CDOT letting results, November 21, 2024
8 contracts let by Colorado DOT on November 21, 2024, $48,855,623 in low bids, a median of 3.5 bidders per contract. On the 8 with an engineer's estimate, the low bid came in under it 6 times; median low bid -7.0% against the estimate.
- Owner
- Colorado DOT
- Contracts
- 8
- Low bids, total
- $48,855,623
- Data through
- 10 SEP 2026
Contracts let that day
| Contract | Project | Region | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| C20624 | This project is located in Region 5, on SH 112 between mileposts 0 (Junction of US 160) and 13.2 (Junction of US 285) in Rio Grande County. The project consists | Region 5 | 2 | Oldcastle SW Group, Inc. | $12,655,932 | $12,759,312 | +1.0% | -6.0% | CDOT |
| C25095 | US 285 FROM MP 220-228.8 | Region 2 | 3 | Brannan Sand and Gravel, LLC | $12,489,800 | $13,277,623 | +6.0% | -4.0% | CDOT |
| C22834 | This project is located on US 160 between mileposts 258.4 and 264.9 in Costilla county. The project will construct acceleration and deceleration lanes at the Tr | Region 5 | 7 | Capital Paving & Construction, LLC | $11,153,848 | $11,894,870 | +7.0% | -38% | CDOT |
| C25058 | THIS PROJECT IS A BRIDGE PREVENTATIVE MAINTENANCE PROJECT OF 10 STRUCTURES IN REGION 4. STRUCTURES G-22-BD AND G-22-BE ON I-70 WILL RECIEVE REMOVAL OF EXISTING | Region 4 | 4 | Structures, Inc. | $5,219,633 | $5,774,116 | +11% | +9.0% | CDOT |
| C25250 | SH 7 AND AIRPORT DR INTERSECTION | Region 1 | 4 | Jalisco International, Inc. | $4,195,724 | $4,426,900 | +6.0% | -7.0% | CDOT |
| C25644 | THIS ROCKFALL MITIGATION PROJECT WILL BE ALONG SH 82 IN GARFIELD COUNTY. THE ROCKFALL MITIFAITON WORK WILL BE PREFORMED EAST OF THE SH 133 AND SH 82 INTERSECTIO | Region 3 | 7 | Rock Supremacy LLC | $1,589,246 | $1,655,373 | +4.0% | -15% | CDOT |
| C25334 | RAILROAD AND ROADWAY IMPROVEMENTS AT CR U AND CR 31 NEAR BRUSH IN MORGAN COUNTY. WORK CONSISTS OF REPLACING AT-GRADE CROSSINGS AND SURFACE IMPROVEMENTS. | Region 4 | 2 | AB Underground | $1,016,441 | $1,397,091 | +37% | -14% | CDOT |
| C25588 | 12TH AND WADSWORTH SE QUADRANT | Region 1 | 2 | HCG Construction LLC | $535,000 | $729,207 | +36% | +7.0% | CDOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than CDOT received, the others did not match their published totals and are left out.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.