FDOT contract T9045 bid tabulation
SR 10 (US 90) AT PENSACOLA WEIGH STATION. Let by Florida DOT on January 29, 2025, Escambia, StateWide. 3 bids received; low bid $511,934 by Bill Smith Electric.
- Owner
- Florida DOT
- Letting
- 29 JAN 2025
- Pay items
- 18
- Data through
- 28 OCT 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid |
|---|---|---|---|
| 1 | Bill Smith Electric | $511,934 | Low |
| 2 | Ingram Signalization, Inc. | $556,753 | +9.0% |
| 3 | New Era Electric Inc | $670,376 | +31% |
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Bill Smith Electric | 2. Ingram Signalization, Inc. | 3. New Era Electric Inc |
|---|---|---|---|---|---|---|
| 0005 | Mobilization (0101-1) | LS | 1 | $25,000 | $32,000 | $60,000 |
| 0010 | Maintenance of traffic (0102-1) | DA | 1 | $2,500.00 | $5,000.00 | $40,000 |
| 0015 | Work zone sign (0102-60) | ED | 1,260 | $3.08 | $2.00 | $2.00 |
| 0020 | Channelizing device- types I, II, VP, drum, or LCD (0102-74-1) | ED | 11,520 | $0.47 | $1.00 | $0.20 |
| 0025 | Type III barricade (0102-115) | ED | 900 | $3.00 | $2.00 | $0.55 |
| 0030 | Sediment barrier (0104-10-3) | LF | 728 | $8.47 | $6.00 | $5.00 |
| 0035 | Inlet protection system (0104-18) | EACH | 3 | $1,165.00 | $500.00 | $322.05 |
| 0040 | Litter removal (0107-1) | ACRE | 29.60 | $116.82 | $100.00 | $72.95 |
| 0045 | Mowing (0107-2) | ACRE | 20.36 | $158.55 | $100.00 | $104.45 |
| 0050 | Initial contingency amount, DO not bid (0999-25) | LS | 1 | $22,600 | $22,600 | $22,600 |
| 0055 | Conduit, furnish & install, open trench (0630-2-11) | LF | 2,694 | $11.41 | $12.00 | $26.00 |
| 0060 | Conduit, furnish & install, directional bore (0630-2-12) | LF | 339 | $61.78 | $30.00 | $50.00 |
| 0065 | Pull & splice box, F&I, 13" X 24" cover size (0635-2-11) | EACH | 28 | $1,084.00 | $1,300.00 | $1,950.00 |
| 0070 | Lighting conductors, F&I, insulated, no.8 - 6 (0715-1-12) | LF | 10,435 | $1.62 | $4.80 | $4.50 |
| 0075 | Lighting conductors, remove & dispose, contractor owns (0715-1-60) | LF | 20,463 | $0.27 | $1.00 | $1.00 |
| 0080 | Light pole complete, F&I, standard pole standard foundation, 50' mounting height, 0' arm length (0715-61500) | EACH | 20 | $12,692 | $14,100 | $12,000 |
| 0085 | Light pole complete, remove pole and foundation (0715-69000) | EACH | 23 | $933.40 | $1,000.00 | $2,850.00 |
| 0090 | Pole cable distribution system, furnish and install, conventional (0715-500-1) | EACH | 20 | $2,686.00 | $800.00 | $950.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from FDOT's tabulation for this contract. FDOT Tabulation of Bids PDFs from its central office lettings, January 2018 to October 2026, all pay items. On A+B contracts the cost part is kept (the total the pay items add up to). Bidders listed without a rank or total are left out.
Every contract let that day: FDOT letting of January 29, 2025. Compiled by Mirage Metrics.