ARDOT contract SA7634 bid tabulation

THE PURPOSE OF THIS PROJECT IS TO OVERLAY APPROXIMATELY 0.53 MILE OF COUNTY ROADS 262 & 55 IN NEVADA & HEMPSTEAD COUNTIES. THIS PROJECT CONSISTS OF AGGREGATE BASE COURSE, ACHM SURFACE COURSE, ACHM PATCHING OF EXISTING ROADWAY, MAINTENANCE OF TRAFFIC, PAVEMENT MARKING, AND MISC. ITEMS. Let by Arkansas DOT on June 25, 2025, Hempstead, Nevada. 4 bids received; low bid $159,465 by Redstone Construction Group, Inc..

Owner
Arkansas DOT
Letting
25 JUN 2025
Pay items
9
Data through
04 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Redstone Construction Group, Inc.$159,465Low
2Tri State Asphalt, Inc.$161,355+1.0%
3Cranford Construction Co.$177,098+11%
4Sidney E Young DBA Sid and Sons$222,254+39%
ARDOT contract SA7634: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Redstone Construction Group, Inc.2. Tri State Asphalt, Inc.3. Cranford Construction Co.4. Sidney E Young DBA Sid and Sons
0001Aggregate base course (class 7) (303117)TON84$60.00$65.00$122.53$80.00
0002Tack coat (401011)GAL703$4.25$6.00$4.35$0.01
0003Mineral aggregate in achm surface course (3/8") (407161)TON775$142.24$135.00$154.15$203.00
0004Asphalt binder (PG 64-22) in achm surface course (3/8") (minimum bid $120.00) (407431)TON50$120.00$135.00$120.00$200.00
0005Achm patching of existing roadway (415011)TON80$250.00$200.00$247.87$400.00
0006Maintenance of traffic (603009)LS1$3,500.00$12,000$9,112.40$1,500.00
0007Signs (604003)SF96$14.00$14.00$13.00$14.00
0008Reflectorized paint pavement marking yellow (4") (718101)LF5,596$0.60$0.60$0.38$0.60
0009Mobilization (unit bid amount may not exceed 5% of subtotal) (601001)LS1$7,000.00$7,600.00$5,964.73$10,000
ARDOT contract SA7634: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ARDOT's tabulation for this contract. ARDOT monthly bid tab PDFs (morning and afternoon sessions), January 2022 to November 2026. Base bids are printed in whole dollars; on A+B and A+C jobs the base bid is kept, and the published rank follows the award amount.

Every contract let that day: ARDOT letting of June 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy