ARDOT contract SA4839 bid tabulation
THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 1.01 MILES OF COUNTY ROAD 18 AND APPROXIMATELY 1.00 MILE OF COUNTY ROAD 32 IN MONROE COUNTY. THIS PROJECT CONSISTS OF ACHM SURFACE COURSE, AGGREGATE BASE COURSE, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on January 15, 2025, Monroe. 7 bids received; low bid $375,358 by Atlas Asphalt, Inc..
- Owner
- Arkansas DOT
- Letting
- 15 JAN 2025
- Pay items
- 10
- Data through
- 04 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Atlas Asphalt, Inc. | $375,358 | Low |
| 2 | Rogers Group, Inc. | $412,856 | +10% |
| 3 | M & T Paving & Const. Co., Inc. | $420,391 | +12% |
| 4 | Sugg Construction, Inc. | $436,855 | +16% |
| 5 | Redstone Construction Group, Inc. | $442,649 | +18% |
| 6 | Delta Asphalt of Arkansas, Inc. | $521,301 | +39% |
| 7 | BTG Enterprises, LLC | $521,638 | +39% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Atlas Asphalt, Inc. | 2. Rogers Group, Inc. | 3. M & T Paving & Const. Co., Inc. | 4. Sugg Construction, Inc. | 5. Redstone Construction Group, Inc. | 6. Delta Asphalt of Arkansas, Inc. |
|---|---|---|---|---|---|---|---|---|---|
| 0001 | Aggregate base course (class 7) (303117) | TON | 318 | $57.23 | $80.00 | $70.78 | $60.00 | $82.43 | $83.73 |
| 0002 | Tack coat (401011) | GAL | 2,368 | $3.50 | $1.00 | $3.73 | $3.00 | $0.10 | $4.22 |
| 0003 | Mineral aggregate in achm surface course (1/2") (407162) | TON | 2,831 | $111.36 | $55.00 | $119.88 | $118.35 | $126.50 | $116.02 |
| 0004 | Asphalt binder (PG 64-22) in achm surface course (1/2") (minimum bid $120.00) (407432) | TON | 165 | $120.00 | $1,000.00 | $153.75 | $120.00 | $120.00 | $600.00 |
| 0005 | Maintenance of traffic (603009) | LS | 1 | $1,500.00 | $40,000 | $9,000.00 | $43,300 | $13,399 | $30,000 |
| 0006 | Signs (604003) | SF | 168 | $7.00 | $8.50 | $8.00 | $7.00 | $7.35 | $7.00 |
| 0007 | Reflectorized paint pavement marking yellow (4") (718101) | LF | 5,350 | $0.40 | $0.35 | $0.45 | $0.40 | $0.42 | $0.42 |
| 0008 | Standard sign (726002) | SF | 48 | $22.00 | $36.50 | $25.00 | $22.00 | $23.10 | $22.00 |
| 0009 | Channel post sign support (type C) (729003) | EACH | 10 | $75.00 | $129.00 | $85.00 | $75.00 | $78.75 | $75.00 |
| 0010 | Mobilization (unit bid amount may not exceed 5% of subtotal) (601001) | LS | 1 | $7,189.00 | $18,000 | $9,500.00 | $7,400.00 | $19,500 | $22,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.
Every contract let that day: ARDOT letting of January 15, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.