SR 5 (US17) AT YULEE WEIGH STATION. Let by Florida DOT on January 29, 2025, Nassau, StateWide. 3 bids received; low bid $393,754 by Chinchor Electric Inc..

Owner
Florida DOT
Letting
29 JAN 2025
Pay items
22
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Chinchor Electric Inc.$393,754Low
2Traffic Control Devices, Inc.$555,555+41%
3New Era Electric Inc$561,753+43%
FDOT contract T9044: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Chinchor Electric Inc.2. Traffic Control Devices, Inc.3. New Era Electric Inc
0005Mobilization (0101-1)LS1$40,534$52,000$50,000
0010Maintenance of traffic (0102-1)DA1$7,150.00$3,240.00$58,000
0015Work zone sign (0102-60)ED840$0.39$0.50$0.30
0020Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED8,040$0.15$0.25$0.15
0025Type III barricade (0102-115)ED600$0.28$1.00$0.35
0030Sediment barrier (0104-10-3)LF277$4.40$10.00$4.70
0035Inlet protection system (0104-18)EACH2$275.00$284.00$250.00
0040Litter removal (0107-1)ACRE16.96$275.00$320.00$350.00
0045Mowing (0107-2)ACRE10.04$165.00$1,920.00$350.00
0050Concrete sidewalk and driveways, 4" thick (0522-1)SY35$165.00$375.00$59.85
0055Initial contingency amount, DO not bid (0999-25)LS1$22,100$22,100$22,100
0060Conduit, furnish & install, open trench (0630-2-11)LF2,202$10.62$23.00$19.20
0065Conduit, furnish & install, directional bore (0630-2-12)LF219$17.55$21.00$39.95
0070Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH21$1,967.30$2,703.00$1,718.40
0075Electrical power service- transformer, F&I, 16-25 kva, single phase, copper windings (0639-6141)EACH1$4,628.25$6,015.00$11,741
0080Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF12,512$2.10$2.50$2.55
0085Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF7,905$0.55$1.00$0.95
0090Load center, F&I, secondary voltage (0715-7-11)EACH1$14,702$28,420$20,963
0095Load center, remove, voltage (0715-7-41)EACH1$1,760.00$1,500.00$1,042.10
0100Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 0' arm length (0715-61500)EACH17$9,286.82$11,960$11,418
0105Light pole complete, remove pole and foundation (0715-69000)EACH19$1,100.00$1,555.00$2,500.00
0110Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH17$551.38$825.00$867.95
FDOT contract T9044: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy