ARDOT contract 101115 bid tabulation
THE PURPOSE OF THIS PROJECT IS STREAM RESTORATION IN RANDOLPH COUNTY. THIS PROJECT CONSISTS OF CLEARING AND GRUBBING, EARTHWORK, AGGREGATE BASE COURSE, EROSION CONTROL, AND MISC. ITEMS. Let by Arkansas DOT on April 8, 2026, Randolph. 4 bids received; low bid $819,728 by Kyneric, LLC.
- Owner
- Arkansas DOT
- Letting
- 08 APR 2026
- Pay items
- 26
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Kyneric, LLC | $819,728 | Low |
| 2 | Seagraves Construction, Inc. | $1,415,954 | +73% |
| 3 | Michelle'S Excavating, Inc. | $1,629,797 | +99% |
| 4 | Robertson Contractors, Inc. | $2,142,157 | +161% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Kyneric, LLC | 2. Seagraves Construction, Inc. | 3. Michelle'S Excavating, Inc. | 4. Robertson Contractors, Inc. |
|---|---|---|---|---|---|---|---|
| 0001 | Clearing (201001) | ACRE | 4 | $1,551.12 | $5,000.00 | $1,000.00 | $5,850.00 |
| 0002 | Grubbing (201101) | ACRE | 4 | $1,551.12 | $5,000.00 | $1,000.00 | $3,800.00 |
| 0003 | Stone backfill (207011) | TON | 50 | $85.00 | $75.00 | $100.00 | $95.00 |
| 0004 | Unclassified excavation (210213) | CY | 11,799 | $15.09 | $15.00 | $15.00 | $38.65 |
| 0005 | Removing and replacing topsoil (210672) | CY | 1,787 | $9.50 | $25.00 | $20.00 | $36.10 |
| 0006 | Aggregate base course (class 7) (303117) | TON | 235 | $67.06 | $40.00 | $75.00 | $52.00 |
| 0007 | Furnishing field office (602011) | EACH | 1 | $15,000 | $40,000 | $20,000 | $30,000 |
| 0008 | Signs (604003) | SF | 48 | $24.65 | $15.00 | $50.00 | $16.00 |
| 0009 | Lime (620001) | TON | 12 | $20.00 | $145.00 | $500.00 | $800.00 |
| 0010 | Special seeding (620015) | ACRE | 5.93 | $1,385.39 | $6,237.29 | $6,000.00 | $2,500.00 |
| 0011 | Special mulch cover (620023) | ACRE | 11.86 | $898.64 | $1,486.29 | $6,000.00 | $2,350.00 |
| 0012 | Water (620030) | MGAL | 725.90 | $5.00 | $5.00 | $50.00 | $7.00 |
| 0013 | Temporary seeding (621002) | ACRE | 5.93 | $675.00 | $1,296.87 | $1,000.00 | $1,200.00 |
| 0014 | Silt fence (621021) | LF | 2,262 | $3.42 | $3.43 | $5.00 | $4.50 |
| 0015 | Sediment removal and disposal (621111) | CY | 84 | $4.78 | $5.00 | $10.00 | $3.10 |
| 0016 | Coir fiber matting (621205) | SY | 9,905 | $7.74 | $30.00 | $15.00 | $18.75 |
| 0017 | Geolift (621206) | LF | 1,217 | $83.64 | $50.00 | $275.00 | $285.00 |
| 0018 | Live brush fascine (621207) | LF | 2,530 | $7.32 | $35.00 | $40.00 | $65.00 |
| 0019 | Live stakes (621208) | EACH | 4,280 | $5.51 | $11.00 | $18.00 | $20.00 |
| 0020 | Special second seeding application (623006) | ACRE | 5.93 | $200.00 | $3,118.65 | $4,000.00 | $2,000.00 |
| 0021 | Rock buttress (630001) | CY | 30 | $106.13 | $195.00 | $500.00 | $940.00 |
| 0022 | Roadway construction control (635001) | LS | 1 | $21,151 | $35,000 | $50,000 | $70,000 |
| 0023 | Filter blanket (816003) | SY | 2,629 | $9.47 | $5.00 | $20.00 | $7.25 |
| 0024 | Dumped riprap (816113) | TON | 4,366 | $50.31 | $85.00 | $75.00 | $94.28 |
| 0025 | Bare root seedling (901081) | EACH | 1,391 | $11.00 | $17.50 | $12.00 | $25.15 |
| 0026 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $35,291 | $63,000 | $50,000 | $102,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 8, 2026. Compiled by Mirage Metrics.