FDOT contract T5858 bid tabulation

SR 528, SR 404, SR 520 AND US 192 AT VARIOUS BRIDGES... Let by Florida DOT on March 26, 2025, Brevard, District 5. 5 bids received; low bid $948,635 by Premier Paving, LLC.

Owner
Florida DOT
Letting
26 MAR 2025
Pay items
28
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Premier Paving, LLC$948,635Low
2Collins Land Services, Inc$1,711,328+80%
3Maer Homes, LLC$1,831,116+93%
4Atlantic Civil Constructors Corp$2,238,240+136%
5Southern Road & Bridge, LLC$2,436,498+157%
FDOT contract T5858: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Premier Paving, LLC2. Collins Land Services, Inc3. Maer Homes, LLC4. Atlantic Civil Constructors Corp5. Southern Road & Bridge, LLC
0005Mobilization (0101-1)LS1$10,000$35,000$12,500$53,288$45,000
0010Mobilization (0101-1)LS1$10,000$35,000$15,000$53,288$45,000
0015Mobilization (0101-1)LS1$10,000$35,000$6,800.00$53,288$45,000
0020Mobilization (0101-1)LS1$10,000$35,000$95,000$53,288$45,000
0025Mobilization (0101-1)LS1$10,000$35,000$18,000$53,288$45,000
0030Maintenance of traffic (0102-1)DA1$5,000.00$35,000$10,000$37,618$40,000
0035Maintenance of traffic (0102-1)DA1$5,000.00$35,000$15,000$37,618$40,000
0040Maintenance of traffic (0102-1)DA1$5,000.00$35,000$6,500.00$37,618$40,000
0045Maintenance of traffic (0102-1)DA1$5,000.00$35,000$45,000$37,618$40,000
0050Maintenance of traffic (0102-1)DA1$5,000.00$35,000$20,000$37,618$40,000
0055Floating turbidity barrier (0104-11)LF3,983$12.00$15.00$18.00$20.22$11.00
0060Clearing & grubbing (0110-1-1)ACRE1$30,000$35,000$11,500$33,748$32,500
0065Clearing & grubbing (0110-1-1)ACRE1$30,000$35,000$12,500$33,748$25,000
0070Clearing & grubbing (0110-1-1)ACRE1$30,000$35,000$8,500.00$33,748$32,500
0075Clearing & grubbing (0110-1-1)ACRE1$30,000$35,000$169,485$72,566$25,000
0080Clearing & grubbing (0110-1-1)ACRE1$30,000$35,000$15,000$45,964$32,500
0085Embankment (0120-6)CY2,768.90$30.00$25.00$35.00$98.04$68.00
0090Flowable fill (0121-70)CY8.30$1,000.00$500.00$400.00$695.86$1,500.00
0095Concrete sidewalk and driveways, 6" thick (0522-2)SY71$125.00$100.00$125.00$135.89$125.00
0100Riprap, sand-cement bags (0530-1100)CY187$95.00$1,000.00$1,650.00$1,496.55$1,565.00
0105Riprap- rubble, bank and shore (0530-3-3)TN2,302.60$120.00$200.00$205.00$183.56$225.00
0110Bedding stone (0530-74)TN2,120.40$87.00$150.00$158.00$161.13$333.00
0115Performance turf, sod (0570-1-2)SY6,606$7.50$5.00$4.00$15.87$7.00
0120Initial contingency amount, DO not bid (0999-25)LS1$1,000.00$1,000.00$1,000.00$1,000.00$1,000.00
0125Initial contingency amount, DO not bid (0999-25)LS1$2,000.00$2,000.00$2,000.00$2,000.00$2,000.00
0130Initial contingency amount, DO not bid (0999-25)LS1$500.00$500.00$500.00$500.00$500.00
0135Initial contingency amount, DO not bid (0999-25)LS1$40,000$40,000$40,000$40,000$40,000
0140Initial contingency amount, DO not bid (0999-25)LS1$4,000.00$4,000.00$4,000.00$4,000.00$4,000.00
FDOT contract T5858: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy