CDOT contract C27164 bid tabulation

SH053A, SH095A, SH287C. Let by Colorado DOT on September 10, 2026, Adams, Denver, and Jefferson, Region 1. 8 bids received; low bid $925,986 by Jalisco International, Inc., -7.4% against the engineer's estimate of $1,000,000.

Owner
Colorado DOT
Letting
10 SEP 2026
Pay items
73
Data through
10 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Jalisco International, Inc.$925,986Low-7.0%
2CONCRETE EXPRESS, INC.dba CEI$1,099,971+19%+10%
3KSK, LLC$1,125,000+21%+12%
4Rodriguez Construction Org., LLC$1,167,182+26%+17%
5Goodland Construction, Inc.$1,294,029+40%+29%
6Chato'S Concrete, LLC$1,306,199+41%+31%
7Concrete Works of Colorado, Inc.$1,362,866+47%+36%
8Noraa Concrete Construction Corporation$1,390,209+50%+39%
CDOT contract C27164: bids by rank

Engineer's estimate: $1,000,000.

Bid tabulation

LinePay itemUnitQuantityEstimate1. Jalisco International, Inc.2. CONCRETE EXPRESS, INC.dba CEI3. KSK, LLC4. Rodriguez Construction Org., LLC5. Goodland Construction, Inc.6. Chato'S Concrete, LLC
1Removal of delineator (202-00090)EACH6$30.89$52.00$30.00$20.00$120.00$92.70$100.00
2Removal of sidewalk (202-00200)SY390$35.00$21.00$25.20$19.00$39.75$36.00$30.00
3Removal of curb and gutter (202-00203)LF627$16.89$16.00$15.00$11.50$15.00$15.10$20.00
4Removal of concrete curb ramp (202-00206)SY449$43.81$40.00$47.85$21.00$45.00$36.00$31.00
5Removal of concrete pavement (202-00210)SY187$54.58$85.00$30.60$22.00$55.00$46.00$32.00
6Removal of asphalt mat (202-00220)SY28$26.04$115.00$18.00$17.00$37.88$33.00$29.00
7Removal of pull box (202-00827)EACH9$245.09$375.00$785.00$500.00$445.00$568.00$575.00
8Removal of detectable warning (202-00889)EACH5$420.28$470.00$150.00$320.00$1,290.00$129.00$500.00
9Clean valve box (202-04005)EACH1$1,000.00$940.00$1,300.00$200.00$800.00$635.00$500.00
10Unsuitable material (203-00050)CY100$100.66$48.00$110.00$45.00$125.00$120.00$100.00
11Front end loader (rubber tire) (203-01590)HR20$131.87$135.00$185.00$20.00$175.00$187.50$250.00
12Potholing (203-01597)HR20$216.02$250.00$280.00$100.00$348.00$341.00$500.00
13Sweeping (203-01620)HR20$129.82$180.00$310.00$20.00$150.00$336.00$350.00
14Structure backfill (flowable fly ash) (206-00066)CY2.50$592.49$400.00$1,210.00$365.00$500.00$1,000.00$600.00
15Topsoil (207-00205)CY15$138.13$95.00$130.00$110.00$40.00$243.00$120.00
16Erosion control (curb ramp) (208-00090)EACH39$437.15$500.00$285.00$500.00$999.09$409.00$1,200.00
17Reset monument (type 3A) (210-00065)EACH5$500.00$1,200.00$505.00$200.00$2,000.00$2,841.00$500.00
18Reset ground sign (210-00810)EACH5$370.98$240.00$230.00$750.00$370.00$812.50$300.00
19Reset pedestal pole (210-00858)EACH5$1,317.86$2,100.00$1,050.00$4,600.00$1,840.00$2,398.00$6,500.00
20Modify pedestrian push button (210-00859)EACH1$963.49$535.00$525.00$1,200.00$1,115.00$455.00$1,700.00
21Reset pedestrian push button (210-00860)EACH24$221.11$375.00$290.00$500.00$409.00$455.00$530.00
22Reset sprinkler head (210-01700)EACH15$91.29$80.00$65.00$50.00$250.00$92.00$65.00
23Relay sprinkler system (210-02510)LS1$20,000$5,400.00$15,000$1,500.00$3,000.00$13,023$5,000.00
24Adjust manhole (210-04010)EACH2$1,004.69$800.00$1,715.00$1,100.00$1,425.00$1,337.00$1,000.00
25Modify inlet (210-04020)EACH1$5,924.16$2,600.00$2,410.00$4,300.00$1,350.00$6,725.00$15,000
26Adjust valve box (210-04050)EACH1$1,591.77$600.00$1,065.00$1,050.00$1,350.00$1,135.00$750.00
27Sod (212-00050)SF1,000$2.50$3.00$2.20$3.00$8.00$3.50$5.00
28Rock mulch (weed free) (213-00067)SF100$10.10$7.00$8.00$25.00$1,000.00$17.50$15.00
29Aggregate base course (class 6) (304-06000)TON200$60.00$77.00$41.95$70.00$100.00$91.80$70.00
30Hot mix asphalt (patching) (asphalt) (403-00721)SY89$234.94$175.00$85.00$95.00$200.00$321.00$300.00
31Concrete pavement (patching) (412-00190)SY184$220.51$120.00$161.55$142.00$134.00$299.00$150.00
32Fence (plastic) (607-11525)LF500$4.44$4.00$3.50$1.00$12.00$7.70$10.00
33Concrete sidewalk (608-00000)SY435$118.31$87.00$90.85$104.50$115.55$130.50$113.00
34Concrete curb ramp (608-00010)SY731$140.00$210.00$230.00$178.00$176.19$189.00$162.00
35Detectable warnings (608-00015)SF8$99.20$55.00$50.95$90.00$75.00$82.00$100.00
36Curb type 2 (section B) (609-20010)LF19$67.97$80.00$25.00$44.00$42.00$60.60$63.00
37Curb type 2 (section M) (609-20011)LF100$28.66$90.00$38.00$44.00$42.00$61.00$60.00
38Curb and gutter type 2 (section I-B) (609-21010)LF265$52.80$47.00$29.00$44.00$47.64$58.60$57.00
39Curb and gutter type 2 (section II-B) (609-21020)LF385$54.76$44.00$37.65$44.00$47.84$61.00$59.00
40Delineator (type I) (612-00001)EACH1$55.29$44.00$60.00$30.00$300.00$91.00$175.00
41Delineator (type II) (612-00002)EACH1$49.06$47.00$70.00$35.00$300.00$91.00$185.00
42Delineator (type III) (612-00003)EACH6$75.70$49.00$81.50$40.00$300.00$91.00$200.00
432 inch electrical conduit (613-00200)LF600$38.14$32.00$42.90$36.50$23.77$54.90$50.00
44Type one pull box (613-07001)EACH1$1,047.01$720.00$1,395.00$1,400.00$1,356.00$1,420.50$1,700.00
45Type two pull box (613-07002)EACH6$1,263.10$800.00$1,740.00$1,700.00$1,777.00$1,738.70$2,400.00
46Type three pull box (613-07003)EACH2$2,100.54$850.00$1,855.00$2,225.00$2,129.50$2,125.00$3,000.00
47Type four pull box (613-07004)EACH1$2,080.83$1,385.00$2,550.00$3,100.00$2,958.00$2,875.00$3,700.00
48Type five pull box (613-07005)EACH1$2,530.78$1,900.00$3,420.00$3,600.00$3,410.00$3,852.30$4,800.00
49Wiring (613-10000)LS1$10,000$3,300.00$21,000$14,000$11,685$20,660$18,000
50Accessible pedestrian signal (614-70200)EACH24$2,182.50$1,600.00$1,335.00$1,000.00$1,371.00$1,579.60$1,780.00
51Pedestrian push button (614-72860)EACH1$274.76$1,150.00$550.00$1,800.00$990.00$568.20$2,900.00
52Pedestrian push button post assembly (614-72863)EACH20$1,855.92$1,600.00$2,150.00$5,200.00$1,927.50$3,636.40$6,500.00
53Field office (class 1) (620-00001)EACH1$14,428$45,000$31,500$21,000$45,000$15,000$60,000
54Field laboratory (class 1) (620-00011)EACH1$20,000$33,000$21,500$21,000$45,000$15,000$41,000
55Sanitary facility (620-00020)EACH3$2,957.77$1,400.00$950.00$50.00$2,000.00$3,977.30$2,000.00
56Construction surveying (hourly) (625-00001)HR25$365.47$265.00$180.00$2,000.00$500.00$301.20$300.00
57Mobilization (626-00000)LS1$59,545$90,000$143,000$181,599$80,000$253,000$52,000
58Public information services (tier IV) (626-01104)LS1$8,500.00$3,500.00$4,100.00$4,000.00$3,995.00$5,171.00$9,500.00
59Pavement marking paint (high build) (627-00013)GAL10$140.79$105.00$120.00$425.00$100.00$313.00$300.00
60Preformed thermoplastic pavement marking (xwalk-stop line) (627-30410)SF2,320$19.53$13.00$20.30$16.50$12.50$16.10$30.00
61Flagging (630-00000)HR1,000$35.00$42.00$44.05$25.00$38.00$51.20$50.00
62Traffic control inspection (630-00007)DAY26$850.00$145.00$350.00$275.00$140.00$255.70$500.00
63Traffic control management (630-00012)DAY50$1,000.00$1,200.00$1,725.00$3,500.00$1,125.00$1,716.00$1,000.00
64Barricade (type 3 M-A) (temporary) (630-80335)EACH6$112.93$160.00$12.00$10.00$10.00$56.90$500.00
65Pedestrian barricade (ADA) (630-80340)LF400$39.56$16.00$7.00$45.00$6.00$39.80$20.00
66Construction traffic sign (panel size A) (630-80341)EACH84$52.14$43.00$5.80$5.00$25.00$28.50$100.00
67Construction traffic sign (panel size B) (630-80342)EACH50$63.56$43.00$5.80$5.00$35.00$39.80$125.00
68Vertical panel (630-80350)EACH100$30.12$21.00$5.80$50.00$5.00$39.80$125.00
69Portable message sign panel (630-80355)EACH6$5,672.45$2,100.00$1,150.00$100.00$981.00$3,977.30$5,000.00
70Advance warning flashing or sequencing arrow panel (C type) (630-80358)EACH6$1,274.53$1,250.00$580.00$100.00$500.00$1,108.00$1,500.00
71Drum channelizing device (630-80360)EACH20$62.86$21.00$7.00$50.00$6.00$28.50$75.00
72Traffic cone (630-80380)EACH150$9.07$14.00$7.00$10.00$6.00$8.00$50.00
73Mobile attenuator (630-85020)EACH3$30,655$11,500$40,500$500.00$45,000$10,000$33,000
CDOT contract C27164: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from CDOT's tabulation for this contract. CDOT Tabulation of Bids PDFs from its bid tab archive, May 2023 to September 2026 (each contract linked to its OnBase document), and four December 2025 lettings read by OCR. About 100 tabulations of late 2025 and 2026 are printed in a font without text and are not read yet. On A+B contracts the cost part is kept. Bids that did not match their published total are left out.

Every contract let that day: CDOT letting of September 10, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy