FDOT contract T3963 bid tabulation

SR 291 (N DAVIS HWY) AT LANGLEY AVE. Let by Florida DOT on April 30, 2025, Escambia, District 3. 2 bids received; low bid $1,168,510 by Ingram Signalization, Inc..

Owner
Florida DOT
Letting
30 APR 2025
Pay items
55
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Ingram Signalization, Inc.$1,168,510Low
2Signal Technology and Installation Corp.$1,438,688+23%
FDOT contract T3963: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Ingram Signalization, Inc.2. Signal Technology and Installation Corp.
0005Mobilization (0101-1)LS1$82,000$463,296
0010Maintenance of traffic (0102-1)DA1$55,000$62,456
0015Traffic control officer (0102-14)HR288$100.00$97.08
0020Work zone sign (0102-60)ED3,298$1.10$0.54
0025Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED7,635$0.50$0.27
0030Channelizing device- pedestrian LCD (longitudinal channelizing device) (0102-74-8)FD4,110$0.50$0.21
0035Arrow board / advance warning arrow panel (0102-76)ED198$20.00$16.05
0040Portable changeable message sign, temporary (0102-99)ED471$55.00$26.75
0045Temporary signalization and maintenance, intersection (0102-104)ED150$10.00$31.29
0050Temporary traffic detection and maintenance, intersection (0102-107-1)ED150$10.00$31.29
0055Type III barricade (0102-115)ED303$10.00$0.81
0060Sediment barrier (0104-10-3)LF286$10.00$3.17
0065Inlet protection system (0104-18)EACH1$300.00$268.55
0070Litter removal (0107-1)ACRE0.75$1,000.00$109.99
0075Mowing (0107-2)ACRE0.11$1,000.00$181.10
0080Monitor existing structures- inspection and settlement monitoring (0108-1)LS1$12,000$5,006.09
0085Monitor existing structures- vibration monitoring (0108-2)LS1$16,500$5,006.09
0090Clearing & grubbing (0110-1-1)ACRE1$15,300$12,216
0095Removal of existing concrete (0110-4-10)SY299$170.00$174.36
0100Borrow excavation, truck measure (0120-2-2)CY96.20$180.00$131.04
0105Optional base, base group 09 (0285-709)SY9$1,200.00$889.17
0110Superpave asphaltic concrete, traffic B, PG76-22 (0334-1-52)TN0.70$13,000$9,566.92
0115Asphalt concrete friction course,traffic B, FC-12.5, PG (0337-7-81)TN0.70$13,000$9,700.63
0120Inlets, curb, type J-5, partial (0425-1455)EACH1$42,500$29,895
0125Concrete curb & gutter, type F (0520-1-10)LF362$170.00$124.35
0130Concrete sidewalk and driveways, 4" thick (0522-1)SY157$277.00$205.92
0135Concrete sidewalk and driveways, 6" thick (0522-2)SY95$437.00$324.92
0140Detectable warnings (0527-2)SF85$55.00$102.96
0145Performance turf, sod (0570-1-2)SY174$20.00$33.23
0150Initial contingency amount, DO not bid (0999-25)LS1$50,000$50,000
0155Single column ground sign assembly, F&I ground mount, 20.0 SF (0700-1112)EACH1$1,000.00$2,461.27
0160Painted pavement markings, durable paint, yellow, island nose (0710-12290)SF5$27.00$66.86
0165Thermoplastic, standard, solid, 12" for crosswalk and roundabout (0711-11123)LF588$10.00$10.70
0170Thermoplastic, standard, yellow, 2-4 dotted guide line dotted extension line, 6" (0711-11241)GM0.02$45,000$26,743
0175Thermoplastic, preformed, white, solid, 24" for crosswalk (0711-14125)LF490$25.00$26.75
0180Thermoplastic, standard-other surfaces, white, solid, 6" (0711-16101)GM0.03$45,000$26,742
0185Thermoplastic, remove existing thermoplastic pavement markings- surface to remain (0711-17-1)SF613$10.00$6.69
0190Conduit, furnish & install, open trench (0630-2-11)LF107$15.00$30.33
0195Conduit, furnish & install, directional bore (0630-2-12)LF165$40.00$100.79
0200Signal cable- new or reconstructed intersection, furnish & install (0632-7-1)PI1$10,000$11,315
0205Fiber optic cable locator (0633-6)DA150$110.00$75.22
0210Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH1$1,500.00$5,385.32
0215Aluminum signals pole, (0646-1-11)EACH7$4,000.00$3,284.01
0220Aluminum signals pole, remove (0646-1-60)EACH4$200.00$625.77
0225Steel mast arm assembly, and install, single arm 60' (0649-21-10)EACH1$113,000$101,665
0230Steel mast arm assembly, and install, single arm 70' (0649-21-15)EACH1$115,000$115,537
0235Steel mast arm assembly, and install, double arm 78'-50' (0649-21-24)EACH1$160,000$148,086
0240Steel mast arm assembly, remove, shallow foundation- bolt on attachment (0649-26-3)EACH3$7,500.00$5,475.41
0245Vehicular traffic signal, furnish & install 3 section, 1 way (0650-1-34)AS8$2,000.00$1,768.28
0250Vehicular traffic signal, furnish & install 4 section, 1 way (0650-1-36)AS4$2,500.00$2,208.95
0255Pedestrian signal, furnish & install LED countdown, 1 way (0653-1-11)AS6$1,200.00$1,152.57
0260Pedestrian signal, furnish & install LED countdown, 2 ways (0653-1-12)AS1$2,500.00$2,196.50
0265Vehicle detection system- relocate above ground equipment (0660-4-42)EACH1$1,500.00$4,014.06
0270Pedestrian detector, relocate (0665-1-40)EACH8$500.00$353.12
0275Internally illuminated sign, furnish & install, overhead mount, 12-18 SF (0700-5-22)EACH4$5,200.00$5,214.25
FDOT contract T3963: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of April 30, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy