FDOT contract T9044 bid tabulation
SR 5 (US17) AT YULEE WEIGH STATION. Let by Florida DOT on January 29, 2025, Nassau, StateWide. 3 bids received; low bid $393,754 by Chinchor Electric Inc..
- Owner
- Florida DOT
- Letting
- 29 JAN 2025
- Pay items
- 22
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Chinchor Electric Inc. | $393,754 | Low |
| 2 | Traffic Control Devices, Inc. | $555,555 | +41% |
| 3 | New Era Electric Inc | $561,753 | +43% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Chinchor Electric Inc. | 2. Traffic Control Devices, Inc. | 3. New Era Electric Inc |
|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $40,534 | $52,000 | $50,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $7,150.00 | $3,240.00 | $58,000 |
| 0015 | Work zone sign (0102-60) | ED | 840 | $0.39 | $0.50 | $0.30 |
| 0020 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 8,040 | $0.15 | $0.25 | $0.15 |
| 0025 | Type III barricade (0102-115) | ED | 600 | $0.28 | $1.00 | $0.35 |
| 0030 | Sediment barrier (0104-10-3) | LF | 277 | $4.40 | $10.00 | $4.70 |
| 0035 | Inlet protection system (0104-18) | EACH | 2 | $275.00 | $284.00 | $250.00 |
| 0040 | Litter removal (0107-1) | ACRE | 16.96 | $275.00 | $320.00 | $350.00 |
| 0045 | Mowing (0107-2) | ACRE | 10.04 | $165.00 | $1,920.00 | $350.00 |
| 0050 | Concrete sidewalk and driveways, 4" thick (0522-1) | SY | 35 | $165.00 | $375.00 | $59.85 |
| 0055 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $22,100 | $22,100 | $22,100 |
| 0060 | Conduit, furnish & install, open trench (0630-2-11) | LF | 2,202 | $10.62 | $23.00 | $19.20 |
| 0065 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 219 | $17.55 | $21.00 | $39.95 |
| 0070 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 21 | $1,967.30 | $2,703.00 | $1,718.40 |
| 0075 | Electrical power service- transformer, F&I, 16-25 kva, single phase, copper windings (0639-6141) | EACH | 1 | $4,628.25 | $6,015.00 | $11,741 |
| 0080 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 12,512 | $2.10 | $2.50 | $2.55 |
| 0085 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 7,905 | $0.55 | $1.00 | $0.95 |
| 0090 | Load center, F&I, secondary voltage (0715-7-11) | EACH | 1 | $14,702 | $28,420 | $20,963 |
| 0095 | Load center, remove, voltage (0715-7-41) | EACH | 1 | $1,760.00 | $1,500.00 | $1,042.10 |
| 0100 | Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 0' arm length (0715-61500) | EACH | 17 | $9,286.82 | $11,960 | $11,418 |
| 0105 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 19 | $1,100.00 | $1,555.00 | $2,500.00 |
| 0110 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 17 | $551.38 | $825.00 | $867.95 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.