FDOT contract T9045 bid tabulation

SR 10 (US 90) AT PENSACOLA WEIGH STATION. Let by Florida DOT on January 29, 2025, Escambia, StateWide. 3 bids received; low bid $511,934 by Bill Smith Electric.

Owner
Florida DOT
Letting
29 JAN 2025
Pay items
18
Data through
28 OCT 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Bill Smith Electric$511,934Low
2Ingram Signalization, Inc.$556,753+9.0%
3New Era Electric Inc$670,376+31%
FDOT contract T9045: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Bill Smith Electric2. Ingram Signalization, Inc.3. New Era Electric Inc
0005Mobilization (0101-1)LS1$25,000$32,000$60,000
0010Maintenance of traffic (0102-1)DA1$2,500.00$5,000.00$40,000
0015Work zone sign (0102-60)ED1,260$3.08$2.00$2.00
0020Channelizing device- types I, II, VP, drum, or LCD (0102-74-1)ED11,520$0.47$1.00$0.20
0025Type III barricade (0102-115)ED900$3.00$2.00$0.55
0030Sediment barrier (0104-10-3)LF728$8.47$6.00$5.00
0035Inlet protection system (0104-18)EACH3$1,165.00$500.00$322.05
0040Litter removal (0107-1)ACRE29.60$116.82$100.00$72.95
0045Mowing (0107-2)ACRE20.36$158.55$100.00$104.45
0050Initial contingency amount, DO not bid (0999-25)LS1$22,600$22,600$22,600
0055Conduit, furnish & install, open trench (0630-2-11)LF2,694$11.41$12.00$26.00
0060Conduit, furnish & install, directional bore (0630-2-12)LF339$61.78$30.00$50.00
0065Pull & splice box, F&I, 13" X 24" cover size (0635-2-11)EACH28$1,084.00$1,300.00$1,950.00
0070Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12)LF10,435$1.62$4.80$4.50
0075Lighting conductors, remove & dispose, contractor owns (0715-1-60)LF20,463$0.27$1.00$1.00
0080Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 0' arm length (0715-61500)EACH20$12,692$14,100$12,000
0085Light pole complete, remove pole and foundation (0715-69000)EACH23$933.40$1,000.00$2,850.00
0090Pole cable distribution system, furnish and install, conventional (0715-500-1)EACH20$2,686.00$800.00$950.00
FDOT contract T9045: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.

Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy