ARDOT contract SA1067 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.60 MILES OF COUNTY ROAD 38 IN CLARK COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, AGGREGATE BASE COURSE, ACHM PATCHING OF EXISTING ROADWAY, PAVEMENT MARKING, MAINTENANCE OF TRAFFIC, AND MISC. ITEMS. Let by Arkansas DOT on May 21, 2025, Clark. 5 bids received; low bid $335,963 by Cranford Construction Co..

Owner
Arkansas DOT
Letting
21 MAY 2025
Pay items
11
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Cranford Construction Co.$335,963Low
2Redstone Construction Group, Inc.$352,380+5.0%
3Jet Asphalt & Rock Co., Inc.$372,083+11%
4Tri State Asphalt, Inc.$395,508+18%
5Sidney E Young DBA Sid and Sons$464,000+38%
ARDOT contract SA1067: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Cranford Construction Co.2. Redstone Construction Group, Inc.3. Jet Asphalt & Rock Co., Inc.4. Tri State Asphalt, Inc.5. Sidney E Young DBA Sid and Sons
0001Aggregate base course (class 7) (303117)TON253$58.28$50.50$75.25$60.00$100.00
0002Tack coat (401011)GAL1,982$0.01$2.75$0.01$6.00$3.00
0003Mineral aggregate in achm surface course (1/2") (407162)TON2,280$120.41$124.50$122.00$132.00$165.00
0004Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432)TON138$120.40$120.00$120.00$132.00$165.00
0005Achm patching of existing roadway (415011)TON50$280.82$300.00$200.00$250.00$300.00
0006Maintenance of traffic (603009)LS1$6,990.33$7,172.42$32,000$12,500$5,264.80
0007Signs (604003)SF194$11.00$7.00$7.00$7.00$10.00
0008Reflectorized paint pavement marking yellow (4") (718101)LF16,896$0.16$0.13$0.13$0.13$0.20
0009Standard sign (726002)SF48$22.00$22.00$22.00$22.00$25.00
0010Channel post sign support (type C) (729003)EACH10$86.00$85.00$85.00$85.00$100.00
0011Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$2,264.01$6,100.00$10,844$18,800$6,000.00
ARDOT contract SA1067: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of May 21, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy