ARDOT contract C65018 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 2.02 MILES OF VARIOUS CITY STREETS IN THE CITY OF BARLING, APPROXIMATELY 1.37 MILES OF VARIOUS CITY STREETS IN THE CITY OF HARTFORD, AND APPROXIMATELY 2.57 MILES IN THE CITY OF MIDLAND IN SEBASTIAN COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, WHEELCHAIR RAMPS, AND MISC. ITEMS. Let by Arkansas DOT on April 8, 2026, Sebastian. 4 bids received; low bid $944,621 by Emery Sapp & Sons, Inc..
- Owner
- Arkansas DOT
- Letting
- 08 APR 2026
- Pay items
- 10
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Emery Sapp & Sons, Inc. | $944,621 | Low |
| 2 | Forsgren, Inc. | $1,052,577 | +11% |
| 3 | McKenzie Asphalt, LLC | $1,075,401 | +14% |
| 4 | Robinson Construction, LLC | $1,191,518 | +26% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Emery Sapp & Sons, Inc. | 2. Forsgren, Inc. | 3. McKenzie Asphalt, LLC | 4. Robinson Construction, LLC |
|---|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of curb (202001) | LF | 14 | $300.24 | $23.00 | $50.00 | $265.00 |
| 0002 | Tack coat (401011) | GAL | 6,346 | $3.38 | $3.00 | $3.75 | $4.50 |
| 0003 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 6,828 | $109.11 | $119.90 | $125.90 | $126.50 |
| 0004 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 467 | $120.00 | $120.00 | $120.00 | $120.00 |
| 0005 | Cold milling asphalt pavement (412001) | SY | 15,657 | $1.66 | $3.10 | $2.56 | $4.20 |
| 0006 | Achm patching of existing roadway (415011) | TON | 360 | $145.52 | $180.00 | $175.00 | $245.00 |
| 0007 | Maintenance of traffic (603009) | LS | 1 | $14,928 | $18,000 | $5,000.00 | $35,000 |
| 0008 | Signs (604003) | SF | 648 | $7.84 | $7.35 | $7.00 | $7.70 |
| 0009 | Wheelchair ramps (type 3) (641014) | SY | 4 | $1,680.42 | $350.00 | $400.00 | $1,880.00 |
| 0010 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $12,817 | $21,000 | $21,000 | $38,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of April 8, 2026. Compiled by Mirage Metrics.