IDOT contract 61K92 bid tabulation

Project Number: Cugb-890 / /, section 18-00481-00-BR. Let by Illinois DOT on January 17, 2025, Mchenry, District 01. 5 bids received; low bid $2,789,285 by Dunnet Bay Construction Company.

Owner
Illinois DOT
Letting
17 JAN 2025
Pay items
61
Data through
18 SEP 2026

Bidders

RankBidderTotal bidAgainst the low bid
1Dunnet Bay Construction Company$2,789,285Low
2Copenhaver Construction, Inc.$2,893,292+4.0%
3Martam Construction Incorporated$3,160,905+13%
4Sjostrom & Sons, Inc.$3,271,830+17%
5Alliance Contractors, Inc.$3,943,520+41%
IDOT contract 61K92: bids by rank

Bid tabulation

LinePay itemUnitQuantity1. Dunnet Bay Construction Company2. Copenhaver Construction, Inc.3. Martam Construction Incorporated4. Sjostrom & Sons, Inc.5. Alliance Contractors, Inc.
1Outfall structure (XX007061)EACH2$5,000.00$3,500.00$82,000$5,000.00$3,600.00
2Washout basin (X0326806)LS1$2,500.00$1,600.00$3,500.00$4,500.00$750.00
3Eros cont blanket SPL (X2511630)SY6,941$1.60$2.00$1.80$1.60$1.50
4Dewatering (X5021507)LS1$25,000$10,000$60,000$50,000$1.00
5Cofferdam typ 1 IS WW (X5021512)EACH2$1.00$15,000$28,000$260,000$1.00
63-sided PCC STR 54 SP (X5042254)LF86$16,250$14,000$14,600$12,000$26,235
7Memb WTRPRF sys B STR (X5810103)SY564.50$50.00$77.00$36.00$60.00$50.00
8Engr FLD off A mod (X6700405)CAL MO12$3,500.00$1,500.00$3,200.00$3,000.00$250.00
9Traf cont & prot SPL (X7010216)LS1$15,000$89,000$147,000$25,000$14,000
10Asb bearing pad remov (Z0001900)EACH9$500.00$500.00$125.00$150.00$250.00
11Stab constr entrance (Z0013797)SY244$0.01$10.00$36.00$60.00$1.00
12Construction layout (Z0013798)LS1$18,000$19,000$67,300$25,000$8,500.00
13Temp info signing (Z0030850)SF241$16.00$20.00$18.00$13.00$13.00
14Earth excavation (20200100)CY190$150.00$45.00$45.00$40.00$10.00
15Rem & disp uns matl (20201200)CY2,210$37.00$37.00$45.00$40.00$15.00
16Channel excavation (20300100)CY920$56.00$60.00$63.00$40.00$1.00
17Furnished excavation (20400800)CY1,965$39.10$0.01$23.00$40.00$5.00
18Porous gran embank (20700220)CY162$79.00$50.00$56.00$85.00$65.00
19Geotech fab F/GR stab (21001000)SY2,217$2.50$3.00$2.00$3.00$3.00
20Topsoil exc & plac (21101505)CY875$27.33$10.00$27.00$30.00$20.00
21Topsoil F & P 6 (21101625)SY360$9.00$9.00$12.00$25.00$10.00
22Seeding CL 2A (25000210)ACRE0.25$2,383.00$4,000.00$2,600.00$2,400.00$5,500.00
23Seeding CL 4A (25000312)ACRE1.25$2,233.00$5,000.00$2,500.00$2,400.00$5,000.00
24Seeding CL 4B (25000314)ACRE0.50$3,471.00$7,000.00$3,800.00$2,500.00$7,000.00
25Nitrogen fert nutr (25000400)LB16$3.00$1.00$4.00$3.00$3.00
26Potassium fert nutr (25000600)LB16$3.00$1.00$4.00$3.00$3.00
27Temp eros contr seed (28000250)LB600$3.00$0.01$4.00$3.00$3.00
28Temp ditch checks (28000305)LF182$3.80$15.00$4.00$4.00$10.00
29Perimeter eros bar (28000400)LF2,482$1.90$3.00$2.00$3.00$3.00
30Temp eros contr blank (28001100)SY22,431$0.90$1.00$1.00$0.90$0.01
31Stone riprap CL A3 (28100105)SY88$91.00$150.00$132.00$65.00$140.00
32Filter fabric (28200200)SY897$7.00$4.00$3.00$5.00$1.00
33Articul block rev mat (28500400)SY809$241.00$405.00$265.00$250.00$445.00
34Agg subgrade improve (30300001)CY930$50.00$49.00$54.00$65.00$75.00
35Agg subgrade impr 12 (30300112)SY2,563$26.33$17.00$16.00$25.00$25.00
36Bit matls PR CT (40600275)LB5,153$0.01$0.10$0.10$0.01$0.10
37Bit matls tack CT (40600290)LB2,199$0.01$0.10$0.10$0.01$0.10
38Long joint sealant (40600370)LF1,350$11.57$14.00$12.00$12.00$12.00
39HMA surf rem butt JT (40600982)SY12$1.00$120.00$1.00$1.00$112.40
40HMA BC IL-9.5 N50 (40602978)TON12$131.00$750.00$150.00$135.00$508.00
41HMA BC IL-19.0 N50 (40603080)TON9$152.00$750.00$170.00$155.00$385.00
42HMA SC IL-9.5 D N50 (40604060)TON19$103.00$950.00$120.00$105.00$457.00
43HMA pavt FD 8 (40701841)SY1,430$49.00$75.00$52.00$50.00$37.00
44Pavement rem (44000100)SY1,479$17.00$19.00$16.00$15.00$20.00
45HMA surf rem 3 1/2 (44000163)SY165$34.00$107.00$37.00$34.00$29.00
46HMA shoulders 8 (48203029)SY860$35.00$89.00$38.00$35.00$38.00
47Rem exist struct (50100100)EACH1$50,000$152,000$140,000$190,650$474,500
48Cofferdam excavation (50200300)CY1,034$52.00$20.00$63.00$40.00$1.00
49Rem/disp uns matl-STR (50200450)CY22$100.00$55.00$96.00$85.00$1.00
50Name plates (51500100)EACH1$850.00$1,200.00$1,200.00$1,000.00$1,000.00
51Granular backfill STR (58600101)CY1,119$56.00$55.00$58.00$75.00$1.00
52Conc HDWL for P drain (60100060)EACH8$700.00$800.00$550.00$800.00$850.00
53Pipe underdrain 4 SP (60108100)LF286$38.00$30.00$32.00$40.00$40.00
54Pipe underdr T 2 4 (60108204)LF1,392$33.50$19.00$23.00$40.00$40.00
55Guardrail remov (63200310)LF486$0.01$10.00$10.00$10.00$15.00
56Fur erect row markers (66600105)EACH13$825.00$500.00$900.00$650.00$1,500.00
57Mobilization (67100100)LS1$167,357$189,000$186,000$281,000$236,000
58Changeable message SN (70107025)CAL DAY270$30.00$45.00$33.00$30.00$30.00
59Pref PL PM TD STD L4 (78004620)LF2,580$7.25$5.00$8.00$6.00$4.50
60GRV RCSD PVT MRKG 5 (78011025)LF2,580$0.95$3.00$1.00$2.00$1.95
61Raised ref PVT MK rem (78300200)EACH7$25.00$100.00$30.00$1.00$50.00
IDOT contract 61K92: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from IDOT's tabulation for this contract. IDOT Unit Price Tabulation of Bids reports for every letting from January 2021 to September 2026 posted on IDOT's letting site. Contracts with alternate bid groups are left out, and so are bids that did not match their published total.

Every contract let that day: IDOT letting of January 17, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy