ARDOT contract C72015 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.29 MILES OF VARIOUS CITY STREETS IN THE CITY OF GREENLAND, APPROXIMATELY 1.57 MILES OF VARIOUS CITY STREETS IN THE CITY OF LINCOLN, APPROXIMATELY 0.33 MILE OF VARIOUS CITY STREETS IN THE CITY OF TONTITOWN IN WASHINGTON COUNTY. THIS PROJECT CONSISTS OF REMOVAL AND DISPOSAL OF CURB AND GUTTER, BORROW, AGGREGATE BASE COURSE, ACHM SURFACE COURSE, COLD MILLING ASPHALT PAVEMENT, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, CONCRETE COMBINATION CURB AND GUTTER, WHEELCHAIR RAMPS, PAVEMENT MARKING AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Washington. 3 bids received; low bid $862,331 by Grant Garrett Excavating, Inc..
- Owner
- Arkansas DOT
- Letting
- 15 JAN 2025
- Pay items
- 16
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Grant Garrett Excavating, Inc. | $862,331 | Low |
| 2 | Emery Sapp & Sons, Inc. | $885,415 | +3.0% |
| 3 | Apac-Central, Inc. | $908,234 | +5.0% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Grant Garrett Excavating, Inc. | 2. Emery Sapp & Sons, Inc. | 3. Apac-Central, Inc. |
|---|---|---|---|---|---|---|
| 0001 | Removal and disposal of curb and gutter (202003) | LF | 5 | $53.57 | $19.00 | $400.00 |
| 0002 | Borrow (210412) | TON | 142 | $48.70 | $24.38 | $82.00 |
| 0003 | Aggregate base course (class 7) (303107) | TON | 828 | $54.15 | $64.74 | $38.00 |
| 0004 | Tack coat (401011) | GAL | 4,471 | $3.76 | $3.44 | $4.40 |
| 0005 | Mineral aggregate in achm surface course (3/8") (407161) | TON | 5,026 | $123.64 | $133.64 | $126.00 |
| 0006 | Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431) | TON | 338 | $120.00 | $120.00 | $120.00 |
| 0007 | Cold milling asphalt pavement (412001) | SY | 1,937 | $7.40 | $4.36 | $9.00 |
| 0008 | Achm patching of existing roadway (415011) | TON | 75 | $338.44 | $341.43 | $465.00 |
| 0009 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $40,000 | $21,096 | $40,000 |
| 0010 | Maintenance of traffic (603009) | LS | 1 | $17,244 | $25,712 | $40,000 |
| 0011 | Signs (604003) | SF | 600 | $23.81 | $7.60 | $22.25 |
| 0012 | Concrete combination curb and gutter (type A) (1' 6") (634201) | LF | 50 | $33.98 | $34.19 | $95.75 |
| 0013 | Wheelchair ramps (type 3) (641014) | SY | 4 | $483.87 | $284.88 | $1,000.00 |
| 0014 | Reflectorized paint pavement marking white (4") (718001) | LF | 5,400 | $0.77 | $0.51 | $0.70 |
| 0015 | Reflectorized paint pavement marking white (12") (718005) | LF | 445 | $5.95 | $6.96 | $5.50 |
| 0016 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 12,778 | $0.77 | $0.51 | $0.70 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.