FDOT contract T2996 bid tabulation

SR 200 (US 301) FROM SR 20 TO SR 26. Let by Florida DOT on January 29, 2025, Alachua, District 2. 3 bids received; low bid $12,465,172 by Anderson Columbia Co., Inc..

Owner
Florida DOT
Letting
29 JAN 2025
Pay items
83
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Anderson Columbia Co., Inc.$12,465,172Low
2Preferred Materials Inc.$14,411,283+16%
3Whitehurst, V. E. & Sons, Inc.$16,030,353+29%
FDOT contract T2996: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Anderson Columbia Co., Inc.2. Preferred Materials Inc.3. Whitehurst, V. E. & Sons, Inc.
0005Concrete class IV, bridge substructure (0400-4-5)CY6.60$5,866.04$4,772.72$27,850
0010Reinforcing steel- bridge substructure (0415-1-5)LB2,680$11.55$9.40$13.50
0015Mobilization (0101-1)LS1$499,042$442,588$1,271,231
0020Maintenance of traffic (0102-1)DA1$395,143$441,604$992,375
0025Special detour- temporary pavement (0102-2200)SY1$9,013.25$17,950$15,000
0030Traffic control officer (0102-14)HR2,750$110.62$130.00$125.00
0035Work zone sign (0102-60)ED13,900$0.31$0.25$0.27
0040Temporary barrier, F&I, low profile, concrete (0102-71-13)LF1,777$50.40$36.00$44.10
0045Temporary barrier, F&I, anchored (0102-71-15)LF1,452$46.71$35.80$40.85
0050Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED29,300$0.12$0.12$0.11
0055Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD33,542$0.07$0.07$0.07
0060Arrow board / advance warning arrow panel (0102-76)ED500$6.15$4.75$5.40
0065Temporary crash cushion, redirective option (0102-89-1)LO7$2,703.97$1,090.00$1,290.00
0070Portable changeable message sign, temporary (0102-99)ED650$12.29$11.00$10.75
0075Sediment barrier (0104-10-3)LF90,788$2.62$0.95$2.00
0080Inlet protection system (0104-18)EACH72$153.64$100.00$125.00
0085Litter removal (0107-1)ACRE1,620$61.46$50.00$80.65
0090Mowing (0107-2)ACRE1,260$28.27$70.00$188.20
0095Clearing & grubbing (0110-1-1)ACRE1$144,641$170,039$156,280
0100Removal of existing concrete (0110-4-10)SY456$46.13$37.53$69.40
0105Regular excavation (0120-1)CY425$223.11$98.66$50.00
0110Embankment (0120-6)CY210$45.89$132.04$50.00
0115Type B stabilization (0160-4)SY1,246$6.62$47.39$30.00
0120Optional base, base group 01 (0285-701)SY1,993$15.39$31.60$21.20
0125Optional base, base group 09 (0285-709)SY1,218$44.22$66.03$30.00
0130Milling existing asphalt pavement, 3 1/2" avg depth (0327-70-2)SY5,340$4.25$6.39$2.88
0135Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY10,768$3.06$5.04$1.92
0140Milling existing asphalt pavement, 4" avg depth (0327-70-7)SY3,196$4.52$9.22$3.15
0145Milling existing asphalt pavement, 2 1/4" avg depth (0327-70-11)SY36,302$4.16$4.82$2.24
0150Milling existing asphalt pavement, 2 3/4" avg depth (0327-70-15)SY236,369$3.16$3.19$2.51
0155Milling existing asphalt pavement, 1/2" avg depth (0327-70-16)SY9,161$3.70$6.77$1.44
0160Milling existing asphalt pavement, 3/4" avg depth (0327-70-19)SY60,357$2.18$2.70$1.55
0165Superpave asphaltic conc, traffic E (0334-1-15)TN755.70$184.20$226.19$175.03
0170Superpave asphaltic concrete, traffic E, high polymer (0334-1-59)TN30,110.70$165.12$200.60$207.54
0175Asphalt concrete friction course, inc bit, FC-5, high polymer (0337-7-26)TN13,267.30$183.27$240.96$235.14
0180Asphalt concrete friction course,traffic E, FC-12.5, high polymer (0337-7-95)TN1,651.30$174.56$256.62$207.54
0185Manhole, adjust (0425-5)EACH2$1,782.16$1,856.00$2,446.00
0190Mitered end section, optional round, 42" CD (0430-982140)EACH1$8,210.53$15,362$9,785.00
0195Mitered end section, optional round, 15" SD (0430-984123)EACH1$6,981.44$5,500.00$2,420.00
0200Mitered end section, optional round, 18" SD (0430-984125)EACH1$5,106.96$6,600.00$3,070.00
0205Mitered end section, optional round, 24" SD (0430-984129)EACH4$5,106.96$8,778.00$3,335.00
0210Mitered end section , optional round, 30" SD (0430-984133)EACH1$5,721.50$10,973$8,170.00
0215Concrete curb & gutter, type F (0520-1-10)LF931$52.22$42.48$93.80
0220Traffic separator concrete- type IV, 4' wide (0520-5-41)LF411$93.09$75.74$218.50
0225Concrete sidewalk and driveways, 6" thick (0522-2)SY60$88.16$71.73$175.00
0230Concrete ditch pavement, non reinforced, 4" (0524-1-2)SY50$88.08$71.66$212.00
0235Riprap, rubble, F&I, ditch lining (0530-3-4)TN71$189.52$126.00$450.00
0240Bedding stone (0530-74)TN25.30$445.47$144.43$427.00
0245Raised rumble strip set- permanent (0546-71-1)EACH4$553.08$450.00$700.00
0250Performance turf, sod (0570-1-2)SY59,212$2.32$2.70$2.90
0255Raised pavement marker, type B (0706-1-3)EACH781$6.15$5.00$5.40
0260Painted pavement markings, standard, white, solid, 6" (0710-11101)GM64.49$1,474.90$1,200.00$1,990.00
0265Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide (0710-11131)GM37.76$921.80$750.00$995.00
0270Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" (0710-11141)GM0.41$921.80$750.00$1,237.00
0275Painted pavement markings, standard, white, message or symbol (0710-11160)EACH2$92.18$75.00$269.00
0280Painted pavement markings, standard, white, arrows (0710-11170)EACH14$61.45$50.00$53.75
0285Painted pavement markings, standard, yellow, solid, 6" (0710-11201)GM44.88$1,474.90$1,200.00$1,990.00
0290Painted pavement markings, standard, yellow, 2-4 dotted guideline/6-10 dotted extension, 6" (0710-11241)GM0.15$921.80$750.00$1,240.00
0295Initial contingency amount, DO not bid (0999-25)LS1$150,000$150,000$150,000
0300Ground-in rumble strips, 8" sinusoidal (0546-72-3)GM26.31$1,898.92$1,682.28$2,000.00
0305Prestressed concrete pole, shallow pole removal- pole 30' and greater (0641-2-70)EACH2$28,702$7,865.00$8,455.00
0310Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH52$479.34$559.00$600.00
0315Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH6$2,703.97$2,213.00$2,380.00
0320Single column ground sign assembly, F&I ground mount, 30.0 SF (0700-1113)EACH5$3,072.69$2,605.00$2,800.00
0325Single column ground sign assembly, remove (0700-1600)EACH12$61.45$40.00$43.00
0330Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH1$184.35$188.00$203.00
0335Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH32$153.64$91.00$96.75
0340Tubular marker, 36" yellow (0704-1-4)EACH5$184.35$200.00$214.00
0345Raised pavement marker, type B (0706-1-3)EACH2,741$6.15$5.00$5.40
0350Painted pavement markings, surface (0710-90)LS1$98,314$79,990$120,400
0355Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF290$6.15$5.00$4.75
0360Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF476$7.99$6.50$7.10
0365Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF322$9.83$8.00$9.50
0370Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM0.18$2,703.97$2,200.00$2,957.00
0375Thermoplastic, standard, arrow (0711-11170)EACH294$79.89$65.00$148.00
0380Thermoplastic, preformed, white, message (0711-14160)EACH9$245.81$200.00$236.50
0385Thermoplastic, preformed, white, arrow (0711-14170)EACH9$165.93$135.00$118.50
0390Thermoplastic, standard-open graded asphalt surfaces solid, 6" (0711-15101)GM20.60$6,391.19$5,200.00$6,030.75
0395Thermoplastic, standard-open graded asphalt surfaces, skip, 6",10-30 skip or 3-9 lane (0711-15131)GM16.59$2,826.88$2,300.00$1,892.00
0400Thermoplastic, standard-open graded asphalt surfaces, yellow, solid, 6" (0711-15201)GM15.84$6,391.19$5,200.00$6,030.00
0405Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM1.28$5,899.57$4,800.00$5,795.00
0410Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM0.74$2,703.97$2,200.00$1,775.00
0415Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM0.72$5,899.57$4,800.00$5,795.00
FDOT contract T2996: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy