibreOffice support.

Sources

Read on eCFR on 12 November 2026; titles 2, 23 and 49 were up to date as of 9 November 2026.

Certifications arrive with the submittals

This log records the documents you collect. No Mirage deployment on Buy America compliance is published. Mirage deploys AI agents that track RFIs and submittals read from email, uploads or Procore, each answer with its source document and revision; at OCBM, three agents are in production and 100% of quantities are tied to a source drawing.