FDOT contract T3940 bid tabulation

SR 61 (US 319 / CRAWFORDVILLE RD) FROM S OF SR 61 SB TO... Let by Florida DOT on July 30, 2025, Leon, District 3. 4 bids received; low bid $4,249,828 by C.W. Roberts Contracting, Inc..

Owner
Florida DOT
Letting
30 JUL 2025
Pay items
95
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1C.W. Roberts Contracting, Inc.$4,249,828Low
2Peavy & Son Construction Co., Inc.$4,588,356+8.0%
3Pigott Asphalt and Sitework LLC$4,891,848+15%
4Capital Asphalt Inc$5,647,786+33%
FDOT contract T3940: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. C.W. Roberts Contracting, Inc.2. Peavy & Son Construction Co., Inc.3. Pigott Asphalt and Sitework LLC4. Capital Asphalt Inc
0005Mobilization (0101-1)LS1$140,000$425,000$300,000$550,000
0010Maintenance of traffic (0102-1)DA1$225,000$280,000$187,500$450,000
0015Traffic control officer (0102-14)HR216$100.00$80.00$100.00$105.00
0020Work zone sign (0102-60)ED22,706$0.40$0.20$0.30$0.40
0025Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED14,979$0.10$0.11$0.01$0.15
0030Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD924$0.10$0.11$1.00$0.15
0035Arrow board / advance warning arrow panel (0102-76)ED125$8.00$5.25$1.00$5.25
0040Portable changeable message sign, temporary (0102-99)ED1,426$20.00$10.50$1.00$19.00
0045Temporary signalization and maintenance, intersection (0102-104)ED560$16.00$26.25$26.00$11.00
0050Temporary traffic detection and maintenance, intersection (0102-107-1)ED560$16.00$23.10$24.00$11.00
0055Type III barricade (0102-115)ED250$0.10$0.28$1.00$0.15
0060Temporary raised rumble per day, includes all sets and relocations (0102-909)DA560$8.20$52.50$25.00$8.00
0065Sediment barrier (0104-10-3)LF1,057$2.40$55.00$3.00$10.00
0070Inlet protection system (0104-18)EACH131$82.00$200.00$150.00$250.00
0075Litter removal (0107-1)ACRE348.20$45.00$70.00$10.00$75.00
0080Mowing (0107-2)ACRE348.20$35.00$70.00$50.00$75.00
0085Clearing & grubbing (0110-1-1)ACRE1$39,500$7,500.00$26,500$10,000
0090Removal of existing concrete (0110-4-10)SY435$38.00$50.00$35.00$80.00
0095Milling existing asphalt pavement, 2" avg depth (0327-70-5)SY66,403$3.00$1.75$3.00$3.00
0100Milling existing asphalt pavement, 1 1/2" avg depth (0327-70-6)SY27,809$4.00$1.00$3.00$4.00
0105Milling existing asphalt pavement, 2 3/4" avg depth (0327-70-15)SY45,039$3.00$1.75$3.00$3.00
0110Superpave asphaltic concrete, traffic C, PG76-22 (0334-1-53)TN3,096.40$148.00$150.00$175.00$183.00
0115Asphalt concrete friction course,traffic C, FC-12.5, PG (0337-7-83)TN13,314.30$148.00$150.00$180.00$183.00
0120Inlets, curb type P-1, partial (0425-1315)EACH1$10,000$10,000$6,500.00$15,000
0125Inlets, curb, type P-5, partial (0425-1355)EACH2$8,500.00$10,000$6,900.00$12,000
0130Manhole, adjust (0425-5)EACH4$1,300.00$2,200.00$1,250.00$1,700.00
0135Manhole, adjust, utilities (0425-5-1)EACH43$1,300.00$2,200.00$1,250.00$1,700.00
0140Valve boxes, adjust (0425-6)EACH62$655.00$1,000.00$850.00$800.00
0145Mitered end section, optional round, 24" SD (0430-984129)EACH1$5,000.00$4,500.00$3,600.00$7,500.00
0150Concrete curb & gutter, type F (0520-1-10)LF370$50.00$60.00$65.00$78.00
0155Concrete sidewalk and driveways, 4" thick (0522-1)SY219$100.00$80.00$90.00$130.00
0160Concrete sidewalk and driveways, 6" thick (0522-2)SY118$110.00$100.00$130.00$155.00
0165Detectable warnings (0527-2)SF225$37.00$35.70$40.00$35.00
0170Performance turf, sod (0570-1-2)SY2,642$3.75$6.00$4.00$7.50
0175Raised pavement marker, type B TTCP (0706-1-3)EACH1,412$4.35$4.20$5.00$4.25
0180Painted pavement markings, standard, white, solid, 6" TTCP (0710-11101)GM4.89$1,600.00$1,575.00$1,500.00$1,575.00
0185Painted pavement markings, standard, white, solid for interchange and urban island, (0710-11102)GM0.09$1,800.00$1,838.00$2,500.00$1,800.00
0190Painted pavement markings, standard, white, solid for crosswalk and roundabout, 12" TTCP (0710-11123)LF4,509$2.75$2.63$2.50$2.60
0195Painted pavement markings, standard, white, solid for stop line or crosswalk, 24" TTCP (0710-11125)LF817$3.30$3.15$3.00$3.25
0200Painted pavement markings, standard, white, skip, 10-30 or skip, 6" wide TTCP (0710-11131)GM2.92$1,200.00$1,155.00$1,200.00$1,155.00
0205Painted pavement markings, standard, white, 2-4 dotted guideline/ 6-10 dotted 6" TTCP (0710-11141)GM1.37$1,250.00$1,208.00$1,200.00$1,200.00
0210Painted pavement markings, standard, white, message or symbol TTCP (0710-11160)EACH49$60.00$58.00$60.00$57.00
0215Painted pavement markings, standard, white, arrows TTCP (0710-11170)EACH141$50.00$48.00$50.00$47.00
0220Painted pavement markings, standard, yellow, solid, 6" TTCP (0710-11201)GM2.79$1,600.00$1,575.00$1,500.00$1,575.00
0225Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000$50,000$50,000
0230Raised rumble strip set- permanent (0546-71-1)EACH4$1,800.00$1,733.00$1,800.00$1,700.00
0235Single column ground sign assembly, F&I ground mount, than 12 SF (0700-1111)EACH68$475.00$410.00$400.00$450.00
0240Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH16$1,800.00$1,890.00$1,800.00$1,785.00
0245Single column ground sign assembly, remove (0700-1600)EACH10$30.00$52.50$100.00$31.00
0250Single column ground sign assembly, F&I cantilever mount, 30.1+ SF (0700-1914)EACH1$3,500.00$4,150.00$5,000.00$3,400.00
0255Multi-column ground sign assembly, remove (0700-2600)EACH6$550.00$368.00$500.00$575.00
0260Sign panel, furnish & install ground mount, UP to 12 SF (0700-3101)EACH45$175.00$105.00$100.00$180.00
0265Sign panel, relocate, UP to 12 SF (0700-3501)EACH1$30.00$58.00$100.00$31.50
0270Sign panel, remove, UP to 12 SF (0700-3601)EACH28$30.00$42.00$50.00$31.50
0275Retroreflective sign strip- furnish and install, 5' (0700-13-15)EACH54$50.00$116.00$150.00$52.00
0280Tubular marker, 36" yellow (0704-1-4)EACH62$120.00$215.00$200.00$115.00
0285Object marker, type 1 (0705-10-1)EACH8$225.00$273.00$250.00$225.00
0290Raised pavement marker, type B (0706-1-3)EACH2,855$4.35$4.20$4.50$4.25
0295Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF495$3.30$3.15$3.00$3.25
0300Painted pavement markings, surface (0710-90)LS1$65,000$65,331$65,000$65,000
0305Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF5,887$5.50$5.25$5.00$5.25
0310Thermoplastic, standard, solid, 18" for diagonals and chevrons (0711-11124)LF134$7.00$6.30$8.00$6.25
0315Thermoplastic, standard, solid, 24" for stop line and crosswalk (0711-11125)LF308$8.00$7.35$8.00$7.25
0320Thermoplastic, standard, 2-4 dotted guideline/ 6-10 gap extension, 6" (0711-11141)GM2.10$5,000.00$4,950.00$5,000.00$4,900.00
0325Thermoplastic, standard, message or symbol (0711-11160)EACH2$275.00$278.00$250.00$275.00
0330Thermoplastic, standard, arrow (0711-11170)EACH153$90.00$90.00$85.00$89.00
0335Thermoplastic, standard, yellow, solid, 18" for diagonal or chevron (0711-11224)LF14$7.00$6.30$12.00$6.25
0340Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF1,137$15.00$14.70$14.00$14.50
0345Thermoplastic, preformed, white, message (0711-14160)EACH86$170.00$163.00$175.00$160.00
0350Thermoplastic, preformed, white, arrow (0711-14170)EACH86$100.00$105.00$100.00$105.00
0355Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM12.02$6,300.00$6,248.00$6,000.00$6,200.00
0360Thermoplastic, standard-other surfaces, white, solid, 8" (0711-16102)GM0.35$9,250.00$9,093.00$8,500.00$9,000.00
0365Thermoplastic, standard-other surfaces, white, skip, 6",10-30 or 3-9 lane drop (0711-16131)GM6.44$2,500.00$2,484.00$2,500.00$2,475.00
0370Thermoplastic, standard-other surfaces, yellow, solid, 6" (0711-16201)GM6.69$6,300.00$6,138.00$6,000.00$6,000.00
0375Permanent tape, white, solid, 6" for concrete bridges (0713-103101)GM0.10$48,000$46,410$50,000$46,000
0380Permanent tape, white, 10-30 6" wide, for concrete surfaces (0713-103181)GM0.05$13,000$11,550$50,000$12,000
0385Permanent tape, yellow, solid, for concrete bridges (0713-103201)GM0.05$46,000$4,515.00$50,000$45,000
0390Permanent tape, black, 10-30 6" wide, for concrete surfaces (0713-103381)GM0.04$12,000$11,550$50,000$12,000
0395Conduit, furnish & install, open trench (0630-2-11)LF562$19.50$18.90$20.00$15.75
0400Conduit, furnish & install, directional bore (0630-2-12)LF130$53.00$52.50$60.00$58.00
0405Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$4,500.00$11,025$11,500$12,500
0410Signal cable, remove- intersection (0632-7-6)PI1$300.00$1,575.00$1,650.00$3,000.00
0415Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH8$1,000.00$1,785.00$1,800.00$1,600.00
0420Aluminum signals pole, (0646-1-11)EACH1$2,100.00$3,360.00$3,500.00$3,200.00
0425Aluminum signals pole, furnish install pedestrian detector post (0646-1-12)EACH1$600.00$2,310.00$2,600.00$1,300.00
0430Aluminum signals pole, remove (0646-1-60)EACH2$300.00$840.00$1,000.00$125.00
0435Vehicular traffic signal, furnish & install 3 section, 1 way (0650-1-34)AS2$1,650.00$2,625.00$2,750.00$2,200.00
0440Vehicular traffic signal, furnish & install 4 section, 1 way (0650-1-36)AS2$2,000.00$3,150.00$3,250.00$2,650.00
0445Vehicular traffic signal, remove- poles to remain (0650-1-60)AS2$200.00$525.00$750.00$130.00
0450Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS1$900.00$1,575.00$1,750.00$1,625.00
0455Loop detector inductive, F&I, type 10 (0660-1110)EACH6$500.00$473.00$600.00$575.00
0460Loop assembly- F&I, type A (0660-2101)AS10$1,500.00$1,943.00$2,000.00$2,100.00
0465Loop assembly, F&I, type B (0660-2102)AS24$1,250.00$1,838.00$1,900.00$3,150.00
0470Loop assembly, F&I, type F (0660-2106)AS7$1,700.00$2,310.00$2,500.00$4,200.00
0475Pedestrian detector, furnish & install, standard (0665-1-11)EACH2$400.00$473.00$600.00$525.00
FDOT contract T3940: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of July 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way