FDOT contract T5858 bid tabulation
SR 528, SR 404, SR 520 AND US 192 AT VARIOUS BRIDGES... Let by Florida DOT on March 26, 2025, Brevard, District 5. 5 bids received; low bid $948,635 by Premier Paving, LLC.
- Owner
- Florida DOT
- Letting
- 26 MAR 2025
- Pay items
- 28
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Premier Paving, LLC | $948,635 | Low |
| 2 | Collins Land Services, Inc | $1,711,328 | +80% |
| 3 | Maer Homes, LLC | $1,831,116 | +93% |
| 4 | Atlantic Civil Constructors Corp | $2,238,240 | +136% |
| 5 | Southern Road & Bridge, LLC | $2,436,498 | +157% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Premier Paving, LLC | 2. Collins Land Services, Inc | 3. Maer Homes, LLC | 4. Atlantic Civil Constructors Corp | 5. Southern Road & Bridge, LLC |
|---|---|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $10,000 | $35,000 | $12,500 | $53,288 | $45,000 |
| 0010 | Mobilization (0101-1) | LS | 1 | $10,000 | $35,000 | $15,000 | $53,288 | $45,000 |
| 0015 | Mobilization (0101-1) | LS | 1 | $10,000 | $35,000 | $6,800.00 | $53,288 | $45,000 |
| 0020 | Mobilization (0101-1) | LS | 1 | $10,000 | $35,000 | $95,000 | $53,288 | $45,000 |
| 0025 | Mobilization (0101-1) | LS | 1 | $10,000 | $35,000 | $18,000 | $53,288 | $45,000 |
| 0030 | Maintenance of traffic (0102-1) | DA | 1 | $5,000.00 | $35,000 | $10,000 | $37,618 | $40,000 |
| 0035 | Maintenance of traffic (0102-1) | DA | 1 | $5,000.00 | $35,000 | $15,000 | $37,618 | $40,000 |
| 0040 | Maintenance of traffic (0102-1) | DA | 1 | $5,000.00 | $35,000 | $6,500.00 | $37,618 | $40,000 |
| 0045 | Maintenance of traffic (0102-1) | DA | 1 | $5,000.00 | $35,000 | $45,000 | $37,618 | $40,000 |
| 0050 | Maintenance of traffic (0102-1) | DA | 1 | $5,000.00 | $35,000 | $20,000 | $37,618 | $40,000 |
| 0055 | Floating turbidity barrier (0104-11) | LF | 3,983 | $12.00 | $15.00 | $18.00 | $20.22 | $11.00 |
| 0060 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $30,000 | $35,000 | $11,500 | $33,748 | $32,500 |
| 0065 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $30,000 | $35,000 | $12,500 | $33,748 | $25,000 |
| 0070 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $30,000 | $35,000 | $8,500.00 | $33,748 | $32,500 |
| 0075 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $30,000 | $35,000 | $169,485 | $72,566 | $25,000 |
| 0080 | Clearing & grubbing (0110-1-1) | ACRE | 1 | $30,000 | $35,000 | $15,000 | $45,964 | $32,500 |
| 0085 | Embankment (0120-6) | CY | 2,768.90 | $30.00 | $25.00 | $35.00 | $98.04 | $68.00 |
| 0090 | Flowable fill (0121-70) | CY | 8.30 | $1,000.00 | $500.00 | $400.00 | $695.86 | $1,500.00 |
| 0095 | Concrete sidewalk and driveways, 6" thick (0522-2) | SY | 71 | $125.00 | $100.00 | $125.00 | $135.89 | $125.00 |
| 0100 | Riprap, sand-cement bags (0530-1100) | CY | 187 | $95.00 | $1,000.00 | $1,650.00 | $1,496.55 | $1,565.00 |
| 0105 | Riprap- rubble, bank and shore (0530-3-3) | TN | 2,302.60 | $120.00 | $200.00 | $205.00 | $183.56 | $225.00 |
| 0110 | Bedding stone (0530-74) | TN | 2,120.40 | $87.00 | $150.00 | $158.00 | $161.13 | $333.00 |
| 0115 | Performance turf, sod (0570-1-2) | SY | 6,606 | $7.50 | $5.00 | $4.00 | $15.87 | $7.00 |
| 0120 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 | $1,000.00 |
| 0125 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 | $2,000.00 |
| 0130 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $500.00 | $500.00 | $500.00 | $500.00 | $500.00 |
| 0135 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $40,000 | $40,000 | $40,000 | $40,000 | $40,000 |
| 0140 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 | $4,000.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of March 26, 2025. Compiled by Mirage Metrics.