ARDOT contract C18020 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO SURFACE APPROXIMATELY 0.21 MILES OF VARIOUS CITY STREETS IN THE CITY OF ANTHONYVILLE AND OVERLAY APPROXIMATELY 0.77 MILES OF CITY STREETS IN THE CITY OF EARLE IN CRITTENDEN COUNTY. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Crittenden. 6 bids received; low bid $273,690 by Atlas Asphalt, Inc..

Owner
Arkansas DOT
Letting
15 JAN 2025
Pay items
9
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Atlas Asphalt, Inc.$273,690Low
2Sugg Construction, Inc.$307,470+12%
3M & T Paving & Const. Co., Inc.$315,092+15%
4BTG Enterprises, LLC$320,985+17%
5Rogers Group, Inc.$341,063+25%
6Apac-Tennessee, Inc.$464,340+70%
ARDOT contract C18020: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Atlas Asphalt, Inc.2. Sugg Construction, Inc.3. M & T Paving & Const. Co., Inc.4. BTG Enterprises, LLC5. Rogers Group, Inc.6. Apac-Tennessee, Inc.
0001Aggregate base course (class 7) (303107)TON855$76.53$65.00$74.80$55.00$83.00$70.00
0002Tack coat (401011)GAL1,166$3.50$3.25$3.75$4.65$1.00$3.00
0003Mineral aggregate in achm surface course (3/8") (407161)TON1,344$111.10$119.94$128.04$140.00$95.00$198.00
0004Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON82$120.00$120.00$160.10$125.00$600.00$150.00
0005Cold milling asphalt pavement (412001)SY400$15.71$10.00$7.00$20.00$10.00$30.00
0006Achm patching of existing roadway (415011)TON130$175.00$175.00$240.00$285.00$285.00$450.00
0007Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$12,967$13,000$12,200$14,300$12,000$21,000
0008Maintenance of traffic (603009)LS1$1,000.00$35,300$13,000$8,560.00$35,000$21,000
0009Signs (604003)SF336$6.00$6.00$7.00$6.60$11.91$30.00
ARDOT contract C18020: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy